JAFP-21-0083, Notification of Readiness for NRC 95001 Inspection

From kanterella
Jump to navigation Jump to search
Notification of Readiness for NRC 95001 Inspection
ML21252A737
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/09/2021
From: Timothy Peter
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-20-138, JAFP-21-0083
Download: ML21252A737 (2)


Text

Exelon Generation . James A. FitzPatrick NPP P 0 Box 110 Lycoming . NY 13093 Timothy C. Peter Site Vice President - JAF EA-20-138 JAFP-21-0083 September 9, 2021 U.S. Nuclear Regulatory Commission A TIN: Document Control Desk Washington , DC 20555 James A. FitzPatrick Nuclear Power Plant Renewed Facility Operating License No. DPR-059 NRC Docket No. 50-333

Subject:

Notification of Readiness for NRC 95001 Inspection

References:

1. NRC letter, Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation, ML21105A543, dated April 20, 2021
2. NRC letter, Response to Contested Violation and Final White Finding and Revised Notice of Violation, ML21244A497, dated September 3, 2021

Dear Sir or Madam :

On April 20, 2021 , the NRC gave Notice to James A. FitzPatrick Nuclear Power Plant (JAF) of an escalated enforcement action, EA-20-138, associated with a White Finding,05000333/2020012-01, Defective Part Results in High Pressure Coolant System Pressure Control Valve Failure. On September 3, 2021, the NRC provided a final White Finding and revised notice of violation.

The NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001 , "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area" following notification of readiness for a supplemental inspection. This letter notifies the NRC that FitzPatrick is ready for the supplemental inspection.

There are no new regulatory commitments contained in this letter. If you should have any questions, please contact Mr. Richard M. Sullivan, Regulatory Assurance Manager, at 315-349-6262.

Very t~...e__..

~~Geter Site Vice President TCP/RMS cc next page

JAFP-21-0083 Page 2 of 2 cc: USNRC Document Control Desk USNRC Region I Regional Administrator USNRC Resident Inspector USNRC NRC Project Manager