Information Notice 2006-05, Possible Defect in Bussman KWN-R and KTN-R Fuses

From kanterella
(Redirected from Information Notice 2006-05)
Jump to navigation Jump to search
Possible Defect in Bussman KWN-R and KTN-R Fuses
ML060330540
Person / Time
Issue date: 03/03/2006
From: Charemagne Grimes
NRC/NRR/ADRA/DPR
To:
Tabatabai O, NRR/DIRS/IOEB, 415-6616
References
IN-06-005
Download: ML060330540 (5)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555-0001 March 3, 2006 NRC INFORMATION NOTICE 2006-05: POSSIBLE DEFECT IN BUSSMANN KWN-R AND

KTN-R FUSES

ADDRESSEES

All holders of operating licensees for nuclear power reactors, except those who have

permanently ceased operations and have certified that fuel has been permanently removed

from the reactor vessel.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to inform

addressees of a possible defect in Bussmann KWN-R and KTN-R fuses. Recipients are

expected to review the information for applicability to their facilities and consider actions to

avoid similar problems. However, the suggestions in this information notice are not NRC

requirements; therefore, no specific action or written response is required.

DESCRIPTION OF CIRCUMSTANCES

A customer of Wyle Laboratories reported that a KWN-R fuse lost its electrical continuity while

in service. The customer cut the fuse open and found the fuse element intact and a lack of

electrical continuity across the soldered connection of the element to the rejection ferrule of the

fuse. According to the customer, the fuse had been in service from March 31, 2005 to

August 4, 2005, carrying 2 to 3 amperes, and there had been no overcurrent events to cause

the fuse to open. The customer returned the fuse to Wyle for failure analysis. Wyle forwarded

the fuse to Bussmann (the fuse manufacturer) for evaluation. Bussmann found a poor solder

connection on the rejection cap. Apparently the cap did not get hot enough to reflow solder

during the manufacturing process. Bussmann stated that the issue might extend to other fuses

due to a manufacturing process problem.

Wyle Laboratories indicated to the NRC that the only two nuclear power plants that purchased

the susceptible KWN-R fuses from Wyle are Hatch Electric Generating Plant and Pilgrim

Nuclear Power Station. Wyle has contacted the two customers that have purchased KWN-R

fuses from Wyle Laboratories. Since these fuses might have been sold to other nuclear power

plants by different vendors, this problem may be generic. Some nuclear power plants have

contacted Bussmann and Wyle with inquiries since a Part 21 report was posted on the NRC

Web-site.

DISCUSSION

The only KWN-R fuses affected are fuses rated less than or equal to 30 amperes. To date, poor solder joints have been found in 3, 6, and 10 ampere KWN-R fuses with date codes L05, M37, and M17. Poor solder connections have also been found in fuses with date codes

L11, L19, M07, M20, and M40. KTN-R fuses with ratings less than or equal to 30 amperes

were later added to the potentially defective fuse list since these fuses are manufactured using

the same process as the KWN-R fuses. Poor solder connections have been found in 3, 4, 5, and 15 amperes KTN-R fuses of 1987-1991 vintage (there are no date codes on these fuses).

On one KWN-R-10 fuse that was in service, Bussmann found no solder connection on the

rejection cap. It appeared the cap did not get hot enough to reflow the solder to the tab on the

element. There were no signs of solder on the connecting tab of the bridge/element assembly.

The lack of solder and corrosion in the cap caused an open circuit condition. Bussmann

identified that the manufacturers personnel have failed to follow process instruction. They are

supposed to pull on the bridge assembly of every fuse to determine that a junction has been

obtained between the bridge tab and cap. The design of the bridge and cap attachment is

common to the KWN-R and KTN-R fuses rated at 1 through 30 amperes.

Bussmann has taken corrective actions to prevent the potential defect in these fuses. It has

added a mechanical test to the KWN-R and KTN-R manufacturing process. The test consists

of checking the resistance of each fuse and then mechanically impacting it and checking the

resistance again. If the resistance readings differ, the fuse is segregated for disposition. The

mechanical impact is produced by dropping the fuse at least 3 feet (93 centimeter) onto the

plain cap end through a tube with an internal diameter of about 5/8 inch (1.6 centimeters).

Bussmann also tests each production lot at 110 percent of the rated current for the KWN-R

product.

As a screening test to ensure a good solder connection, the manufacturer recommends

performing a current-carrying test for 30 minutes at 110 percent of the rated current after warm

up at 100 percent of the rated current. This will avoid blowing the fuse. When performing the

mechanical impact test, if the resistance readings differ by more than +/- 10 percent or fall

outside the manufacturers specifications, the fuse should be rejected. Only KWN-R and KTN-

R fuses that pass the mechanical impact test and the 110 percent current-carrying capacity test

are qualified.

CONTACT

This information notice requires no specific action or written response. Please direct any

questions about this matter to the technical contact listed below or the appropriate Office of

Nuclear Reactor Regulation (NRR) project manager.

/RA/

Christopher I. Grimes, Director

Division of Policy and Rulemaking

Office of Nuclear Reactor Regulation

Technical Contact:

Duc Nguyen, NRR/DE/EEEB

301-415-3202 E-mail: dtn1@nrc.gov

Omid Tabatabai, NRR/DIRS/IOEB

301-415-6616 E-mail: oty@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under Electronic Reading Room/Document Collections.

ML060330540 *previous concurrence

OFFICE NRR/DE/EEEB Tech Editor BC/DE/EEEB NRR/DIRS/IOEB TL:NRR/DIRS/IQEB

NAME DNguyen* PKleene* EABrown* OTabatabai* EJBenner*

DATE 02/08/2006 02/06/2006 02/09/2006 02/13/2006 02/13/2006 OFFICE DPR:PGCB:LA DPR:PGCB DPR:PGCB:BC DPR:D

NAME CHawes* DBeaulieu* CJackson* CIGrimes*

DATE 02/02/2006 02/28/2006 03/03/2006 03/03/2006