IR 05000456/2020001

From kanterella
(Redirected from IR 05000457/2020001)
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2020001 and 05000457/2020001
ML20112F313
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 04/21/2020
From: Hironori Peterson
Region 3 Branch 3
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2020001
Download: ML20112F313 (17)


Text

April 21, 2020

SUBJECT:

BRAIDWOOD STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000456/2020001 AND 05000457/2020001

Dear Mr. Hanson:

On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station, Units 1 and 2. On April 15, 2020, the NRC inspectors discussed the results of this inspection with Mr. J. Keenan, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket Nos. 50-456; 50-457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2020001 and 05000457/2020001

Enterprise Identifier: I-2020-001-0040

Licensee:

Exelon Generation Company, LLC

Facility:

Braidwood Station, Units 1 and 2

Location:

Braceville, IL

Inspection Dates:

January 01, 2020 to March 31, 2020

Inspectors:

D. Betancourt-Roldan, Senior Resident Inspector

J. Bozga, Senior Reactor Inspector

D. Kimble, Senior Resident Inspector

P. Smagacz, Resident Inspector

J. Weigandt, Reactor Engineer

R. Bowen, Illinois Emergency Management Agency

Approved By:

Hironori Peterson, Chief

Branch 3

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Units 1 and 2 both began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, both units remained operating at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial equipment alignment verifications of the following systems/trains:

(1) The Unit 0 and Unit 1 Station Air Compressors (SACs) with the 2A SAC undergoing commissioning testing (elevated risk activity) during the week ending February 22, 2020.
(2) The 2B Safety Injection (SI) Train during a 2A SI Train maintenance work window during the week ending February 29, 2020.
(3) The 1B Auxiliary Feedwater (AF) Train following return to service after maintenance during the week ending March 21, 2020.

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete alignment verification of the Unit 1 SI System during the weeks ending March 14, through March 28, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting physical inspections and reviews to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 3.2A-2: Unit 2 Lower Cable Spreading Room during the week ending March 21, 2020.
(2) Fire Zone 4.5-2: Division 22 Miscellaneous Electrical Equipment Room and Battery Room during the week ending March 28, 2020.

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the training and performance of the station's fire brigade during observation of an unannounced fire drill on January 31, 2020.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated the station's internal flooding mitigation protections for the following areas:

(1) The Unit 1 Diesel Fuel Oil Storage Rooms during the week ending January 25, 2020.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Main Control Room during various activities involving on-watch operations crews during the weeks ending February 22 through February 28, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a crew of licensed operators during a graded casualty scenario in the station's simulator on January 30, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remained capable of performing their intended functions:

(1) The facility's permanently installed station air compressors (SACs) during the weeks ending January 25 through February 1, 2020.
(2) The Unit 2 pressurizer heaters during the weeks ending March 28 through March 31, 2020.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's assessment of risk associated with the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Various performance issues and repairs on all three SACs during the weeks ending January 25 through February 1, 2020.
(2) A 2A SI Cubicle Cooler maintenance window as documented in Work Order (WO)

===1931687 during the week ending February 29, 2020.

(3) Troubleshooting and repairs to the Unit 2 Containment Emergency Airlock as documented in WO 4640976 during the weeks ending March 14 through March 21, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01)===

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Issues with structural fireproofing coatings in the Unit 2 Lower Cable Spreading Room as documented in IR 4304844 during the weeks ending January 18 through January 25, 2020.
(2) Issues with diesel generator jacket water leakage from the 2DG01KB-X2 lower cooler leak as documented in IR 4312030 during the weeks ending January 25 through February 1, 2020.
(3) An adverse trend associated with multiple issues/failures of Unit 2 pressurizer heaters as documented in IR 4322388 during the weeks ending March 14 through March 28, 2020.
(4) An emergent issue that resulted from a failure of the Unit 2 containment emergency airlock door interlocks as documented in IR 4325451 during the weeks ending March 14 through March 28, 2020.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Functional acceptance testing for a newly installed fourth station air compressor (SAC 2A) per Engineering Change (EC) 627885 and as documented in Work Order (WO)

===4959489 during the weeks ending February 8 through February 22, 2020.

(2) Functional testing of the 1B AF Train following planned maintenance activities per WOs 4898748 and 5011451 during the weeks ending March 14 through March 21, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance testing activities:

Surveillance Tests (other) (IP Section 03.01)

(1)1BwOSR 3.8.1.2-2: 1B EDG Semiannual Surveillance during the week ending February 15, 2020.

Inservice Testing (IP Section 03.01)===

(1)2BwOSR 5.5.8.RH-5B: Group A Inservice Test Requirements for Residual Heat Removal Pump 2RH01PB during the week ending January 18, 2020.

(2)1BwOSR 5.5.8.CS-3B: Comprehensive Full Flow Test for 1B Containment Spray Pump (1CS01PB), and Check Valves 1CS003B, and 1CS011B during the week ending March 14, 2020.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated the station's Emergency Response Organization during the performance of a site-wide drill on February 1,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors reviewed and verified selected portions of the licensee's performance indicator submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) Unit 1 (January 2019 - December 2019)
(2) Unit 2 (January 2019 - December 2019)

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)

(1) Unit 1 (January 2019 - December 2019)
(2) Unit 2 (January 2019 - December 2019)

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)

(1) Unit 1 (January 2019 - December 2019)
(2) Unit 2 (January 2019 - December 2019)

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of their corrective action program related to the following issue:

(1) The notification of a Code nonconformance for the Unit 1 replacement steam generators as documented in IR 4272501 during the week ending February 22, 2020.

71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

(1) For the COVID-19 National Emergency declared by the President of the United States, the inspectors performed various reviews and the tracking of licensee actions during the weeks ending March 21 through March 31, 2020.

Event Report (IP Section 03.02) (1 Partial)

The inspectors evaluated the following licensee event reports (LERs):

(1)

(Partial)

LER 05000456/2019-001-00, Unit Trip on Low Steam Generator Level Due to Failure of a Controller on a Feedwater Regulating Valve. (ADAMS Accession Number ML19324D929)

The inspection conclusions associated with this LER are documented in Inspection Report 05000456/2020010 and 05000457/2020010. (ADAMS Accession Number ML20086G679)

INSPECTION RESULTS

Observation: Notification of Code Nonconformance for Replacements Steam Generators 71152 The inspectors performed a detailed review of Issue Report (IR) 4272501, Notification of Code Nonconformance for Replacements Steam Generators. The manufacturer of the licensees replacement steam generators (RSGs) for Byron Unit 1 and Braidwood Unit 1 had recently identified that volumetric examination of a nozzle weld repair that was accomplished by the manufacturer prior to the delivery of the RSGs to the licensee had not been performed, contrary to American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section III, Class 1, requirements. The affected nozzles were the 3-inch diameter blowdown and recirculation nozzles. The nozzles were fabricated by weld metal buildup as permitted by NB-4244(c). The manufacturer determined that the nozzles required repair of surface indications; the manufacturers records did not indicate the depth of the excavations and no post-repair volumetric examinations were performed.Section III, Division 1, Subsection NB-4453.4 of the ASME Boiler and Pressure Vessel Code requires a volumetric exam when the excavation exceeds the lesser of 10 percent of the section thickness or 3/8 inch. For this Problem Identification and Resolution Annual Sample, the inspectors focused on assessment of the licensees corrective actions taken to date and those planned from this point forward.

The licensee performed an engineering change which included an ASME code class reconciliation for the 3-inch diameter blowdown and recirculation nozzles. This reconciliation involved a section by section evaluation applicable to nozzle weld buildups to determine the ASME Code Class 1 versus the ASME Code Class 2 requirements. The licensee determined based on their code class reconciliation that the blowdown and recirculation nozzles could be classified as ASME Code Class 2 (Subsection NC). Since Section III, Subsection NC (4453.4 and 5254), of the ASME Boiler and Pressure Vessel Code requires volumetric examination for nozzle weld buildups after weld repair only if the nozzles diameter is 6-inch or greater, this code reconciliation resolved the ASME Code nonconformance.

The inspectors concluded that the licensees actions taken in accordance with their corrective action program were reasonable given the overall safety significance of the issue. The inspectors did not identify any findings or violations of NRC requirements in the course of their review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On April 15, 2020, the inspectors presented the integrated inspection results to Mr. J. Keenan, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

M-61

Diagram of Safety Injection Sheet 1A

BJ

M-61

Diagram of Safety Injection Sheet 6

AX

M-61

Diagram of Safety Injection Sheet 3

AR

Engineering

Changes

M-61

Diagram of Safety Injection Sheet 1B

BF

Fire Plans

M-61

Diagram of Safety Injection Sheet 2

AJ

Procedures

1BwOSR 3.5.2.2-

Unit One ECCS and CS Venting and Valve Alignment / UT

Verification Surveillance

BwOP AF-E1

Electrical Lineup - Unit 1 Operating

BwOP AF-M1

Operating Mechanical Lineup Unit 1

BwOP SA-E1

Electrical Lineup - Unit 1, Station Air System Operating

BwOP SA-E2

Electrical Lineup - Unit 2, Station Air System Operating

BwOP SA-M1

Operating Mechanical Lineup - Unit 0

BwOP SA-M2

Operating Mechanical Lineup - Unit 2

BwOP SI-E1

Electrical Lineup - Unit 1 Operating

BwOP SI-M1

Operating Mechanical Lineup Unit 1

Radiation Work

Permits (RWPs)

4964464

U1 ECCS V/V M2 Entry Ascending

10/20/2019

Work Orders

4987403

U1 ECCS Venting and Vlv Alignment Quarterly

03/05/2020

4993365

U1 ECCS Venting and Vlv Alignment Semi-Annual Inside

Containment

03/05/2020

71111.05

Fire Plans

Pre-Fire Plan 76

Fire Zone 8.5-2; Tubine Building Mezzanine Floor (SE)

Pre-Fire Plan No.

Fire Zone 3.2A-2; CSR 439 Unit 2, Nonsegregated Bus Duct

Area

Pre-Fire Plan

No.48

Fire Zone 5.4-2; Division 22 Miscellaneous Electrical

Equipment Room and Battery Room, 451 Elevation

Miscellaneous

Fire Drill Scenario

20.20.01.30

Transient Combustible Fire

01/30/2020

Procedures

BwAp 1110-1

Fire Protection Program System Requirements

BwAP 1110-3

Plant Barrier Impairment Program

71111.05

Procedures

BwOP PBI-1

Plant Barrier Impairment Program Pre-Evaluated Barrier

Matrix

CC-AA-01

Plant Barrier Control Program

ER-AA-600-1069

High Risk Fire Area Identification

ER-BR-600-1069

Site List of High Risk Fire Areas - Braidwood Unit 1 and Unit

OP-AA-201-007

Fire Protection System Impairment Control

OP-AA-201-008

Pre-Fire Plan Manual

OP-AA-201-009

Control of Transient Combustible Material

OP-AA-201-009

Control of Transient Combustible Material

OP-AA-201-104

Fire Prevention for Hot Work

71111.06

Corrective Action

Documents

Resulting from

Inspection

210831

NRC Identified Removed 1OD01PA Staged too Close to

Transfer

01/14/2019

Drawings

M-48

Diagram of Miscellaneous Sumps & Pumps

BC

M-50

Diagram of Diesel Fuel Oil Unit 1

BA

71111.11Q Procedures

OP-AA-101-102

Watch-Standing Practices

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-108-107-

1002

Interface Procedure Between BGE/COMED/PECO and

Exelon Generation (Nuclear/Power) for Transmission

Operations

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

71111.12

Corrective Action

Documents

4305913

Unexpected Annunciator: 2-12-B6

2/23/2019

4308965

2RY03EB Heater 40 was Found Degraded

01/09/2020

4310328

Found 2 Heater Deficiencies

2/24/2020

4311227

Entry into 0/1/2 BwOA SEC-4 Lowering Instrument Air

Header Pressure

01/19/2020

4311429

Temporary Air Compressors Problems

01/20/2020

4311433

2SA01C Oil level Above High Mark on Sightglass

01/20/2020

4311692

2SA01C Oil Mist Emanating from Oil Mist Eliminator

01/21/2020

4311729

Small Amount of Valve Seat Rubber Material Missing

0SA140

01/22/2020

4311798

2SA01C U2 SAC Rising Vibrations

01/22/2020

4311924

0SA140 Installed without Internal Liner

01/22/2020

4312008

U-0 SAC Trip

01/23/2020

4312018

U1 SAC 2nd Stage Intercooler Leak

01/23/2020

4312287

Water Leaking from 2SA03M

01/23/2020

4312908

Water Found in Oil Sample of U2 Station Air Compressor

(SAC)

01/27/2020

21350

2RY03EA Breaker B5B was Found in Tripped Position

2/25/2020

22388

Trend IR for U2 RY Heaters

2/28/2020

Drawings

113E760

Pressurizer Heater Power Distribution Requirements and

Suggested Heater Groupings

B

Miscellaneous

EC 630430

Disconnect Unit 2 Pressurizer Heaters #17, #18, #40, #69,

  1. 70 & Open Breakers 2RY03EA-B5A/B5B for Heaters #13,
  1. 14, #37

Procedures

ER-AA-310-1002

Maintenance Rule Functions - Safety Significant

Classification

ER-AA-320

Maintenance Rule Implementation per NEI 18-10

ER-AA-320-1001

Maintenance Rule 18-10 - Scoping

ER-AA-320-1003

Maintenance Rule 18-10 - Failure Definitions

ER-AA-320-1004

Maintenance Rule 18-10 - Performance Monitoring and

Dispositioning Between (a)(1) and (a)(2)

71111.13

Corrective Action

Documents

4311227

Entry into 01/2 BwOA SEC-4 for Lowering Instrument Air

Header Pressure

01/19/2020

4311429

Temporary Air Compressor Problems

2/20/2020

4311798

2SA01C - Unit 2 SAC Rising Vibrations

01/22/2020

4311924

OSA140 Installed Without Internal Liner

01/22/2020

4312018

Unit 1 SAC 2nd Stage Intercooler Leak

01/23/2020

21013

2A Safety Injection Cubicle Cooler (2VA04SA) Divider Plate

Requires Repair

2/24/2020

Corrective Action

Documents

Resulting from

Inspection

4312008

Unit 0 SAC Trip

01/23/2020

Drawings

M-54, Sheet 1A

Diagram of Service Air - Units 1 and 2

AP

M-54, Sheet 1B

Diagram of Service Air - Units 1 and 2

AL

M-54, Sheet 2

Diagram of Service Air - Units 1 and 2

AH

M-55, Sheet 1

Diagram of Instrument Air

AF

Engineering

Changes

EC 246977

Evaluate Minimum Wall Criteria and Gasket Mating Surface

Requirements for Safety Injection Pump Cubicle Coolers

Operability

Evaluations

BwAR 0-39-B2

SAC 2 Trouble

Procedures

1BwOA SEC-4

Loss of Instrument Air - Unit 1

107

2BwOA SEC-4

Loss of Instrument Air - Unit 2

106

BwAR 1-12-D7

Pressurizer PORV Supply Pressure High/Low

BwMP 3100-

077A1

Installation and Removal of Temporary Air Compressors

BwOA SEC-4

Loss of Instrument Air - Unit 0

104

BwOP SA-1

Startup and Operation of Station Air Compressors

- 48

BwOP SA-2

Shutdown of the Station Air Compressors

BwOP SA-8

Aligning Service Air Compressor for Standby Operation

ER-AA-330-009

ASME Section XI Repair/Replacement Program

ER-AA-335-015-

2013

VT-2 Visual Examination in Accordance with ASME 2013

ER-AA-340-1002

Service Water Heat Exchanger Inspection Guide

ER-AA-600

Risk Management

ER-AA-600-1042

On-Line Risk Management

MA-AA-716-004

Conduct of Troubleshooting

OP-AA-108-117

Protected Equipment Program

WC-AA-101-1006

On-Line Risk Management and Assessment

Work Orders

1931687

2VA04SA: Clean and Inspect 2A Safety Injection Pump

Cubicle Cooler

2/24/2020

4640976

Unit 2 Containment Emergency Airlock

Troubleshooting/Repair

03/12/2020

4989830

Hook Up Temporary Air Compressors

01/19/2020

71111.15

Corrective Action

Documents

4304844

Fireproofing Missing From Ceiling in Lower Cable Spreading

Room

2/18/2019

4310367

2FIS-611 Initially Suspect During 2B RH ASME Run

01/14/2020

4312030

2DG01KB-X2 Jacket Water Lower Cooler Leak

01/23/2020

21350

2RY03EA Breaker B5B was Found in Tripped Position

2/25/2020

22388

Trend Issue Report for Unit 2 Pressurizer Heaters

2/28/2020

25451

Unit 2 Emergency Hatch Doors Unable to be Opened

03/10/2020

Procedures

2BwOSR 3.8.1.2-

Unit Two 2B Diesel Generator Operability Surveillance

Work Orders

4995339

LR-IST-2B Emergency Diesel Generator Monthly

Surveillance

01/22/2020

71111.19

Corrective Action

Documents

4317383

Multiple Small Leaks on 2A Station Air Compressor

2/12/2020

4317384

2A Station Air Compressor Start Permissive Discovery

2/12/2020

4317760

2A Station Air Compressor Increase of Discharge Pressure

2/13/2020

4318080

2A Station Air Compressor - Oil Filter Differential Pressure

Value is Not Valid

2/14/2020

26219

Oil Level Out of Band for 1AF01PB - 1B Auxiliary Feed

Pump

03/12/2020

Engineering

Changes

27885

Install Fourth Station Air Compressor

Miscellaneous

Night Shift Unit 1 Control Room Logs

03/13/2020

Procedures

1BwOSR

5.5.8AF-3B

Group A Inservice Testing Requirements for Unit 1 Diesel-

Driven Auxiliary Feedwater Pump

BwOP AF-7

Auxiliary Feedwater Pump B (Diesel) Startup on Recirc

CC-AA-107

Configuration Change Acceptance Testing Criteria

SPP 20-001

Modification Test for 2SA02C Station Air Compressor

WC-AA-101

On-Line Work Control Process

Work Orders

4959489

Install Fourth Station Air Compressor per EC 627885

03/03/2020

71111.22

Corrective Action

Documents

4310367

2FIS-611 Initially Suspect During 2B RH ASME Run

01/14/2020

4317240

1DG01KB-Y2: 1B Diesel Generator Lower Lube Oil Cooler

Leak While Loading

2/12/2020

27401

1BwOSR 5.5.8.CS-3B: 1B CS D/P EDG Uncertainties

(CA2644573)

03/17/2020

Procedures

1BwOSR 3.8.1.2-

1B Diesel Generator Operability Surveillance

1BwOSR

5.5.8.CS-3B

Comprehensive Full Flow Test for 1B Containment Spray

Pump (1CS01PB) and Check Valves 1CS003B, 1CS011B

2BwOSR

5.5.8.RH-5B

Group A IST Requirements for Residual Heat Removal

Pump 2RH01PB

BwOP DG-11

Diesel Generator Startup and Operation

BwOP DG-12

Diesel Generator Shutdown

BwOP-DG-1

Diesel Generator Alignment to Standby Condition

Work Orders

4952653

1B Diesel Generator Operability Semi-Annual Surveillance

2/12/2020

4983010

OP ASME Surveillance Requirement for 2B Residual Heat

Removal Pump

01/14/2020

5002800

1B Diesel Generator Operability Monthly Surveillance

2/12/2020

71114.06

Procedures

EP-AA-1000

Standardized Radiological Emergency Plan

EP-AA-1001

Radiological Emergency Plan Annex for Braidwood Station

71151

Miscellaneous

NRC Performance Indicator Data; Initiating Events -

Unit/Reactor Shutdown Occurences

01/2019 -

2/2019

NRC Performance Indicator Data; Initiating Events -

Unplanned Power Changes per 7000 Critical Hours

01/2019 -

2/2019

Procedures

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator Data 15

LS-AA-2010

Monthly Data Elements for NRC/WANO Unit/Reactor

Shutdown Occurrences

LS-AA-2030

Monthly Data Elements for NRC Unplanned Power Changes

per 7000 Critical Hours

71152

Corrective Action

Documents

272501

Notification of Code Nonconformance for Replacements

Steam Generators

08/16/2020

Corrective Action

Documents

Resulting from

Inspection

4319744

NCR Identified Typo in UFSAR Table 3.9-6

2/20/2020

Engineering

Changes

EC 630375

Issue Revision 009 to Design Specification 18-1229648 for

U1 BWXT Replacement Steam Generators

Procedures

NO-AA-10

Quality Assurance Topical Report (QATR)

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP Procedure)

PI-AA-125-1001

Root Cause Analysis Manual

PI-AA-125-1003

Corrective Action Program Evaluation Manual

5