IR 05000456/2020001
| ML20112F313 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 04/21/2020 |
| From: | Hironori Peterson Region 3 Branch 3 |
| To: | Bryan Hanson Exelon Generation Co, Exelon Nuclear |
| References | |
| IR 2020001 | |
| Download: ML20112F313 (17) | |
Text
April 21, 2020
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000456/2020001 AND 05000457/2020001
Dear Mr. Hanson:
On March 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station, Units 1 and 2. On April 15, 2020, the NRC inspectors discussed the results of this inspection with Mr. J. Keenan, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Hironori Peterson, Chief Branch 3 Division of Reactor Projects
Docket Nos. 50-456; 50-457 License Nos. NPF-72 and NPF-77
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000456 and 05000457
License Numbers:
Report Numbers:
05000456/2020001 and 05000457/2020001
Enterprise Identifier: I-2020-001-0040
Licensee:
Exelon Generation Company, LLC
Facility:
Braidwood Station, Units 1 and 2
Location:
Braceville, IL
Inspection Dates:
January 01, 2020 to March 31, 2020
Inspectors:
D. Betancourt-Roldan, Senior Resident Inspector
J. Bozga, Senior Reactor Inspector
D. Kimble, Senior Resident Inspector
P. Smagacz, Resident Inspector
J. Weigandt, Reactor Engineer
R. Bowen, Illinois Emergency Management Agency
Approved By:
Hironori Peterson, Chief
Branch 3
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Units 1 and 2 both began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, both units remained operating at or near full power for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/readingrm/doc-collections/insp-manual/inspection-procedure/index.html.
Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. From January 1 - March 19, 2020, the inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; and observed risk significant activities when warranted. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In the cases where it was determined the objectives and requirements could not be performed remotely, management elected to postpone and reschedule the inspection to a later date.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial equipment alignment verifications of the following systems/trains:
- (1) The Unit 0 and Unit 1 Station Air Compressors (SACs) with the 2A SAC undergoing commissioning testing (elevated risk activity) during the week ending February 22, 2020.
- (2) The 2B Safety Injection (SI) Train during a 2A SI Train maintenance work window during the week ending February 29, 2020.
- (3) The 1B Auxiliary Feedwater (AF) Train following return to service after maintenance during the week ending March 21, 2020.
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated system configurations during a complete alignment verification of the Unit 1 SI System during the weeks ending March 14, through March 28, 2020.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting physical inspections and reviews to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Fire Zone 3.2A-2: Unit 2 Lower Cable Spreading Room during the week ending March 21, 2020.
- (2) Fire Zone 4.5-2: Division 22 Miscellaneous Electrical Equipment Room and Battery Room during the week ending March 28, 2020.
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the training and performance of the station's fire brigade during observation of an unannounced fire drill on January 31, 2020.
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated the station's internal flooding mitigation protections for the following areas:
- (1) The Unit 1 Diesel Fuel Oil Storage Rooms during the week ending January 25, 2020.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Main Control Room during various activities involving on-watch operations crews during the weeks ending February 22 through February 28, 2020.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a crew of licensed operators during a graded casualty scenario in the station's simulator on January 30, 2020.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remained capable of performing their intended functions:
- (1) The facility's permanently installed station air compressors (SACs) during the weeks ending January 25 through February 1, 2020.
- (2) The Unit 2 pressurizer heaters during the weeks ending March 28 through March 31, 2020.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the licensee's assessment of risk associated with the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Various performance issues and repairs on all three SACs during the weeks ending January 25 through February 1, 2020.
===1931687 during the week ending February 29, 2020.
- (3) Troubleshooting and repairs to the Unit 2 Containment Emergency Airlock as documented in WO 4640976 during the weeks ending March 14 through March 21, 2020.
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01)===
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Issues with structural fireproofing coatings in the Unit 2 Lower Cable Spreading Room as documented in IR 4304844 during the weeks ending January 18 through January 25, 2020.
- (2) Issues with diesel generator jacket water leakage from the 2DG01KB-X2 lower cooler leak as documented in IR 4312030 during the weeks ending January 25 through February 1, 2020.
- (3) An adverse trend associated with multiple issues/failures of Unit 2 pressurizer heaters as documented in IR 4322388 during the weeks ending March 14 through March 28, 2020.
- (4) An emergent issue that resulted from a failure of the Unit 2 containment emergency airlock door interlocks as documented in IR 4325451 during the weeks ending March 14 through March 28, 2020.
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:
- (1) Functional acceptance testing for a newly installed fourth station air compressor (SAC 2A) per Engineering Change (EC) 627885 and as documented in Work Order (WO)
===4959489 during the weeks ending February 8 through February 22, 2020.
- (2) Functional testing of the 1B AF Train following planned maintenance activities per WOs 4898748 and 5011451 during the weeks ending March 14 through March 21, 2020.
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance testing activities:
Surveillance Tests (other) (IP Section 03.01)
(1)1BwOSR 3.8.1.2-2: 1B EDG Semiannual Surveillance during the week ending February 15, 2020.
Inservice Testing (IP Section 03.01)===
(1)2BwOSR 5.5.8.RH-5B: Group A Inservice Test Requirements for Residual Heat Removal Pump 2RH01PB during the week ending January 18, 2020.
(2)1BwOSR 5.5.8.CS-3B: Comprehensive Full Flow Test for 1B Containment Spray Pump (1CS01PB), and Check Valves 1CS003B, and 1CS011B during the week ending March 14, 2020.
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated the station's Emergency Response Organization during the performance of a site-wide drill on February 1,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors reviewed and verified selected portions of the licensee's performance indicator submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
- (1) Unit 1 (January 2019 - December 2019)
- (2) Unit 2 (January 2019 - December 2019)
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)
- (1) Unit 1 (January 2019 - December 2019)
- (2) Unit 2 (January 2019 - December 2019)
IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)
- (1) Unit 1 (January 2019 - December 2019)
- (2) Unit 2 (January 2019 - December 2019)
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)
The inspectors reviewed the licensees implementation of their corrective action program related to the following issue:
- (1) The notification of a Code nonconformance for the Unit 1 replacement steam generators as documented in IR 4272501 during the week ending February 22, 2020.
71153 - Followup of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)
- (1) For the COVID-19 National Emergency declared by the President of the United States, the inspectors performed various reviews and the tracking of licensee actions during the weeks ending March 21 through March 31, 2020.
Event Report (IP Section 03.02) (1 Partial)
The inspectors evaluated the following licensee event reports (LERs):
(1)
(Partial)
LER 05000456/2019-001-00, Unit Trip on Low Steam Generator Level Due to Failure of a Controller on a Feedwater Regulating Valve. (ADAMS Accession Number ML19324D929)
The inspection conclusions associated with this LER are documented in Inspection Report 05000456/2020010 and 05000457/2020010. (ADAMS Accession Number ML20086G679)
INSPECTION RESULTS
Observation: Notification of Code Nonconformance for Replacements Steam Generators 71152 The inspectors performed a detailed review of Issue Report (IR) 4272501, Notification of Code Nonconformance for Replacements Steam Generators. The manufacturer of the licensees replacement steam generators (RSGs) for Byron Unit 1 and Braidwood Unit 1 had recently identified that volumetric examination of a nozzle weld repair that was accomplished by the manufacturer prior to the delivery of the RSGs to the licensee had not been performed, contrary to American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section III, Class 1, requirements. The affected nozzles were the 3-inch diameter blowdown and recirculation nozzles. The nozzles were fabricated by weld metal buildup as permitted by NB-4244(c). The manufacturer determined that the nozzles required repair of surface indications; the manufacturers records did not indicate the depth of the excavations and no post-repair volumetric examinations were performed.Section III, Division 1, Subsection NB-4453.4 of the ASME Boiler and Pressure Vessel Code requires a volumetric exam when the excavation exceeds the lesser of 10 percent of the section thickness or 3/8 inch. For this Problem Identification and Resolution Annual Sample, the inspectors focused on assessment of the licensees corrective actions taken to date and those planned from this point forward.
The licensee performed an engineering change which included an ASME code class reconciliation for the 3-inch diameter blowdown and recirculation nozzles. This reconciliation involved a section by section evaluation applicable to nozzle weld buildups to determine the ASME Code Class 1 versus the ASME Code Class 2 requirements. The licensee determined based on their code class reconciliation that the blowdown and recirculation nozzles could be classified as ASME Code Class 2 (Subsection NC). Since Section III, Subsection NC (4453.4 and 5254), of the ASME Boiler and Pressure Vessel Code requires volumetric examination for nozzle weld buildups after weld repair only if the nozzles diameter is 6-inch or greater, this code reconciliation resolved the ASME Code nonconformance.
The inspectors concluded that the licensees actions taken in accordance with their corrective action program were reasonable given the overall safety significance of the issue. The inspectors did not identify any findings or violations of NRC requirements in the course of their review.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On April 15, 2020, the inspectors presented the integrated inspection results to Mr. J. Keenan, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Drawings
M-61
Diagram of Safety Injection Sheet 1A
BJ
M-61
Diagram of Safety Injection Sheet 6
AX
M-61
Diagram of Safety Injection Sheet 3
Engineering
Changes
M-61
Diagram of Safety Injection Sheet 1B
BF
Fire Plans
M-61
Diagram of Safety Injection Sheet 2
AJ
Procedures
1BwOSR 3.5.2.2-
Unit One ECCS and CS Venting and Valve Alignment / UT
Verification Surveillance
BwOP AF-E1
Electrical Lineup - Unit 1 Operating
BwOP AF-M1
Operating Mechanical Lineup Unit 1
BwOP SA-E1
Electrical Lineup - Unit 1, Station Air System Operating
BwOP SA-E2
Electrical Lineup - Unit 2, Station Air System Operating
BwOP SA-M1
Operating Mechanical Lineup - Unit 0
BwOP SA-M2
Operating Mechanical Lineup - Unit 2
BwOP SI-E1
Electrical Lineup - Unit 1 Operating
BwOP SI-M1
Operating Mechanical Lineup Unit 1
Radiation Work
Permits (RWPs)
4964464
U1 ECCS V/V M2 Entry Ascending
10/20/2019
Work Orders
4987403
U1 ECCS Venting and Vlv Alignment Quarterly
03/05/2020
4993365
U1 ECCS Venting and Vlv Alignment Semi-Annual Inside
Containment
03/05/2020
Fire Plans
Pre-Fire Plan 76
Fire Zone 8.5-2; Tubine Building Mezzanine Floor (SE)
Pre-Fire Plan No.
Fire Zone 3.2A-2; CSR 439 Unit 2, Nonsegregated Bus Duct
Area
Pre-Fire Plan
No.48
Fire Zone 5.4-2; Division 22 Miscellaneous Electrical
Equipment Room and Battery Room, 451 Elevation
Miscellaneous
Fire Drill Scenario
20.20.01.30
Transient Combustible Fire
01/30/2020
Procedures
BwAp 1110-1
Fire Protection Program System Requirements
BwAP 1110-3
Plant Barrier Impairment Program
Procedures
BwOP PBI-1
Plant Barrier Impairment Program Pre-Evaluated Barrier
Matrix
Plant Barrier Control Program
High Risk Fire Area Identification
ER-BR-600-1069
Site List of High Risk Fire Areas - Braidwood Unit 1 and Unit
Fire Protection System Impairment Control
Pre-Fire Plan Manual
Control of Transient Combustible Material
Control of Transient Combustible Material
Fire Prevention for Hot Work
Corrective Action
Documents
Resulting from
Inspection
210831
NRC Identified Removed 1OD01PA Staged too Close to
Transfer
01/14/2019
Drawings
M-48
Diagram of Miscellaneous Sumps & Pumps
M-50
Diagram of Diesel Fuel Oil Unit 1
BA
71111.11Q Procedures
Watch-Standing Practices
OP-AA-101-111-
1001
Operations Standards and Expectations
Operator Fundamentals
OP-AA-101-113-
1006
4.0 Crew Critique Guidelines
OP-AA-103-102-
1001
Strategies for Successful Transient Mitigation
Operation of Plant Equipment
Communications
OP-AA-108-107-
1002
Interface Procedure Between BGE/COMED/PECO and
Exelon Generation (Nuclear/Power) for Transmission
Operations
Operating Narrative Logs and Records
Reactivity Management
Systematic Approach to Training Process Description
Operator Training Programs
Conduct of Simulator Training and Evaluation
Examination Security and Administration
Simulator Management
TQ-BR-201-0113
Braidwood Training Department Simulator Examination
Security Actions
Corrective Action
Documents
4305913
Unexpected Annunciator: 2-12-B6
2/23/2019
4308965
2RY03EB Heater 40 was Found Degraded
01/09/2020
4310328
Found 2 Heater Deficiencies
2/24/2020
4311227
Entry into 0/1/2 BwOA SEC-4 Lowering Instrument Air
Header Pressure
01/19/2020
4311429
Temporary Air Compressors Problems
01/20/2020
4311433
2SA01C Oil level Above High Mark on Sightglass
01/20/2020
4311692
2SA01C Oil Mist Emanating from Oil Mist Eliminator
01/21/2020
4311729
Small Amount of Valve Seat Rubber Material Missing
0SA140
01/22/2020
4311798
2SA01C U2 SAC Rising Vibrations
01/22/2020
4311924
0SA140 Installed without Internal Liner
01/22/2020
4312008
U-0 SAC Trip
01/23/2020
4312018
U1 SAC 2nd Stage Intercooler Leak
01/23/2020
4312287
Water Leaking from 2SA03M
01/23/2020
4312908
Water Found in Oil Sample of U2 Station Air Compressor
(SAC)
01/27/2020
21350
2RY03EA Breaker B5B was Found in Tripped Position
2/25/2020
22388
Trend IR for U2 RY Heaters
2/28/2020
Drawings
113E760
Pressurizer Heater Power Distribution Requirements and
Suggested Heater Groupings
B
Miscellaneous
Disconnect Unit 2 Pressurizer Heaters #17, #18, #40, #69,
- 70 & Open Breakers 2RY03EA-B5A/B5B for Heaters #13,
- 14, #37
Procedures
Maintenance Rule Functions - Safety Significant
Classification
Maintenance Rule Implementation per NEI 18-10
Maintenance Rule 18-10 - Scoping
Maintenance Rule 18-10 - Failure Definitions
Maintenance Rule 18-10 - Performance Monitoring and
Dispositioning Between (a)(1) and (a)(2)
Corrective Action
Documents
4311227
Entry into 01/2 BwOA SEC-4 for Lowering Instrument Air
Header Pressure
01/19/2020
4311429
Temporary Air Compressor Problems
2/20/2020
4311798
2SA01C - Unit 2 SAC Rising Vibrations
01/22/2020
4311924
OSA140 Installed Without Internal Liner
01/22/2020
4312018
Unit 1 SAC 2nd Stage Intercooler Leak
01/23/2020
21013
2A Safety Injection Cubicle Cooler (2VA04SA) Divider Plate
Requires Repair
2/24/2020
Corrective Action
Documents
Resulting from
Inspection
4312008
Unit 0 SAC Trip
01/23/2020
Drawings
M-54, Sheet 1A
Diagram of Service Air - Units 1 and 2
M-54, Sheet 1B
Diagram of Service Air - Units 1 and 2
M-54, Sheet 2
Diagram of Service Air - Units 1 and 2
AH
M-55, Sheet 1
Diagram of Instrument Air
Engineering
Changes
Evaluate Minimum Wall Criteria and Gasket Mating Surface
Requirements for Safety Injection Pump Cubicle Coolers
Operability
Evaluations
BwAR 0-39-B2
SAC 2 Trouble
Procedures
1BwOA SEC-4
Loss of Instrument Air - Unit 1
107
2BwOA SEC-4
Loss of Instrument Air - Unit 2
106
BwAR 1-12-D7
Pressurizer PORV Supply Pressure High/Low
BwMP 3100-
077A1
Installation and Removal of Temporary Air Compressors
BwOA SEC-4
Loss of Instrument Air - Unit 0
104
BwOP SA-1
Startup and Operation of Station Air Compressors
- 48
BwOP SA-2
Shutdown of the Station Air Compressors
BwOP SA-8
Aligning Service Air Compressor for Standby Operation
ASME Section XI Repair/Replacement Program
ER-AA-335-015-
2013
VT-2 Visual Examination in Accordance with ASME 2013
Service Water Heat Exchanger Inspection Guide
Risk Management
On-Line Risk Management
Conduct of Troubleshooting
Protected Equipment Program
On-Line Risk Management and Assessment
Work Orders
1931687
2VA04SA: Clean and Inspect 2A Safety Injection Pump
Cubicle Cooler
2/24/2020
4640976
Unit 2 Containment Emergency Airlock
Troubleshooting/Repair
03/12/2020
4989830
Hook Up Temporary Air Compressors
01/19/2020
Corrective Action
Documents
4304844
Fireproofing Missing From Ceiling in Lower Cable Spreading
Room
2/18/2019
4310367
2FIS-611 Initially Suspect During 2B RH ASME Run
01/14/2020
4312030
2DG01KB-X2 Jacket Water Lower Cooler Leak
01/23/2020
21350
2RY03EA Breaker B5B was Found in Tripped Position
2/25/2020
22388
Trend Issue Report for Unit 2 Pressurizer Heaters
2/28/2020
25451
Unit 2 Emergency Hatch Doors Unable to be Opened
03/10/2020
Procedures
2BwOSR 3.8.1.2-
Unit Two 2B Diesel Generator Operability Surveillance
Work Orders
4995339
LR-IST-2B Emergency Diesel Generator Monthly
Surveillance
01/22/2020
Corrective Action
Documents
4317383
Multiple Small Leaks on 2A Station Air Compressor
2/12/2020
4317384
2A Station Air Compressor Start Permissive Discovery
2/12/2020
4317760
2A Station Air Compressor Increase of Discharge Pressure
2/13/2020
4318080
2A Station Air Compressor - Oil Filter Differential Pressure
Value is Not Valid
2/14/2020
26219
Oil Level Out of Band for 1AF01PB - 1B Auxiliary Feed
Pump
03/12/2020
Engineering
Changes
27885
Install Fourth Station Air Compressor
Miscellaneous
Night Shift Unit 1 Control Room Logs
03/13/2020
Procedures
1BwOSR
5.5.8AF-3B
Group A Inservice Testing Requirements for Unit 1 Diesel-
Driven Auxiliary Feedwater Pump
BwOP AF-7
Auxiliary Feedwater Pump B (Diesel) Startup on Recirc
Configuration Change Acceptance Testing Criteria
SPP 20-001
Modification Test for 2SA02C Station Air Compressor
On-Line Work Control Process
Work Orders
4959489
Install Fourth Station Air Compressor per EC 627885
03/03/2020
Corrective Action
Documents
4310367
2FIS-611 Initially Suspect During 2B RH ASME Run
01/14/2020
4317240
1DG01KB-Y2: 1B Diesel Generator Lower Lube Oil Cooler
Leak While Loading
2/12/2020
27401
1BwOSR 5.5.8.CS-3B: 1B CS D/P EDG Uncertainties
(CA2644573)
03/17/2020
Procedures
1BwOSR 3.8.1.2-
1B Diesel Generator Operability Surveillance
1BwOSR
5.5.8.CS-3B
Comprehensive Full Flow Test for 1B Containment Spray
Pump (1CS01PB) and Check Valves 1CS003B, 1CS011B
2BwOSR
5.5.8.RH-5B
Group A IST Requirements for Residual Heat Removal
Pump 2RH01PB
BwOP DG-11
Diesel Generator Startup and Operation
BwOP DG-12
Diesel Generator Shutdown
BwOP-DG-1
Diesel Generator Alignment to Standby Condition
Work Orders
4952653
1B Diesel Generator Operability Semi-Annual Surveillance
2/12/2020
4983010
OP ASME Surveillance Requirement for 2B Residual Heat
Removal Pump
01/14/2020
5002800
1B Diesel Generator Operability Monthly Surveillance
2/12/2020
Procedures
Standardized Radiological Emergency Plan
Radiological Emergency Plan Annex for Braidwood Station
71151
Miscellaneous
NRC Performance Indicator Data; Initiating Events -
Unit/Reactor Shutdown Occurences
01/2019 -
2/2019
NRC Performance Indicator Data; Initiating Events -
Unplanned Power Changes per 7000 Critical Hours
01/2019 -
2/2019
Procedures
Collecting and Reporting of NRC Performance Indicator Data 15
Monthly Data Elements for NRC/WANO Unit/Reactor
Shutdown Occurrences
Monthly Data Elements for NRC Unplanned Power Changes
per 7000 Critical Hours
Corrective Action
Documents
272501
Notification of Code Nonconformance for Replacements
08/16/2020
Corrective Action
Documents
Resulting from
Inspection
4319744
NCR Identified Typo in UFSAR Table 3.9-6
2/20/2020
Engineering
Changes
Issue Revision 009 to Design Specification 18-1229648 for
U1 BWXT Replacement Steam Generators
Procedures
Quality Assurance Topical Report (QATR)
Issue Identification and Screening Process
Corrective Action Program (CAP Procedure)
Root Cause Analysis Manual
Corrective Action Program Evaluation Manual
5