SUBJECT:
UPDATED INSPECTION PLAN FOR BYRON STATION, UNITS 1 AND 2 (REPORT 05000454/2025005 AND 05000455/2025005)
Dear David Rhodes:
The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for Byron Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025 (ML25042A278), the NRC determined that a broad, comprehensive review of the ROP is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented.
August 22, 2025
D. Rhoades
This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 630-829-9803 with any questions you have regarding this letter.
Sincerely, Dariusz Szwarc, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000454, 05000455 and 07200068 License Nos. NPF-37 and NPF-66 Enclosure:
Inspection Plan cc: Distribution via LISTSERV Signed by Szwarc, Dariusz on 08/22/25
D. Rhoades
Letter to David Rhoades from Dariusz Szwarc dated August 22, 2025.
SUBJECT:
UPDATED INSPECTION PLAN FOR BYRON STATION, UNITS 1 AND 2 (REPORT 05000454/2025005 AND 05000455/2025005)
DISTRIBUTION:
Rodney Clagg RidsNrrDorlLpl3 RidsNrrPMByron Resource RidsNrrDroIrib Resource Jack Giessner Mohammed Shuaibi Diana Betancourt-Roldan John Pelchat Jared Heck Jennifer Dalzell R3-DORS ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML25233A261
SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available OFFICE R-III NAME DSzwarc:anm DATE 08/22/2025 OFFICIAL RECORD COPY
Site Inspection Activity Plan Byron 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Force-on-Force Planning and Exercise Weeks - BYR
1,2 7/21/2025 7/25/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 9/22/2025 9/26/2025 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Material Control and Accounting Triennial Inspection - BYR
1,2 7/28/2025 9/1/2025 IP 71130.11 000742 Material Control and Accounting (MC&A)
Radiation Protection Baseline Inspection - BYR
1,2 9/8/2025 9/12/2025 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 9/8/2025 9/12/2025 IP 71124.07 000731 Radiological Environmental Monitoring Program 1,2 9/8/2025 9/12/2025 IP 71151 000746 Performance Indicator Verification Biennial Problem Identification and Resolution Inspection - BYR
1,2 9/15/2025 10/3/2025 IP 71152B 000747 Problem Identification and Resolution Emergency Preparedness Exercise Inspection / Performance Indicator Review - BYR
1,2 8/25/2025 10/24/2025 IP 71114.08 000723 Exercise Evaluation - Scenario Review 1,2 10/20/2025 10/24/2025 IP 71114.01 000716 Exercise Evaluation 1,2 10/20/2025 10/24/2025 IP 71151 001397 Performance Indicator Verification Eplan and EAL Changes Review - BYR
1,2 11/1/2025 12/31/2025 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Corporate Security Baseline Inspection - BYR
1,2 1/19/2026 1/23/2026 IP 71130.01 000733 Access Authorization 1,2 1/19/2026 1/23/2026 IP 71130.08 000740 Fitness-For-Duty Program Security Baseline Inspection - BYR
1,2 2/9/2026 2/13/2026 IP 71130.01 000733 Access Authorization 1,2 2/9/2026 2/13/2026 IP 71130.02 000734 Access Control 1,2 2/9/2026 2/13/2026 IP 71130.08 000740 Fitness-For-Duty Program Inservice Inspection - Unit 1 - BYR
1 3/2/2026 3/20/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
Radiation Protection Baseline Inspection - BYR
1,2 3/9/2026 3/13/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/9/2026 3/13/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 3/9/2026 3/13/2026 IP 71124.04 000728 Occupational Dose Assessment 1,2 3/9/2026 3/13/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation Security Baseline Inspection - BYR
1,2 3/23/2026 3/27/2026 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Prepared on 8/18/2025 10:08:49 AM 1 of 4
Site Inspection Activity Plan 1,2 3/23/2026 3/27/2026 IP 71130.09 001656 Security Plan Changes 1,2 3/23/2026 3/27/2026 IP 71151 001338 Performance Indicator Verification Emergency Preparedness Baseline Inspection / Performance Indicator Verification - BYR
1,2 4/20/2026 4/24/2026 IP 71114.02 000717 Alert and Notification System Testing 1,2 4/20/2026 4/24/2026 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1,2 4/20/2026 4/24/2026 IP 71114.05 000720 Maintenance of Emergency Preparedness 1,2 4/20/2026 4/24/2026 IP 71151 001397 Performance Indicator Verification License Renewal Post Approval Phase 2 - Unit 2 - BYR
1,2 5/18/2026 6/5/2026 IP 71003 000687 Post-Approval Site Inspection for License Renewal Functional Engineering Inspection - Age Related Degradation - BYR
1,2 7/6/2026 7/24/2026 IP 71111.21N.04 001832 Age-Related Degradation Baseline Security Inspection - BYR
1,2 8/10/2026 8/14/2026 IP 71130.05 000737 Protective Strategy Evaluation Inservice Inspection - Unit 2 - BYR
2 9/28/2026 10/16/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
Radiation Protection Baseline Inspection - BYR
1,2 10/5/2026 10/9/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 10/5/2026 10/9/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 10/5/2026 10/9/2026 IP 71124.04 000728 Occupational Dose Assessment 1,2 10/5/2026 10/9/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation EAL & EPlan Changes Review - BYR
1,2 11/1/2026 12/31/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes Byron 2026 Licensed Operator Biennial Requalification Program Inspection
1,2 11/15/2026 11/21/2026 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Radiation Protection Baseline Inspection - BYR
1,2 11/16/2026 11/20/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Security Baseline Inspection - BYR
1,2 1/1/2027 12/31/2027 IP 71130.14 000743 Review of Power Reactor Target Sets Byron January 2027 Initial License Examination
1,2 12/13/2026 12/18/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)
1,2 1/10/2027 1/22/2027 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)
1,2 2/1/2027 2/5/2027 IP 71130.10 000741 Cybersecurity Security Baseline Inspection - BYR
1,2 2/22/2027 2/26/2027 IP 71130.02 000734 Access Control Prepared on 8/18/2025 10:08:49 AM 2 of 4
Site Inspection Activity Plan 1,2 2/22/2027 2/26/2027 IP 71130.09 001656 Security Plan Changes Biennial Problem Identification and Resolution Inspection - BYR
1,2 3/8/2027 3/26/2027 IP 71152B 000747 Problem Identification and Resolution Prepared on 8/18/2025 10:08:49 AM 3 of 4
Site Inspection Activity Plan Byron 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count ISFSI Preoperational and Initial Loading Inspection
5/10/2027 5/14/2027 IP 60855 001001 Operation Of An ISFSI Prepared on 8/18/2025 10:08:49 AM 4 of 4