IR 05000461/2019011

From kanterella
Jump to navigation Jump to search
Design Bases Assurance Inspection (Team); Inspection Report 05000461/2019011 (DRS-J.Benjamin)
ML19128A329
Person / Time
Site: Clinton 
Issue date: 05/08/2019
From: Karla Stoedter
NRC/RGN-III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2019011
Download: ML19128A329 (21)


Text

May 8, 2019

SUBJECT:

CLINTON POWER STATION, UNIT 1DESIGN BASES ASSURANCE INSPECTION (TEAM); INSPECTION REPORT 05000461/2019011

Dear Mr. Hanson:

On March 29, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Clinton Power Station, Unit 1. On April 11, 2019, the NRC inspectors discussed the results of this inspection with Mr. John Kowalski and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors documented one finding of very low safety significance (Green) in this report. The finding did not involve a violation of NRC requirements.

If you disagree with a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC resident inspector at Clinton. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Karla K. Stoedter, Chief Engineering Branch 2

Docket No.: 05000461 License No.: NPF-62

Enclosure:

IR 05000461/2019011

Inspection Report

Docket Number:

05000461

License Number:

NPF-62

Report Number:

05000461/2019011

Enterprise Identifier: I-2019-011-0024

Licensee:

Exelon Generation Company, LLC

Facility:

Clinton Power Station

Location:

Clinton, IL

Inspection Dates:

March 11, 2019, to March 29, 2019

Inspectors:

J. Benjamin, Senior Reactor Inspector

W. Hopf, Electrical Contractors

V. Petrella, Reactor Inspector

J. Robbins, Senior Reactor Inspector

L. Rodriguez, Reactor Inspector

R. Waters, Mechanical Contractor

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Design Bases Assurance (Team) Inspection at Clinton Power Station, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

Findings and violations being considered in the NRCs assessment are summarized in the table below.

List of Findings and Violations

Failure to Have Procedures Ensuring Satisfactory Performance of Decay Heat Removal Systems during Station Blackout Event Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green FIN 05000461/2019011-01 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding for the licensee's failure to have procedures ensuring the satisfactory performance of the high pressure core spray (HPCS) system and the suppression pool during a station blackout out (SBO) event as delineated in NUMARC 87-00.

Specifically, Procedures Clinton Power Station (CPS) 4402.01 and CPS 4407.01 did not ensure the HPCS system and the suppression pool would remain available for decay heat removal for the duration of the SBO event.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Teams)

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

Reactor Core Isolation Cooling Turbine

  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing; and
  • Calculations:

o Accumulator sizing; o Maximum allowable accumulator leakage; o Minimum accumulator backup air bottle pressure o Valve weak link analysis; o Steam line pressure drop; and o Battery capacity.

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (6 Samples)

(1) Primary System Safety Relief Valve F047A
  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing; and
  • Calculations:

o Weak link analysis; and o Minimum voltage analysis.

(2) High Pressure Core Spray Injection Valve 1E22-F004
  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing; and
  • Calculations:

o Thrust margin; o Motor sizing calculation; o Minimum voltage; and o Electrical protection and coordination.

(3) Safety-related 480Vac Switchgear AP05E
  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing:

o Load testing; o Relay calibration; and o Terminal resistance.

  • Calculations:

o Loading; o Short circuit; o Voltage regulation; o Coordination; o Bus capacity; and o Overcurrent protection.

(4) Safety-related 4kVac Switchgear AP07E
  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing:

o Loading; o Degraded voltage relay drop out; and o Terminal resistance.

  • Calculations:

o Bus loading; o Short circuit; o Supple voltage; o Breaker coordination; o Bus capacity; o Static VAR compensator voltage; o Overcurrent protection; and o Overload heating impact.

(5) Scram Discharge Drain Valve 1C11-F011
  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing; and
  • Calculations:

o Weak link analysis.

(6)125 VDC Battery 1A

  • Technical Specifications;
  • Visual non-intrusive walkdown to assess the installation configuration, material condition, and potential vulnerability to hazards;
  • Normal, abnormal, and emergency operating procedures;
  • Protection against internal events;
  • Protection against external events;
  • Maintenance effectiveness;
  • Overall system health;
  • Translation of vendor specifications;
  • Testing; and
  • Calculations:

o Hydrogen generation; o Seismic qualification of battery and battery racks; o Sizing; and o Station blackout loading.

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

(1) Engineering Change (EC) 324675, "Install Static VAR Compensator Unit on Reserve Auxiliary Transformer";
(2) EC 324759, "Install Static VAR Compensator Unit on Emergency Reserve Auxiliary Transformer";
(3) EC 621081, "High Pressure Core Spray Discharge Relief Valve Modification";
(4) EC 400235, "Removal of Main Steam Line Flow Restrictor Differential Pressure Line Snubbers and Pipe Supports"; and
(5) EC 622359, "Replacement of Dry Type Transformer 1AP11E".

Review of Operating Experience Issues (IP Section 02.06) (2 Samples)

(1) NRC Information Notice 2017-03, "Anchor/Darling Double Disc Gate Valve Wedge Pin and Stem-Disc Separation Failures"; and
(2) NRC Information Notice 2017-06, "Battery and Battery Charger Short-Circuit Current Contributions to a Fault on the Direct Current Distribution System".

INSPECTION RESULTS

Failure to Have Procedures Ensuring Satisfactory Performance of Decay Heat Removal Systems during Station Blackout Event Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green FIN 05000461/2019011-01 Open/Closed None (NPP)71111.21M The inspectors identified a Green finding for the licensee's failure to have procedures ensuring the satisfactory performance of the HPCS system and the suppression pool during a SBO event as delineated in NUMARC 87-00. Specifically, Procedures CPS 4402.01 and CPS 4407.01 did not ensure the HPCS system and the suppression pool would remain available for decay heat removal for the duration of the SBO event.

Description:

The licensee evaluated a SBO using the guidelines of NUMARC 87-00, "Guidelines and Technical Bases for NUMARC Initiatives Addressing Station Blackout at Light Water Reactors." The licensee's SBO coping analysis EPU-T0903, "Extended Power Uprate Task T0903 Station Blackout," Revision 0, evaluated two different methods for responding to an SBO event using either the HPCS system or the reactor core isolation cooling system. The HPCS system is considered the licensing basis system for vessel inventory makeup and core cooling during a SBO.

Analysis EPU-T0903 concluded the suppression pool temperature could exceed the heat capacity temperature limit (HCTL) approximately 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> into the 4-hour SBO coping period.

Usually, the Emergency Operating Procedures (EOP) direct operations personnel to perform an emergency depressurization of the reactor vessel when the suppression pool temperature cannot be maintained less than the HCTL. However, the SBO coping analysis assumed emergency depressurization of the reactor vessel would not be performed because it was not necessary to cope with the SBO. The coping analysis concluded the final suppression pool temperature was acceptable because it remained below the maximum suppression pool temperature limit of 185 degrees Fahrenheit. As a result, the coping analysis contained the following assumption in Section 3.2.2, "Key Assumptions," Item 15:

"Actions specified in CPS Procedures, EOP, Off-Normal Procedures, and Operating Procedures are accomplished as required, with the exception that an emergency blowdown (depressurization) as directed by EOP-6 will not be performed."

The coping analysis also contained the following recommendation in Section 3.4.1, "Recommendations," Item 3, "Revise the Primary Containment Control EOP to permit exceeding the suppression pool HCTL without requiring emergency blowdown for an SBO event."

Procedure CPS 4200.01, "Loss of AC Power," is one of the implementing procedures that would be used by the licensee during a SBO. Section 4.4.4 of the procedure designates the HPCS system as the preferred injection source. Procedure CPS 4402.01, "EOP-6 Primary Containment Control," is an EOP that would be implemented during a SBO. Procedure CPS 4402.01 directs operators to perform an emergency depressurization (i.e., blowdown)in accordance with CPS 4407.01, "EOP 3 Emergency RPV Depressurization (Blowdown),"

when the plant cannot be maintained below the HCTL. Procedure CPS 4407.01 directs operators to perform emergency depressurization as long as the action will not result in the loss of injection needed for core cooling. Therefore, when using the preferred HPCS system during a SBO, emergency depressurization would be directed because the system does not rely on reactor pressure to perform its function.

The inspectors noted Procedures CPS 4402.01 and CPS 4407.01 did not incorporate the assumption and recommendation of the SBO coping analysis that emergency depressurization would not occur during the event. Therefore, the licensee failed to meet the guidance in NUMARC 87-00, Section 2.1, "General Criteria," which states, "Procedures and equipment in light water reactors relied upon in a station blackout should ensure that satisfactory performance of necessary decay heat removal systems is maintained for the required station blackout coping duration." Specifically, Procedures CPS 4402.01 and CPS 4407.01 did not ensure the HPCS system or the suppression pool would remain available for the duration of the SBO event because they would direct emergency depressurization when the HCTL was exceeded, a scenario which was not evaluated in the SBO coping analysis.

Corrective Action(s): The licensee's immediate corrective actions included the performance of two evaluations, EC 627704, "Functionality Evaluation of Suppression Pool Temperature During Station Blackout," and EC 627757, "Evaluation of Past Plant Conditions for SBO,"

which used more realistic assumptions to demonstrate the decay heat removal functions provided by the HPCS system and the suppression pool would be maintained for the duration of a SBO event. The licensee also issued Standing Order 2019-02, "Supplemental Station Blackout Guidance," to ensure the assumptions used in the evaluations remained supported until final corrective actions could be implemented.

Corrective Action Reference(s): Action Request 04231346, "NRCID: DBAI Question Regarding RPV Blowdown During SBO."

Performance Assessment:

Performance Deficiency: The inspectors determined the licensee's failure to have procedures ensuring the satisfactory performance of the HPCS system and the suppression pool would be maintained for the duration of a SBO event as delineated in NUMARC 87-00 was a performance deficiency. Specifically, Procedures CPS 4402.01 and CPS 4407.01 did not ensure the HPCS system or the suppression pool would remain available for the duration of the SBO event because the procedures would direct emergency depressurization of the reactor vessel when the HCTL was exceeded, a scenario which was not evaluated in the SBO coping analysis.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone. Specifically, the failure to have procedures that incorporated the assumption and recommendation of the SBO coping analysis that emergency depressurization would not occur during the event did not ensure the availability and capability of the HPCS system and the suppression pool to cope with a SBO to prevent undesirable consequences (i.e., core damage).

Significance: The inspectors assessed the significance of the finding using Appendix A, Significance Determination of Reactor Inspection Findings for At - Power Situations. The finding screened as having very low safety significance (Green) because the team answered "No" to the risk screening questions listed in IMC 0609, Appendix A, Exhibit 2, Section A.

Cross-cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 11, 2019, the inspector presented the Design Bases Assurance (Team)

Inspection results to Mr. John Kowalski and other members of the licensee staff.

  • On March 29, 2019, the inspector presented the Inspection Debrief to Mr. John Kowalski, Plant Manager and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

01HP15

Development of HPCS Pump Curves and System

Resistances

Revision 4

01ME77

Calcs for Flooding - Safe Shutdown Analysis

01/28/1990

01RI13

NPSH Calculation - RCIC Suction from Suppression Pool

Revision 2

01RI16

RCIC Development of RCIC Pump Curves and Comparison

with the System Resistance Curves for Operating Modes A,

B, C, D, and F

Revision 0

01RI17

RCIC Turbine Performance Requirements

Revision 0

19-AI-60

Electrical Heat Loading in Switchgear and Battery Rooms

Served by VX System

Revision 2

19-AJ-16

Overload Heater Sizing for AC Motor Operated Valves

Revision 3

19-AJ-19

Voltage Analysis of 125 VDC Circuits for 4 kV Circuit

Breakers Operating during LOCA

Revision 2

19-AK-13

Analysis of Load Flow, Short Circuit and Motor Starting

Using ETAP Power Station

Revision 3

19-AN-04

480V ESF Switchgear Breakers and Associated Upstream

Relay Settings

Revision 13

19-AN-20

Circuit Breaker Settings for 480V HPCS MCC (1E22-S002)

Revision 2

19-D-19

Sizing Battery Charger 1A for Division I;

Revision 0

19-D-22

Hydrogen Generated by Batteries during Charging

Revision 0

19-D-23

Estimating Load for 125 VDC System - MCC 1A

Revision 8

19-D-28

Review of Division 1 DC System Review 1A

Revision 15

19-D-42

Station Blackout Analysis - 4 Hour Battery Capacity

Revision 5

and 5A

19-D-42

Station Blackout Analysis - 4 Hour Battery Capacity

Revision 5

19-G-30

Calculation for Ampacity of Power Cables in Trays

Revision 1

3C10-1188-001

NUMARC 87-00 Station Blackout Equipment List

04/07/1989

CALC 01IA044A

SRV Supply Air Design Basis

Revision 1

CALC EH22-

P041A

Piping Stress Analysis for Piping Associated with Panel

1H22-P041A

Revision 15-

A

CALC EPU-T0315 Extended Power Uprate Task T0315: SRV Setpoint

Tolerance Monitoring Program Review

Revision 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CALC IP-M-0054

Minimum Pressure Required for Div 1 ADS Backup Air

Bottles

Revison 0

CQD-005460

Revised Anchor Stress Calculation for 125 V Battery Racks

1DC01E, 02E, 03E, 04E, and 05E

Revision 0

and 0A

CQD-020727

Seismic Battery Loads on DC Battery Terminal

Revision 0

CQD-041783

Westinghouse Switchgear Door Bolting Detail

2/22/1988

DKY-98-002

Use of High Purity Nitrogen for SRV Set Pressure Testing

2/18/1998

EMD-027596

Foundation Loads for 125V Battery Racks

Revision 0

IP-CL-030

Seismic Qualification of MOV 1E22F004

Revision 1,

1a, and 1b

IP-M-0001

Bounding Differential Pressure Calculations for Selected HP

System MOVs

Revision 1a

IP-M-0063

ADS Accumulator Size

Revision 0

IP-M-0181

Heat Content Values for Electrical Equipment

Revision 1

IP-M-0233

System Response Time Evaluation for LPCS, HPCS, and

LPCI Injection

Revision 0

IP-M-0381

Gate Valves Subject to Pressure Locking

Revision 0

IP-M-0409

Main Control Room Temperature Rise during SBO

Revision 0

IP-M-0541

RCIC Gland Steam Failure During a Fire

Revision 0

IP-M-0559

Minimum Cooling Water Flow to RCIC Lube Oil Cooler

Revision 0

IP-O-0123

Tech Spec Indicator Loop Uncertainty Evaluation for Battery

Capacity, Float/Cell Voltage and Current, and Charger

Amps, SR 3.8.4.1, 2, and SR 3.8.6.1, 2, 5, 6, and TS PR

5.5.14a

Revision 1

IP-Q-0390

Qualify ADS and Non-ADS MSRV Air Accumulator Tanks

Due to the Increased Internal Pressure Due to Increased

Ambient Temperature of a Small Break LOCA

Revision 0

MIDACALC

Results for

1E22F004

Electrical and Motor Data, Design Thrust and Torque

Requirements

Revision 7

Corrective Action

Documents

IR 00589228

1RI01T: Notice of Violation (White Finding) Related to

HPCS

2/07/2007

IR 00879332

NRC ID Weakness Identified in 10 CFR 50.59 Screening

Document

2/11/2009

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IR 02508949

Computer Point C11DA009 Displaying Bad Data

06/02/2015

IR 02523392

1DC01E DIV 1 Battery Multiple Cell Post with Blistering

07/22/2015

IR 02603377

1DC01E Cell Post Weld Blisters Noted

2/21/2015

IR 02677753

5067-8L SRV Monitoring System Trouble in MCR

06/04/2016

IR 03951292

1E51C002E - RCIC TTV Latch Level Link Pin Displacement

- CCP

2/09/2016

IR 03972881

SRV 1B21F041C Acoustic Alarm

2/11/2017

IR 03977720

UFSAR and TS Bases Discrepancy; RCIC not an ESF

System

2/23/2017

IR 040066102

NER NC-017-008-Y: LAS HP MOV Stem Disc Separation

05/03/2017

IR 04009649

1DC01E DIV 1 Battery Test Data UNSAT

05/10/2017

IR 04011221

Potentially Degraded Battery Posts on 1DC01E Battery

05/16/2017

IR 04045407

Cracks in 1DC01E Cells Observed

08/24/2017

IR 04149625

4.0 Critique of 1E22F004 Failure Response

06/22/2018

IR 04229482;

DBAI - Calculation Does Not Identify Use of IEEE Standard

03/14/2019

Corrective Action

Documents

Resulting from

Inspection

IR 04229119

DBAI - UFSAR and Tech Spec Bases Discrepancy; RCIC

not an ESF System

03/13/2019

IR 04229425

NRC ID: 1WO05SJ Leak Larger than Catch Containment

03/14/2019

IR 04231346

NRCID: DBAI Question Regarding RPV Blowdown during

SBO

03/20/2019

IR 04232132

DBAI - Calculation Updates Missed during LAR Impact

Review

03/22/2019

IR 04233042

NRC DBAI Basis for 9061.11C001 Acceptance Criteria

03/26/2019

IR 04233486

DBAI Missing Evaluation for RCIC Piping Stresses at EOP

Conditions

03/27/2019

IR 04233496

NRC DBAI: Standard Temperature in ADS Supply Calcs

03/27/2019

IR 04233500

DBAI - Calculation 01RI16 Contains Incorrect Reference

and Value

03/27/2019

IR 04233902

NRC DBAI: TS Bases and USAR Inconsistent

03/28/2019

IR 04234000

NRC DBAI Observations: 9061.11C001 Temperature

03/28/2019

IR 4229588

NRC DBAI Questions Plant Risk with RAT SVC Unavailable

03/14/2019

IR 4233270

Training Lesson Plan has Inaccurate Description of HPCS

Injection Valve

03/26/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawings

796E724

Nuclear Boiler System (NB) (B21-1010)

Revision 2

D-77-269

Air Accumulator Vessel Illinois Power Company

Revision 7

D-77-270

Air Accumulator Vessel Illinois Power Company

Revison 5

M01-1600;

Environmental

Zone Map

Auxiliary Fuel &

Containment Plan

EL. 778-0 &

781-0

Revision A

M05-1002 Sheet

P&ID Main Steam Clinton Power Station Clinton Illinois

Revision 0

M10-9002 Sheet

P&ID/C&I Diagram Main Steam Clinton Power Station Unit 1 Revision E

Engineering

Changes

EC 324756

RAT SVC Equipment Structures

08/13/1998

EC 324759

Relay Setting for SVC Operation

11/13/1999

EC 338201

Revise RCIC Pump NPSH Calculation 01RI13

08/28/2002

EC 341481

25Vdc Divisions I & II Battery Cell Jumper Evaluation

Revision 0

EC 386325

Replace 1B33F067 A/B RR Discharge Valve Disc with Anti-

Rotation Disc

Revision 0

EC 400235

Removed Snubbers 1RB2456S, 1RB24566S, 1RB 2468S,

1RB 2469S, 1RB 2475s, and 1RB 2457s

Revision 0

EC 401924

RCIC Piping Evaluation for ELAP Temperatures

05/19/2015

EC 621081

Replace HPCS Relief Valve 1E22F035 with Seal Welded

Valve

07/27/2018

EC 622359

Replacement of Dry Type Transformer 1AP11E2

Revision 2

EC 627704

Functionality Evaluation of Suppression Pool Temperature

during Station Blackout

Revision 0

Engineering

Evaluations

EPU-T0315

Extended Power Uprate Task T0315: SRV Setpoint

Tolerance Monitoring Program Review

Revision 0

Miscellaneous

07/02/1986

1-LUB-TX02763S;

750kVA VPE

Ventilated Dry

Revision 2 and 6

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Type Transformer

Seismic

Certification

Report for Class

1E Electrical

Equipment

158-AM-11X6

Amendment to FMP 11X6 Rev. 0 Storage Instruction,

Inspection and Maintenance Requirements for Diaphragm

Operated Control Valves and Accessories

05/21/1976

1E22F004

JOG MOV Evaluation Report

Revision 7

A33007.F10-3947

Clinton Power Station SVC Design Report

Revision 0

B21-F041

Stress Report No. G471-6 125.04.07

Revision 8

C8185-000052

Justification for Two Revisions to Fisher Product Bulletin

Manual form 61.1:657 in VTIP Binder K2864-0001 Tab 16

and K2882-0106 Tab 1

Revision 0

CPS NO

1005.06f001

Safety Evaluation Screening for Modification AP-37, RAT

SVC Installation, ECNS 30526, 30527, and 30528

07/31/1999

EPU-T0902

Extended Power Uprate Task Report Anticipated Transients

without Scram

Revision 2

G471.6/125.04.10

Dikkers Nuclear Safety/Relief Valve Instruction Manual

10/02/1980

IST-CPS-BDOC-

V-16

Clinton IST Bases Document for 1B21-F047A

05/19/2011

IST-CPS-BDOC-

V-20

Clinton IST Bases Document for 1C11-F011

05/19/2011

JAP-90-034

SRV Stud Removal - MDM Process

07/18/1990

Log No 2019-02

Supplemental Station Blackout Guidance

03/24/2019

NSED Standard

MS-07-00

MOV Periodic Verification Program Scope

Revision 14

NSED-I-EE-6

Transmission Grid Conditions for Clinton Power Station

Revision 5

Product Bulletin

61.1:657

Type 657 and 667 Diaphragm Actuators

06/2002

RCIC Turbine

Vendor Manual

Type GS-2 SNT-38187-A Terry Turbine

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

K2801-030

U-0763

Clinton Power Station (CPS) Unit 1 Request for Additional

Information TMI Action Item II.K.3.28 (Confirmatory Issue

047)

11/19/1984

Y-96136

Air Supply Line Testing for SRVs, ADS-SRVs and MSIVs to

Satisfy Design and Licensing Bases

01/28/1991

Y-96190

CPS 9061.11 Pressure Drop Test Acceptance Criteria

2/06/1991

Procedures

01RI15

RCIC TS SR for RCIC Pump Differential Pressure at Rated

Flow

Revisions 1,

1a, and 1b

1014.11

6900, 4160, 480 Vac Switchgear Circuit Breaker Operability

Program

Revision

005E

3309.01

High Pressure Core Spray (HPCS)

Revision 17e

3310.01

Reactor Core Isolation Cooling (RI)

Revision 30d

3315.02

Leak Detection

Revision 15a

3501.01

High Voltage Auxiliary Power System

Revision 29

3501.01C001

Generator Backfeed Checklist

Revision 10

3501E001

High Voltage Auxiliary Power System Lineup

Revision 14

3504.01

346 and 138kV Switchyard

01/11/2017

3505.01

346 and 138 kV Switchgear (SY)

Revision

20E

3505.01C005

RAT B - LTC Manual Switching Order

Revision 0d

3506.01

Diesel Generator and Support System Electrical Lineup

Revision

18C

3514.01C005

4160 V Bus 1A1 (1AP07E) Outage

Revision 7

3514.01E005

4160 V Bus 6900, 4160, 480 V Circuit Breakers

Revision 8c

3808.01

RCIC Turbine Overspeed Trip Test

Revision 10b

4100.01

Reactor Scram

Revision 23f

200.01

Loss of AC Power

Revision 26

200.01C002

DC Load Shedding during a SBO

Revision 5a

200.01D008

Emergency Bus 1A1 Trip Data Sheet

Revision 2a

4411.03

Injection/Flooding Sources

Revision 10d

4411.04

Throttling ECCS Flow

Revision 5d

8491.01

Cable Pulling

03/27/2013

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

9051.02

HPCS Valve Operability Data Sheet

Revision 42b

9054.01 C002

RCIC High Pressure Operability Checks

08f

9054.01 C003

RCIC Low Pressure Operability Checks

Revision 05f

9054.05

RCIC RSP Operability Checks

Revision 33d

9054.06

RCIC Discharge Header Filled and Flow Path Verification

and Flow Controller Checks

Revision 28

CC-AA-302

Control of Cable Management Database

Revision 3

CPS 3214.01

Plant Air (IA & SA)

Revision 27c

CPS 8216.02

Safety/Relief Valve Removal and Installation

Revision 21

EOP 1a

ATWS RPV Control

Revision 30

EOP 2

RPV Flooding

Revision 30

EOP 3

Emergency RPV Depressurization (Blowdown)

Revisions

26, 27, 28,

29, and 30

EOP 6

Primary Containment Control

Revisons 26,

27, 28, 29,

and 30

EOP-1

RPV Control

Revision 30

IP-M-0587

RCIC EOP Operation Maximum Suppression Pool

Temperature

Revision 0

N-CL-OPS-

209002

High Pressure Core Spray System

Revision 3

N-CL-OPS-

217000

Reactor Core Isolation Cooling

Revision 6

OP-CL-101-1001-

F-02

Start of Scram Choreography

Revision 1a

OP-CL-102-106-

1001

Operator Response Time Master List at CPS

Revision 8c

P927-000001

PCI Energy Services MDM Stud Cutting Procedure

Revision 0

SE-EOP-20A

EOP-1A, ATWS RPV Control with a Group 1 Isolation

Revision 0

Shipping Records

PO # 000074880

Amergen/Exelon Clinton Nuclear Station

11/2005

Work Orders

GEK-75652A;

Operation and

Maintenance

07/02/1986

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Instructions for

Automatic

Depressurization

System

WO 00973837

Overhaul Actuator and Replace Accessories 1C11F011

01/24/2008

WO 01347634

Replaced SRV with a Qualified Spare

05/11/2015

WO 01459364

LLRT HPCS Injection Valve

10/15/2013

WO 01518247

Perform Flowscan in Support of the AOV Program

1C11F011

10/19/2013

WO 01533801

9061.11R20 OP La Check Valve Operation

10/28/2013

WO 01539946

9012.01B20 VER SDV Vent and Drain Valve Operation

01/29/2014

WO 01541057

1E22F035 HPCS Injection Line Relief Valve Leaking 1-2

DPM

10/25/2017

WO 01688707

HPCS RTT (All Channels)

2/23/2017

WO 01691814

9061.11R20 OP La Check Valve Operation

05/15/2015

WO 01759037

Overhaul Actuator and Replace Accessories 1C11F011

05/23/2017

WO 01848439

9061.11R20 Op La Check Valve Operation

05/27/2017

WO 01850854

9012.01a20 OP SDV Vent and Drain Valve Operation

10/30/2015

WO 01858436

HPCS 1E22F004 Valve Functional Test

05/20/2017

WO 01868077

Removed Snubbers in Accordance with EC 400235

05/22/2017

WO 01910395

Division I Battery 1DC01E Modified Performance Test

05/04/2018

WO 04643900

SDV Drain Valves (F011 and F191) Failing 9012.01 Stroke

Surveillance

05/26/2017

WO 04644807

CAT A Valve LRT 1E22F004 HPCS Injection

04/17/2018

WO 04674876

9012.01a20 OP SDV Vent and Drain Valve Operation

10/24/2017

WO 04780286

OP SDV Vent and Drain Valve Operation

07/24/2018

WO 04812195

9012.01a20 OP SDV Vent and Drain Valve Operation

10/23/2018

WO 04832963

OP DIV I ICV and Charger Checks

2/19/2018

WO 04847752

HPCS Valve Operability (Stroke Time)

01/11/2019

WO 04851866

9012.01a20 OP SDV Vent and Drain Valve Operation

01/22/2019

WO 04856031

RCIC High Pressure Test and Valve Operability

01/23/2019

WO 05297810

Replace SRV with a Qualified Spart

2/18/2004

WO 06672060

Tail Pipe Temp Indicator Hose is Cut

2/22/2004

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 07721790

Replaced SRV with a Qualified Spare

01/22/2010