IR 05000454/2025003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000454/2025003 and 05000455/2025003
ML25346A020
Person / Time
Site: Byron  
Issue date: 12/12/2025
From: Dariusz Szwarc
NRC/RGN-III/DORS/RPB3
To: Mudrick C
Constellation Energy Generation
References
IR 2025003
Download: ML25346A020 (0)


Text

SUBJECT:

BYRON STATION - INTEGRATED INSPECTION REPORT 05000454/2025003 AND 05000455/2025003

Dear Christopher H. Mudrick:

On September 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Byron Station. On December 10, 2025, the NRC inspectors discussed the results of this inspection with Harris Welt, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown. However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300. On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025, 3rd quarter integrated inspection reports normally issued by November 15, 2025, to December 31, 2025. The NRC will resume the routine cycle of issuing inspection reports on a quarterly basis beginning with the calendar year 2025, 4th quarter integrated inspection reports, which will be issued 45 days after the 4th quarter ends on December 31, 2025.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

December 12, 2025 If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Byron Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Dariusz Szwarc, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454 and 05000455 License Nos. NPF-37 and NPF-66

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000454 and 05000455

License Numbers:

NPF-37 and NPF-66

Report Numbers:

05000454/2025003 and 05000455/2025003

Enterprise Identifier:

I-2025-003-0057

Licensee:

Constellation Nuclear

Facility:

Byron Station

Location:

Byron, IL

Inspection Dates:

July 01, 2025, to September 30, 2025

Inspectors:

N. Bolling, Resident Inspector

T. Hooker, Health Physicist

M. Learn, Team Leader

T. Ospino, Resident Inspector

C. Padilla, Senior Resident Inspector

Approved By:

Dariusz Szwarc, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Byron Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71111.1

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power and remained at or near full power throughout the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)partial walkdown of the 1A emergency diesel generator (EDG) on July 9, 2025 (2)partial walkdown of the 1A auxiliary feedwater train prior to other train work on July 17, 2025

71111.05 - Fire Protection

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1)observation and evaluation of the stations fire brigade during an announced fire drill on July 15, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1)observation of various activities involving on-watch operations crews in the main control room during the week ending September 5, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)observation of the performance of a complex casualty graded scenario by a crew of licensed plant operators in the facilitys simulator on August 12, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples 1 Partial)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)

(Partial) maintenance effectiveness review of the 0A essential service water makeup pump (2)review of work practices and challenges generated during the work window associated to the Unit 2B safety injection unplanned maintenance on the week ending July 11, 2025 (3)review of work practices related to the EDG control air system and the maintenance and operability implications for the week ending August 22, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)review and evaluation of the risk associated with dry cask storage activities, as documented in various work orders (2)risk assessment of the week of September 2, 2025, due to multiple opposite train planned work

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)evaluation of the operability of 1B EDG starting air system, as documented in various action requests (ARs)

(2)evaluation of the operability of 1A EDG after control air loss, as documented in AR 4884396 (3)evaluation of the operability of 2A main steam isolation valve (MSIV) upon discovery of a non-safety-related gauge installed on the safety-related train, as documented in AR 4889796 (4)evaluation of the functionality of four non-safety-related diaphragms installed on the 2A auxiliary feedwater train which is safety related, as documented in various ARs

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1)functional and operational testing of the 2B safety injection train test after failed air test of the 2B SI pump cubicle cooler, as documented in Work Order (WO) 5677654 (2)functional and operational testing of 1B EDG following replacement of 1DG5212B turning gear interlock valve, as documented in WO 5681243 (3)functional and operational testing of DC 211 battery following cell replacement, as documented in WO 5678488 (4)functional and operational testing of 0A SX makeup pump following fuel line repairs, as documented in WO 5535776

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) BOP IC-3, Moveable Incore Detectors Flux Mapping Procedure, on July 23, 2025 (2)2BOSR 7.5.4-2, Unit Two Diesel Driven Auxiliary Feedwater Pump Monthly Surveillance, on August 5, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)1BOSR 5.5.8.CS.5-2c, Unit One Comprehensive Inservice Testing (IST) Requirements for Containment Spray Pump 1CS01PB, as documented in WO 5647834

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1)emergency preparedness drill on July 24, 2025

Additional Drill and/or Training Evolution

The inspectors evaluated:

(1)emergency preparedness drill before evaluated NRC drill on September 17,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (1 Sample)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 2, essential service water process monitor, 2PR03J

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (3 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1)auxiliary building ventilation system, including Unit 1 auxiliary building ventilation effluent monitor (1RE-PR028) and the Unit 2 auxiliary building vent effluent monitor (2RE-PR028)

(2)liquid effluent discharge system, including the effluent release tanks, and radwaste release tank monitor (0RE-PR01J)

(3)gaseous radwaste system, including gaseous decay tanks, sampling station, and radiological waste control room

Sampling and Analysis (IP Section 03.02) (3 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1)gaseous effluents released from the Unit 2 auxiliary building vents (2)liquid effluents released from the liquid effluent discharge system (3)gaseous effluents released from the gaseous decay tanks

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1)permit number L-20250507-465-B; Liquid Release Tank 0WX01T; May 5, 2025 (2)permit number G-20250331-2224-B; Unit 2 Containment Purge; April 14, 2025

Abnormal Discharges (IP Section 03.04) (1 Sample)

The inspectors evaluated the following abnormal discharges:

(1) 2023 gaseous abnormal release

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative (GPI) program to identify incomplete or discontinued program elements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (July 1, 2024, through June 30, 2025)
(2) Unit 2 (July 1, 2024, through June 30, 2025)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (February 1, 2024, through August 31, 2025)
(2) Unit 2 (February 1, 2024, through August 31, 2025)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) May 1, 2024, through August 31, 2025 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) April 1, 2024, through August 31, 2025

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors reviewed the implementation and tracking of the essential service water fouling monitoring program (BVP 800-30) and extent-of-condition exams.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1)non-safety-related equipment installed as safety-related parts on safety-related trains

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.15 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: 10 CFR 50, Appendix B, Criterion VIII, Identification and Control of Materials, Parts, and Components, requires, in part, that identification and control measures shall be designed to prevent the use of incorrect or defective material, parts, and components.

Contrary to above, the licensee failed to establish measures for the identification and control of materials, parts, and components. Specifically, the licensee failed to ensure Procurement Classification 1 (QL-1), Safety Related, components were selected for replacement in safety-related components, as required by step 4.1 of site procedure SM-AA-300-1002, Revision 11, Bill of Material Development and Right Parts Selection for Maintenance, when a non-safety-related (NSR) gauge and four NSR diaphragms were installed in safety-related systems and constitutes a performance deficiency. The NSR gauge was installed on the pressure sensing line of the 2A main steam isolation valve accumulator on April 27, 2021, discovered on August 12, 2025, and replaced on September 5, 2025. The four NSR diaphragms were installed in the 2AF005A through 2AF005D auxiliary feedwater flow control valves on April 18, 2025, discovered on August 27, 2025, and replaced on October 29, 2025.

Significance/Severity: Green. The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green)because they answered Yes to question 1 in Exhibit 2, Mitigating Systems Screening Questions.

Corrective Action References:

AR 4889796, NSR Pressure Gauge Installed in SR Application AR 4893579, NSR Diaphragm Installed in 2AF005A AR 4893583, NSR Diaphragm Installed in 2AF005B AR 4893585, NRS Diaphragm Installed in 2AF005C AR 4893586, NSR Diaphragm Installed in 2AF005D Observation: Non-Safety-Related Equipment Installed as Safety-Related Parts on Safety-Related Trains 71152S The inspectors conducted a review of plant issues, with a focus on entries in the licensees corrective action program over recent months. This review identified a potential negative trend involving the installation of non-safety-related (NSR) components in safety-related (SR)applications.

1. NSR Pressure Gauge Installed in SR Application (AR 4889796)

A non-safety-related, Quality Level 4, pressure gauge (Part 2PI-MS251A) was installed on the safety-related 2A main steam isolation valve (MSIV) train under Work Order (WO)4569070 on April 27, 2021. This gauge, which serves as the accumulator tank pressure indicator, remained in place for over 4 years without detection when the error was discovered on August 12, 2025. Although a past operability determination was performed, which determined there was no reason to suspect the pressure boundary would fail during a design basis event, the gauge was isolated immediately and subsequently replaced with a safety-related pressure gauge on September 5, 2025.

2. NSR Diaphragms Installed in SR Auxiliary Feedwater Flow Control Valves

(ARs 4893585, 493583, 493585, 493586)

During the most recent Unit 2 outage, four NSR, Quality Level 4 diaphragms, were installed in place of SR, qualified diaphragms in the 2A auxiliary feedwater system flow control valves (2AF005A-D), under WOs 5411043, 5411042, 5411041, and 5411040, respectively.

The installation followed procedure MA-BY-MM-4-AF005, Revision 7, 1/2AF005A Through H Valve Repair. This issue was identified not through routine checks but as a result of a question raised by Braidwood Nuclear Plant regarding preventive maintenance frequency.

A functionality evaluation (EC 645425) was conducted, which noted that the NSR diaphragms had undergone a parts quality initiative (PQI) inspection prior to use. Although no operability concerns were identified, the licensee replaced the diaphragms with Quality Level 1 components on October 29, 2025.

In both cases, the licensee failed to meet the requirements of SM-AA-300-1002, Revision 11, Bill of Material Development and Right Parts Selection for Maintenance. Step 4.1.4 states, in part, Only Safety Related item/components (Cat ID Quality Level 1 or 2) are permissible for use, in Configuration Level 1 (Safety-Related Equipment). These oversights represent lapses in human performance which could have led to more significant consequences.

Upon discovery, the licensee did perform extent-of-condition searches and took action to replace the affected parts. The licensee also expanded the scope by including evaluation of ARs generated as a result of a potential for incorrect parts to be installed in generation of a Trend IR, AR 4901934, in order to evaluate their parts selection process performance.

The licensee identified opportunities to improve training and the parts selections. However, it is also important to stress the importance of acquiring parts that meet the design and manufacturing requirements under a quality assurance program complying with 10 CFR 50, Appendix B and their role in ensuring the continued reliability of structures, systems, and components important to the safe shutdown of the plant.

The screening and significance determinations for the installation of these NSR components are discussed in the licensee-identified non-cited violation attached to this report.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On December 10, 2025, the inspectors presented the integrated inspection results to Harris Welt, Site Vice President, and other members of the licensee staff.
  • On September 11, 2025, the inspectors presented the radiation protection inspection results to Harris Welt, Site Vice President, and other members of the licensee staff.
  • On September 30, 2025, the inspectors presented the radiation protection inspection results to Jason Reed, Manager of RP Programs, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

AR 4880501

NRC ID DG M/E Lineups Need to be Revised

07/09/2025

BOP AF-E1A

Auxiliary Feedwater Train A Electrical Lineup

BOP AF-M1A

Auxiliary Feedwater System Train 'A' Valve Lineup

BOP DG-E1A

Diesel Generator Train A Electrical Lineup

71111.04

Procedures

BOP DG-M1A

Train A Diesel Generator System Valve Lineup

71111.05

Miscellaneous

Fire Drill Scenario

  1. 25-03

Barrel Storage Building

07/15/2025

HU-AA-1211-F-

Pre-Job Briefing Checklist

OP-AA-101-111

Roles and Responsibilities of On-Shift Personal

OP-AA-101-111-

1001

Operation Standards and Expectations

71111.11Q

Procedures

TQ-AA-155

Conduct of Simulator Training and Evaluation

AR 4868384

1A DG Loss of 80# Air Header

05/25/2025

AR 4879681

2VA04SB Welds Repairs Required

07/08/2025

AR 4879924

Delay to LCO Window Due to Additional Welds Needed

07/08/2025

AR 4880326

2B SI Lower Cooler Failed Pressure Test During

Maintenance

07/10/2025

AR 4880525

Active SX Leak from 2VA04SB Lower Cooler

07/10/2025

AR 4880537

Need Contingency Weld Package for Future SI Cooler Work

07/10/2025

AR 4883026

Foreign Material Causes Loss of Control Air - 1A EDG

07/17/2025

AR 4884293

1A DG Output Breaker Opened during Monthly Surveillance

07/22/2025

AR 4884396

1A DG Inoperability Due to Control Air Loss

07/22/2025

AR 4884465

1PI-DG124 Reading Low Turbo Lube Oil Pressure

07/22/2025

AR 4885891

1A DG Non-Essential Control Air Reg Failure

07/25/2025

Corrective Action

Documents

AR 4888432

AR 1A DG Starting Air Systems Have Crosstalk

08/05/2025

71111.12

Drawings

M-152, Sheet 15

MFRs Supplement Diagram of Diesel Generator Control

Diagram Shutdown System

2/05/1998

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

M-152, Sheet 20

Control Diagram Starting System and Alarms

2/06/2013

Failure Analysis

Failure Analysis of Valve, Check, Body Material Aluminum,

Size 1/4 X 1

07/17/2023

Miscellaneous

Maintenance Plan

(Excel file)

2B Safety Injection (2SI01PB) 48hrs of 7d LCO

Work Orders

WO 5698019

1A DG Output Breaker Opened During Monthly Surveillance

07/23/2025

Miscellaneous

Major Activities

for Week

Week: 2536BA A-Train

09/02/2025

BFP FH-69

Hi-Trac Movement Within the Fuel Building

Procedures

OU-AA-630-1000

Spent Fuel Loading Campaign Management

71111.13

Work Orders

WO 5618966

25 Dry Cask Storage Campaign

AR 4815961

1B DG Starting Air Receiver Pressure did not Change

on Start

11/07/2025

AR 4843282

1B DG Starting Air Receiver Pressure Uneven Change

on Start

03/07/2025

AR 4863962

1B DG Starting Air Receiver Pressure Uneven Change

on Start

05/07/2021

AR 4872849

1B DG Starting Receiver Degraded Trend

06/11/2025

AR 4873850

1B DG Starting Air Receiver Pressure Uneven SAT Outage

03/09/2025

AR 4884293

1A DG Output Breaker Opened during Monthly Surveillance

07/22/2025

AR 4884396

1A DG Inoperability Due to Control Air Loss

07/22/2025

AR 4884465

1PI-DG124 Reading Low Turbo Lube Oil Pressure

07/22/2025

AR 4889796

NSR Pressure Gauge Installed in SR Application

08/12/2025

AR 4893579

NSR Diaphragm Installed in 2AF005A

08/27/2025

AR 4893583

NSR Diaphragm Installed in 2AF005B

08/27/2025

AR 4893585

NSR Diaphragm Installed in 2AF005C

2/27/2025

Corrective Action

Documents

AR 4893586

NSR Diaphragm Installed in 2AF005D

08/27/2025

M-152, Sheet

Number 15

MFRs Supplement Diagram of Diesel Generator Control

Diagram Shutdown System

2/05/1998

Drawings

M-152, Sheet

Number 20

Control Diagram Starting Systems and Alarms

2/06/2013

71111.15

Engineering

Changes

EC 345722

Replace MSIV N2 Pressure Gauge with Safety Related

Gauges

04/05/2005

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EC 645425

2AF005A-D Functionality Evaluation for NSR Actuator

Diaphragm

09/04/2025

CES SO-0351

MO-7176

Report of Witness Tests of KSV-20-T Engine-Generator Set

11/30/1979

CES-0420-100

Report of Witness Tests KSV-20T Engine-Generator Set

09/20/1984

Logs

Byron Logs 22-23 July

07/22/2025

Miscellaneous

Past Operability

2A MSIV Past Operability

09/17/2025

WO 4569070

EWP IM Perform Calibration of 2PI-MS251A

04/27/2021

WO 5411040

Rebuild Actuator/Replace Elastomers 2AF005D

04/18/2025

WO 5411041

Rebuild Actuator/Replace Elastomers 2AF005B

04/18/2025

WO 5411042

Rebuild Actuator/Replace Elastomers 2AF005C

04/18/2025

Work Orders

WO 5411043

Rebuild Actuator/Replace Elastomers 2AF005A

04/18/2025

AR 4246114

EC 398675 (EDG Frequency and Voltage Variation)

08/09/2019

AR 4866048

Post-B2R25 Incore Blocked Thimbles

05/07/2025

AR 4872400

2B AF PP is Leaking a Decent Amount of Exhaust to the

Room

06/12/2025

AR 4880326

2B SI Lower Cooler Failed Pressure Test During

Maintenance

07/10/2025

AR 4880754

Minor Active Leak on Lower Cooler of 2VA04SB

07/11/2025

Corrective Action

Documents

AR 4886534

Incore Blocked Thimble #15

07/23/2025

0BOSR 7.9.6-1

Essential Service Water Makeup Pump 0A Monthly

Operability Surveillance

1BOSR

5.5.8.CS.5-2c

Unit One Comprehensive Inservice Testing (IST)

Requirements for Containment Spray Pump 1CS01PB

2BOSR

5.5.8.SI.5-2A

Unit Two Group A Inservice Testing (IST) Requirements for

Safety Injection Pump 2SI01PB

2BOSR 7.5.4-2

Unit Two Auxiliary Feedwater Pump Monthly Surveillance

Procedures

BOP IC-3

Moveable Incore Detectors Flux Mapping Procedure

WO 5535776

Essential Service Water Makeup Pump Support 0BVSR

Z.7.A.6-1

09/23/2025

WO 5647834

OPS Perform 1BOSR 5.5.8.CS.5-2C 1B CS Pump

Comprehensive

07/17/2025

71111.24

Work Orders

WO 5677654

(NEIL)-2SI01PB Group A IST Requirements for Safety

07/11/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Injection Pump

WO 5678488

DC 211 Battery Voltage Low (Cell 44)

09/12/2025

WO 5681243

1B DG Staring Air Receiver Pressure Uneven Change on

Start

09/12/2025

WO 5696620

(NEIL) - 2B Diesel Driven AF Pump Monthly Surveillance

08/05/2025

Byron 2025

Integrated Drill

Byron 2025 Integrated Drill Binder #3

07/24/2025

71114.06

Miscellaneous

Byron 2025 Pre-

Exercise

Byron 2025 Pre-exercise Binder #31

09/17/2025

71124.05

Miscellaneous

2PR03J Calibration Source Tracking

09/30/2025

22 Annual Radioactive Effluent Release Report

04/27/2023

24 Annual Radioactive Effluent Release Report

04/28/2025

Software Quality Assurance for OpenEMS Byron Nuclear

Power Plant

23 Annual Radioactive Effluent Release Report

04/25/2024

21 Annual Radioactive Effluent Release Report

04/02/2022

L-20250507-465-

B

Liquid Permit Release Information

05/07/2025

2C.111

Gaseous Pre-Release Permit Report, Gaseous Release

Permit Report, RP-BY-90-0-0H3 Bubbler, Supporting

Documentation and BCP 400-TCNMT/Continuous

03/31/2025

CY-BY-110-600-1

Chemistry Sample Points - Turbine Building

G-20250822-

29-B

Gas Permit Release Information

08/22/2025

L-20250505-463-

B

Liquid Permit Release Information

05/05/2025

Miscellaneous

L-20250822-488-

B

Liquid Permit Release Information

08/22/2025

CY-AA-170-000

Radioactive Effluent and Monitoring Programs

CY-AA-170-210

Potentially Contaminated Systems Controls Program

CY-AA-170-2300

Determination of Carbon-14 in Gaseous Effluents

CY-BY-170-301

Offsite Dose Calculation Manual for Byron Station Units 1

and 2

71124.06

Procedures

Y-AA-170-1100

Quality Assurance for Radiological Monitoring Programs

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Self-Assessments 04893178

25 RETS/REMP 71124.06 & 71124.07

09/05/2025

Calibration

Records

CY-BY-130-8000

CY-BY-130-8001 Attachment 3 Compositor Performance

Check Sheet, CY-BY-130-8000 Attachment 2

NPDES/Compositor Performance Check Sheet 06/4/2025 -

6/07/2025

06/11/2025

AR 4668429

NOS ID: Correct ODCM for Two Offsite Dosimeters

04/07/2023

AR 4705740

No Flow into CWBD Steel Pot for ODCM Sampling

09/29/2023

AR 4882979

Third Party Lab Issues with RETS/REMP Reports

07/17/2025

Corrective Action

Documents

AR 4886899

CGS Vendor Labs Unable to Meet Ni-63 Specs. on Byron

Fish

07/29/2025

BYRON 2023-

22

22 Annual Radiological Environmental Operating Report

(AREOR)

05/04/2023

BYRON 2024-

28

23 Annual Radiological Environmental Operating Report

(AREOR)

05/09/2024

Miscellaneous

BYRON 2025-

29

24 Annual Radiological Environmental Operating Report

(AREOR)

05/12/2025

0BCSR 12.A.1-7

Radiological Environmental Monitoring, Milk Ingestion -

Monthly

0BCSR 12.B.1-1

Radiological Environmental Monitoring, Land Use Census -

Annual

CY-AA-170-100

Radiological Environmental Monitoring Program

CY-BY-170-301

Offsite Dose Calculation Manual for Byron Station Units 1

and 2

CY-BY-408-416-

Radiological Groundwater Protection Program Sampling

EN-AA-407

Response to Inadvertent Releases of Licensed Materials to

Groundwater, Surface Water, Soil or Engineered Structures

EN-AA-408

Radiological Groundwater Protection Program

EN-AA-408-4000

Radiological Groundwater Protection Program

Implementation

71124.07

Procedures

EN-BY-408-4160

RGPP Reference Material for Byron Generating Station

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Cooling Water

Systems

07/01/2024-

06/30/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Residual Heat

Removal Systems

07/01/2024-

06/30/2025

NRC Performance Indicator Data; Mitigating Systems -

Mitigating System Performance Index for Heat Removal

Systems

07/01/2024-

06/30/2025

LS-AA-2140

Monthly Data Elements for NRC ROP Indicator -

Occupational Exposure Control Effectiveness

various

LS-AA-2150

Monthly Data Elements for NRC ROP Indicator -

RETS/ODCM Radiological Effluent Occurrences

various

Corrective Action

Documents

AR 4495844

0SX98AB - B2R23 UT Inspection Results

04/27/2022

Corrective Action

Documents

Resulting from

Inspection

AR 4820258

NRC ID: NRC Document Request Not Provided in a Timely

Manner

07/15/2025

Engineering

Evaluations

EC 634325

B2R23 Minimum Wall Thickness Evaluation for Raw Water

Program

BVP 800-30

Essential Service Water Fouling Monitoring Program

(GL 89-13 Program Basis Document)

71152A

Procedures

ER-AA-5400-

1001

Raw Water Piping Integrity Management Guide

AR 4889796

NSR Pressure Gauge Installed in SR Application

08/12/2025

AR 4893579

NSR Diaphragm Installed in 2AF005A

08/27/2025

AR 4893583

NSR Diaphragm Installed in 2AF005B

08/27/2025

AR 4893585

NSR Diaphragm Installed in 2AF005C

08/27/2025

AR 4893586

NSR Diaphragm Installed in 2AF005D

08/27/2025

Corrective Action

Documents

AR 4901934

Trend IR: Cases Where the Wrong Parts Were Installed

09/30/2025

71152S

Engineering

Changes

EC 645425

2AF005A-D Functionality Evaluation for NSR Actuator

Diaphragm

09/05/2025