IR 05000461/1980007

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-461/80-07 on 800422-24.Noncompliance Noted: Failure to Properly Store Welding Matl,Failure to Verify Conformance During Insp & Failure to Conform W/Procedures
ML19318A455
Person / Time
Site: Clinton Constellation icon.png
Issue date: 05/09/1980
From: Danielson D, Lee E K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19318A449 List:
References
50-461-80-07, 50-461-80-7, NUDOCS 8006230151
Download: ML19318A455 (6)


Text

__ _

.

,m

%)

'

U.S. NUCLEAR REGULATORY C0tiMISSION OFFICE OF INSPECTION AND ENF0kCEffENT

REGION III

Report No. 50-461/80-07 Docket No. 50-461 License No. CPPR-137 Licensee:

Illinois Power Company 500 South 27th Street Decatur, IL 62525 Facility Name:

Clinton Power Station, Unit 1 Inspection At:

Clinton Site, Clinton, IL Inspection Conducted: April 22-24, 1980 Jwan/w

'

80 Inspector:

. W. K. Lee

-

irm a.

/ n Approved By:

D. H. Danielson, Chief

d'#

Engineering Support Section 2 i

Inspection Siunmary Inspection on April 22-24, 1980 (Report No. 50-461/80-07)

Areas Inspected: Reactor coolant pressure boundary and safety related piping and welding QA manuals, procedures, and work activities. The inspection involved a total of 18 inspector hours on site by one NRC inspector.

Results: Of the six areas inspected, no apparent items of noncompliance were identified in five areas; three apparent items of noncompliance were identified in one area (infraction - failure to properly store welding material - Paragraph 2.b; infraction - failure to verify conformance with requirements during inspection - Paragraph 8; infraction - failure to con-form with procedural parameters - Paragraph 3).

i eonesso15r '

I

.

.

DETAILS Persons Contacted Principal Licensee Employees

  • G. M. Brashear, Manager, Clinton Site
  • R. J. Canfield, Director, Construction
  • L. Dozier, Piping and Mechanical
  • R. W. Folck, Construction, Quality Assurance
  • J. F. Hampton, Supervisor, Construction, Quality Assurance
  • M. Tindill, Quality Assurance Specialist Other Personnel
  • R. D. Bennett, Manager, Technical Service, Baldwin Associates (BA)
  • F. Camasta, Piping, BA
  • J. Findley, Project Engineer, BA
  • J.R. Hilding, Quality Assurance Manager, BA
  • M. J. King, Authorized Nuclear Inspector, Hartford Steam Boiler Ins. Co.
  • J. Linehan, Manager, Quality Control, BA
  • E. Muelhausen, Piping, BA
  • H. R. Swift, Assistant Project Engineer, BA
  • T. Walker, Senior Quality Control Engineer, BA
  • C, Winfrey, Quality Control, BA The inspector also talked with and interviewed several other licensee and his contractor's employees, including a member of the technical services staff, Quality Control and Quality Assurance personnel, and craftsmen.
  • Denotes those present at the exit interview.

Functional or Program Areas Inspected 1.

Reactor Coolant Pressure Boundary and Safety Related Piping - Welding Procedures, Specificatiuns, and Quality Assurance Procedures a.

Quality Assurance Procedures The inspector reviewed the Baldwin Associates, Incorporated (BA)

Quality Assurance manual and procedures related to the welding of reactor coolant pressure boundary and safety related piping.

It was established that the manual and the procedures have not been revised since the last review (Report No. 50-461/80-03 ex-cept for four procedures. The revised portion of the four procedures were reviewed and determined to be acceptable.

b.

Welding Procedures The inspector reviewed the following BA welding procedures:

-2-

,

(1) GE/NP-1-1-BA-2L, Revision 2, and Procedure Qualification Record (PQR) Nos. 20 and 21.

(2) GE/NP-8-8-BA-2L, Revision 2, and PQR No. 3183.

(3)

NP-1-1-BA-L, Revision 4, and PQR Nos. 0606, 24, 25 and 26.

(4)

NP-8-8-BA-M, Revision 4, and PQR No. 109-16.

(5)

N-1-1-B-S, Revision 7, and PQR Nos. 6907 and 44.

It was determined that ASME B&PV Code Section IX requirements were met.

No items of noncompliance or deviations were identified.

2.

Reactor Coolant Pressure Boundary and Safety Related Piping - Welding Material Control The inspector reviewed the following documents:

a.

(1) BA procedure No. BTS-402, Revision 14, " Procedure Specification for the Procurement, Storage, and Control of Welding Filler Materials."

(2) BA procedure No. BTS-402 (GE/ Weld Control), Revision 2,

" Procedure Specification for the Procurement, Storage, and Control of Welding Filler Materials."

(3) Receiving Inspection Reports, Material Certifications, and Purchase Orders for ER 309 welding rods with heat No.

C3287T309, No. D3313T309, No. A3287T309, No. 6J12A mix 19, No. 6N22B mix 15, and No. 7A12B mix 9.

It was determined that the above requirements met the PSAR, 10 CFR 50, Appendix B, and the applicable code and procedure requirements.

b.

Control of Materials The inspector toured the welding material issuance station No. 4.

It was determined that (1) the welding materials are properly identified and segregated; (2) the temperature of the rod oven is maintained; (3) records are properly kept; (4) issuance and return of welding materials are controlled in accordance with approval procedures and (5) sandwiches were being stored in a rod oven, No. TS-192. This condition represents an item of noncompliance identified in Appendix A (461/80-07-01).

Except as noted, no items of noncompliance or deviations ;ere identified.

-3-

.

3.

Reactor Coolant Pressure Boundary Piping - Observation of Welding Activities The inspector observed the following activities:

Nuclear Boiler System weld No. B4 on traveller No. IB21-D302B-A-FI.

a.

,

b.

High Pressure Core Spray System weld No. 1-HP-5-9.on traveller No. HP-5-A.

c.

Nuclear Boiler System weld No. C4 on traveller No. 1B21-D302C-A-FI.

d.

Recirculation System weld no. A3 on traveller No. B33-G001-A.

It was determined that (1) work was conducted in accordance with the traveller; (2) proper welding materials were used; (3) welding proce-dure requirements were met; (4) work area was free of weld rod-stubs; (5) physical appearance was acceptable; and (6) the weld bead width of a fill pass on weld No. A3 on traveller No. B33-G001-A exceeded the welding procedure allowance.

This represents a noncompliance as identified in Appendix A (461/80-07-02).

Except as noted, no items of noncompliance or deviations were identified.

4.

Reactor Coolant Pressure Boundary Piping - Observation of NDE Work Activities The inspector observed liquid penetrant examination on the following welds:

a.

Recirculation System weld No. A-10 on traveller No. B33-G001-A.

b.

Peactor Water Clean-up System welds No. 1RT-37-5W1, No. 1RT-37-SW2, No. 1RT-37-5W3, No. IRT-37, SW5 and No. 1RT-37-5W6 on traveller No. FRT-37-A.

It was determined that (1) surface condition was acceptable, (2)

procedure requirements were met, and (3) personnel were properly qualified.

No items of noncompliance or deviations were identified.

5.

Reactor Coolant Pressure Boundary and Safety Related Piping - Weld Heat Treatment a.

Review of Procedure The inspector established that the welding procedures reviewed under paragraph Ib of this report specified the acceptable pre-heating and monitoring methods.

-4-

.

.

'

b.

Observation While observing welding activities for items stated in paragraphs 3 and 9 of this report, the inspector determined that preheat met the procedure requirements.

No items of noncompliance or deviations were identified.

6.

Reactor Coolant Pressure Boundary and Safety Related Piping - Welder Qualification The inspector reviewed the following documents:

a.

BA Procedure No. BTS-401, Revision 9, " General Welding Procedure Specification."

b.

Qualification records of twelve welders who performed welding on welds stated in paragraphs 3 and 9 of this report.

The inspector determined that the above documents met the require-ments of ASME B&PV Code Section IX.

No items of noncompliance or deviations were identified.

7.

Reactor Coolant I'ressure Boundary Piping - Special Welding Applications The inspector observed grinding of defects of the Nuclear Boiler System weld No. B4 on traveller No. 1B21-D302B-A-FI.

It was determined that procedure requirements were met and good construction practice was ad-hered to.

No itemt of noncompliance or deviations were identified.

8.

Safety Related Piping - Observation of Work Activities The inspector observed the fit-up and alignment of Residual Heat Removal System weld No. 1-RH-9-2 on traveller No. RH-9-B.

It was determined that the internal surface alignment failed to meet the procedure requirements. This represents an item of noncompliance as identified in Appendix A (461/80-07-03).

9.

Safety Reltted Piping - Observation of Welding Activities The inspector observed the welding of High Pressure Core Spray System weld No. 1-HP-4-5 on traveller No. HP-4-A and Containment Combustible Gas Control System weld No. 1-HG-8-2 on tras'11er No. HG-8.

It was determined that (1) work was conducted in accordance with traveller; (2) proper welding materials were used; (3) welding procedure requirements were met; (4) work area was free of weld rod-stubs; and (5) physical appearance was acceptable.

No items of noncompliance or deviations were identified.

-5-

.

._

.

Exit Interview The inspector met with the licensee representatives (denoted under Persons Contacted) at the conclusion of the inspection on April 24, 1980. The in-apector summarized the purpose and findings of the inspection. The inspec-tor again emphasized his concern relative to the monitoring and enforcement of the four hours allowance of electrodes being out of the portable oven as allowed by the weld material control procedure.

It was also noted that about thirty 1/8" diameter and eight 3/32" diameter coated electrodes at one weld joint location were not returned to the portable oven prior to the craftsman going to lunch, and the electrodes were stone cold. This is contrary to a statement made by a licensee representative during an exit interview on March 6,1980, that it is a general practice that electrodes are returned to the portable oven during lunch break. The licensee acknowledged the infor-mation.

-6-