IR 05000445/2025012
| ML25101A075 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 04/15/2025 |
| From: | Nick Taylor NRC/RGN-IV/DORS/EB1 |
| To: | Peters K Vistra Operations Company |
| References | |
| IR 2025012 | |
| Download: ML25101A075 (1) | |
Text
April 15, 2025
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT - COMPREHENSIVE ENGINEERING TEAM INSPECTION REPORT 05000445/2025012 AND 05000446/2025012
Dear Ken Peters:
On March 10, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Comanche Peak Nuclear Power Plant and discussed the results of this inspection with Hunter A. Schill, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Nicholas H. Taylor, Deputy Director Division of Operating Reactor Safety Docket Nos. 05000445 and 05000446 License Nos. NPF-87 and NPF-89
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000445 and 05000446
License Numbers:
Report Numbers:
05000445/2025012 and 05000446/2025012
Enterprise Identifier:
I-2025-012-0003
Licensee:
Vistra Operations Company LLC
Facility:
Comanche Peak Nuclear Power Plant
Location:
Glen Rose, TX
Inspection Dates:
January 27, 2025, to March 10, 2025
Inspectors:
D. Bryen, Reactor Inspector
W. Cullum, Senior Reactor Inspector
R. Kumana, Senior Reactor Inspector
B. Nwafor, Reactor Inspector
D. Reinert, Senior Reactor Analyst
A. Saunders, Reactor Inspector
F. Thomas, Reactor Inspector
C. Young, Senior Reactor Analyst
Approved By:
Nicholas H. Taylor, Deputy Director
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (teams) inspection at Comanche Peak Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Structures, Systems, and Components (SSCs) (IP section 03.01)===
(1)2ED2, Unit 2 125 VDC Switchboard
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Visual inspection of configuration and material condition
- Sizing and equipment protection calculation
- Maintenance and testing history
- System health report
- (2) BC2ED2-1, Unit 2 Battery Charger
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Visual inspection of configuration and material condition
- Battery and charger sizing calculation
- Maintenance and testing history
- System health report
- (3) CP2-CCATST-01, Unit 2 Component Cooling Water Surge Tank
- Component cooling water system piping and instrumentation diagram
- Vendor manual for installation, operation, and maintenance of the surge tank
- System and abnormal operating procedures
- Corrective action program documents
- Visual inspection of the as-built configuration and material configuration (4)1HV8010A, Unit 1 Pressurizer Safety Relief Valve
- Reactor coolant system piping and instrumentation diagram
- Inservice and diagnostic testing procedures and results
- Vendor manual for installation and testing instructions
- Corrective action program documents (5)2-VAAUSE-08, Unit 2 MDAFW Pump 2-02 Room Cooler Fan
- Piping and Instrumentation diagrams
- Vendor documentation
- Preventative maintenance history
- Visual inspection of the component
- Room cooling load calculations
- Corrective actions related to component
- (6) CP2-MEDGEE-02, Unit 2 Diesel Generator 2-02
- Visual inspection of the as-built configuration and material condition
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Vendor manuals
- System and abnormal operating procedures
- Maintenance and testing history
- System health report
- Calculations for:
a.
Starting air requirements b.
Water cooling requirements c.
Maximum load d.
Fuel requirements
- Corrective action program documents
- (7) CP1-AFAPTD-01, Unit 1 Turbine-Driven Auxiliary Feedwater Pump
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Normal and abnormal operating procedures
- Maintenance and testing history
- System health report
- Design basis calculations and analyses
- Physical walkdown of the component
- Corrective action program documents
- Vendor manuals
- (8) PV-4553, Unit 1, Component Cooling Water Supply Valve to Chiller 1-06
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Normal and abnormal operating procedures
- Maintenance and testing history
- System health report
- Design basis calculations and analyses
- Physical walkdown of the component
- Corrective action program documents
- Vendor manuals
- (9) T1EB4, Unit 1, 6.9 kV Feeder Breaker
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Visual inspection of the as-built configuration and material condition
- Component maintenance history
- System health reports
- Corrective action documentation review
- Component maintenance history and corrective action program documents
- Voltage drop calculations
- Electrical drawings
- Vendor manual and plant design drawings (10)1EB4-1, Unit 1, 480-volt Motor Control Center
- Final Safety Analysis Report, Technical Specifications, and Technical Specifications bases document
- Visual inspection of the as-built configuration and material condition
- Reduced voltage calculations
- Visual inspection of spare breakers in warehouse
- Component maintenance history
- System health reports
- Corrective action documentation review
- Electrical drawings
- Vendor manual and plant design drawings
Modifications (IP section 03.02) (4 Samples)
- (1) FDA-2021-000005-01-00, Safety Chiller Control Panel Modification
- (2) FDA-2023-00009-01-00, Component Cooling Water Heat Exchanger Service Water Relief Valve Replacement
- (3) FDA-2023-000003-01-00, Emergency Diesel Generator RUN/STOP Switch Replacement
- (4) FDA-2023-000068-01-00, Valve Operator 1-8104-MO Springpack Replacement 10 CFR 50.59 Evaluations/Screening (IP section 03.03) (10 Samples)
- (1) EV-TR-2020-009257-1, Unit 1 & 2 Refueling Machine Modification
- (2) EV-TR-2019-009785-2, Rod Control Circuit Surge Suppressors Modification
- (3) FDA-2021-000003-02-00, Revise Design Basis Documents for Main Steam Line Break Containment Analysis
- (4) FDA-2021-000003-01-00, Revise DBD-ME-008 and M1-3007 to Incorporate Revised Loss of Coolant Containment Analyses
- (5) FDA-2021-000053-01-00, Approve Shortening Length of Station Service Water Seismic Restraint Bolts
- (6) FDA-2023-000018-01-00, Abandon the Loose Parts Monitoring System for both Units 1and 2 due to the Removal of this System from the Licensing Basis
- (7) FDA-2021-000054-01-01, Replace in-line Air Filters on the U1 and U2 Power Operated Atmospheric Relief Valves (ARVs)
- (8) FDA-2021-000003-01-00, CR-2015-008785 Accept Void in pipe CT-2-013 Unit 2 Train A CT Point 70
- (9) FDA-2024-000001-01-00, Adding a Vent Valve in the Discharge Piping of 1-02 CCP
- (10) EV-CR-2024-004178-3, Compensatory Action to Manually Run Unit 1 Train B SSW Screen Wash
Operating Experience Samples (IP section 03.04) (3 Samples)
- (1) OER-2022-008061, Review of NRC Regulatory Issue Summary 2022-02, "Operational Leakage"
- (2) OER-2021-003367, Review of NRC Information Notice 2021-01
INSPECTION RESULTS
Very Low Safety Significance Issue Resolution Process: Question on Diesel Generator Frequency Acceptance Criteria 71111.21 M
This issue is a current licensing basis question and inspection effort is being discontinued in accordance with the Very Low Safety Significance Issue Resolution (VLSSIR) process. No further evaluation is required.
Description:
The inspectors identified an issue of concern associated with the performance of Technical Specification (TS) Surveillance Requirement (SR) 3.8.1.11 on May 19, 2023, for the 2-02 diesel generator (DG).
The inspectors reviewed the licensees record of the surveillance test and noted that the licensee had recorded the lowest observed output frequency as 59.8 Hz as read by the licenses Data Acquisition System (DAS). This was below the technical specification acceptance criteria of 59.9 Hz. At the time of the test, the licensee evaluated the data and stated that the test results were acceptable based on the average frequency being above 59.9 Hz.
The inspectors noted that SR 3.8.1.11 requires that the DG:
4. maintains steady state frequency >
= 59.9 Hz and <= 60.1 Hz, and 5. supplies permanently connected, and auto-connected shutdown loads for >= 5 minutes.
Furthermore, the TS Bases state the following:
The specified minimum and maximum frequencies of the DG are 59.9 Hz and 60.1 Hz, respectively. These values are equal to +/- 0.1 Hz of the 60 Hz nominal frequency and are based on DG control system capabilities.
The inspectors were unable to confirm whether the licensee had fully evaluated the capability of all supported safety related loads (e.g. pumps, valves, and other equipment) to perform their safety functions at a steady state frequency below 59.9 Hz.
The inspectors questioned whether the licensee had appropriately reviewed and evaluated the surveillance test data. The inspectors reviewed the available data and discovered a total of seven frequency transients between 59.9 to 59.8 Hz, each of very short duration (i.e. less than one second), in the first five minutes after load sequencing was complete. The licensees evaluation did not describe all of the identified frequency transients.
After discussing the identified concerns with the inspectors, the licensee performed an additional evaluation and determined that the specific transients that occurred during the test would not have impacted the operability of any of the supported safety related loads or adversely impact the safety analysis.
Based on the licensees conclusions, the inspectors do not have a current safety concern with the transients that were observed during this specific test. However, an unresolved question remained as to whether the specific transients observed during the test constituted a failure to meet the surveillance requirement as described in the current licensing basis.
Licensing Basis: The licensee believes that short duration frequency transients outside the band do not represent a failure to maintain steady-state frequency >= 59.9 Hz and <= 60.1 Hz. The licensee also referenced statements in the technical specification bases that discuss short transients.
The inspectors determined that the licensing basis is not explicit as to whether or not the definition of steady state includes any transients during the surveillance test, or whether the requirement to supply connected loads for five minutes also implies that the frequency must be maintained wholly within the specified band for five minutes. The discussions of transients in the bases are explicitly tied to voltage and load, and do not address changes in frequency. Those discussions are also tied to other surveillance requirements and do not explicitly address SR 3.8.1.11.
After considering all available information, the inspectors were unable to conclude whether the practice of allowing short frequency transients outside the specified steady state acceptance criteria for this surveillance test was consistent with the current licensing basis. Also, the inspectors were not able to determine whether either similar or more limiting frequency transients could be considered acceptable for future tests. The inspectors determined that this issue met the criteria for the Very Low Safety Significance Issue Resolution Process because:
- The inspection staff has not been able to conclude that the issue of concern is a violation after considering licensee provided supporting information and relevant information developed during the inspection process.
- The specific condition surrounding the issue of concern cannot have any potential to be Greater than Green.
- The resources required to resolve the current licensing basis question would not effectively and efficiently serve the Agencys mission.
Significance: For the VLSSIR process, the inspectors screened the issue of concern through IMC 0609, Appendix A and determine the issue of concern would likely be Green had a performance deficiency been identified.
Technical Assistance Request: No Technical Assistance Request was processed for this issue.
Corrective Action Reference: CR-2025-000805
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On March 10, 2025, the inspectors presented the Comanche Peak Comprehensive Engineering Team Inspection results to Hunter A. Schill, Plant Manager and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
16435-EEB-005
Voltage drop in D.C. Control Circuits for Class 1E 6.9 KV
004
2-ME-0042
Minimum Allowable Service Water Flow to the Diesel
Generator
2-9222189-000
CPNPP EDG ETAP Dynamic Calculation
DBD-ME-302
Safeguards Building Ventilation System
DBD-ME-311
Safety Chilled Water System
EE-1E-2ED2-2
25V DC Distribution Panel, CP2-ECDPED-04 (2ED2-2)
Bus Based Calculation
EE-EDG-LOAD-
UNIT-2
Unit 2 EDG Loading Calculation
EE-VP-U1-1E
Unit 1 Class 1E Voltage Profile
005
IMT-CA-EQ-0482-
MS10
Service Water Pump Supplemental Calculation
ME-CA-0000-
20
Air Operated Valve Capability Evaluation
ME-CA-0000-
5487
Turbine Driven Auxiliary Feedwater Pump Design
Performance Limit for Inservice Testing
ME-CA-0206-
3147
Auxiliary Feedwater Flow Distribution Evaluation on Turbine
Driven Overspeed
ME-CA-0215-
4054
Diesel Generator Fuel Oil Storage Requirements and Tank
Level Process Set Points
MEB-156
Diesel Generator Fuel Oil Day Tank Technical Specification
Volume
Calculations
MES-071
Operation of Emergency Diesel Generators Without Full
Service Water Flow to JW Heat Exchanger
Corrective Action
Documents
(CR)
24-006866, 2021-008062, 2023-000980, 2018-004603,
2018-004701, 2025-000492, 2021-003196, 2022-008146,
25-000517, 2017-012024, 2023-002718, 2023-002788,
2008-000640, 2024-004178, 2020-002396, 2021-007320,
22-002920, 2022-007252, 2021-007748, CR-2010-
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
005563, CR-2013-006604, CR-2013-008405, CR-2015-
004077, CR-2023-003723, CR-2023-004582, CR-2023-
008360, CR-2024-006967
Corrective Action
Documents
Resulting from
Inspection
(CR)
24-007688, 2025-000322, 2025-000755, 2025-000537,
25-000741, 2025-000755, 2025-000454, 2025-000455,
25-000456, 2025-000457, 2025-000458, 2025-000460,
25-000461, 2025-000463, 2025-000479, 2025-000492,
25-000517, 2025-000544, 2025-000545, 2025-000617,
25-000789, 2025-000813, 2025-000491, 2025-000772,
25-000774, 2025-000790, 2025-000805, 2025-000806,
25-000818
1SB12K110-D001
sh. 7
Shaft Displacement Function diagram individual level
AC Motor Control Centers
018
DBD-EE-041
480 V and 120 V AC Electrical Power Systems
2
DDELE E1-0004
Sheet. A
6.9 KV Auxiliaries One line Diagram Safeguard Buses
DDVEN 076-
09089E-01C
Elementary Diagram Safety Chiller CP1-CHCICE-06
DDVEN_51B5897
Body 30 Actuator 657-B-U Spec A Diaphragm Actuated
Control Valve
D
E1-0005 Sht. A
480V Auxiliaries One Line Diagram Safeguards Buses
e1-0009 Sht. B
Containment And Diesel Generator Safeguard 480 V MCCs
One line Diagram
000
E1-0031 Sheet
019
6.9 KV Switchgear Bus 1EA2 TRANSF T1EB4 Feeder BKR
Schematic Diagram
E2-0137 Sht. -
Core Cooling Monitoring System Core Exit Thermocouple
Rack CP2-EIPRCI-10
M1-0229
Flow Diagram Component Cooling Water System
M2-0215 Sheet G
Flow Diagram Diesel Fuel Oil Piping CP2-MEDGEE-02
M2-02229
Flow Diagram Component Cooling Water System
M2-0302
Flow Diagram - Ventilation Safeguards and Electrical Area
Drawings
M2-2250 Sht. 04A
Instrumentation & Control Diagram Reactor Coolant System
Channel 3611, 3612, 0001/0050
000
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
SK-0000-23-
000018-01-00
SK-0001, SK-0005, SK-0006, SK-0007, SK-0008, SK-0009,
SK-0010, SK-0012, SK-0013, SK-0014, SK-0015 SK-0018,
SK-0019, SK-0020, SK-0021, SK-0022, SK-0023, SK-0026,
SK-0027, SK-0028, SK-0029 Drawings
SK-0002-22-
000041-01-00
DIESEL GENERATOR AIR COMPRESSOR 3 TAG CP1-
MECAED-03
000
SK-0003-22-
000041-01-00
Protective Device Setting 480 V Safeguard Buses
000
SK-0004-22-
000041-01-00
Safeguards And Auxiliary Buildings Safeguard 480V MCCs
One Line Diagram
000
SK-0005-22-
000041-01-00
000
SK-0006-22-
000041-01-00
MCC 1EB2-
000
DBD EE-078
Loose Parts Monitoring System Design Basis Document
DCA 89328
Component Cooling Water Surge Tank Partition Opening
Sizing
ECE-1.06-F10
Engineering Risk/Rigor Assessment
ECE-5.08-F3
Commercial Change Package
ECE-5.21-06
Testing of Digital Systems and Devices
001
EPID-L-2020-
PWROG - Regulatory Relaxation for PWR Loose-Part-
Detection Systems
FDA-2000-
001852-03-00
Safety Chiller Timing Relay Replacement
FDA-2021-
000053-01
Design Equivalent Change Package
FDA-2021-
000054-01
Replace in-line air filters on the U1 and U2 Power Operated
Atmospheric Relief Valves (ARV's)
FDA-2021-
000064-01-00
2-TE-0016 is non-functional. Disable 2-TE-0016 by lifting
wires in the core exit thermocouple rack CP2-EIPRCI-10
000
FDA-2022-
000041-01-00
Replace NEMA size 3 starter with NEMA size 2 starter
000
Engineering
Changes
FDA-2022-
000050-01-00
Prepare a Temporary Modification to block the Thrust Trip
on the Unit 1 TG
000
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
FDA-2023-
000003-01-00
Replace existing Emergency Diesel Generator RUN/STOP
switch with new model
FDA-2023-
000009-01
Component Cooling Water Heat Exchange Station Service
Water Relief Valve Replacement
FDA-2023-
000018-01-00
Abandon the Loose Parts Monitoring System for both Units
1and 2 due to the removal of this system from the Licensing
Basis
09/20/2023
STA-707-4
Applicability Determination for a reduced thread
engagement on certain bolted connections.
23102-C-003
Tornado Missiles Analysis - Terry Turbine Flash Tank
System Steam Exhaust Stacks
Emergency Diesel Generator Train B
000064-01-00
50.59 Screen
000
ER-ME-021
NNS Piping Classification Practices
ER-ME-109
Evaluation of Safety-Related Pump Degradation Issues
EV-TR-2022-
007252-2
Unit 1 Turbine Thrust Bearing Software Trip Block (FDA-
22-000050-01 R. 0)
000
EV-TR-2022-
007252-5
Unit 2 Turbine Thrust Bearing Software Trip Block (FDA-
22-000050-02 )
000
EV-TR-2022-
00752
Unit 1 Turbine Thrust Bearing Software Trip Block
000
Engineering
Evaluations
ODMI 7252
Turbine Shaft Displacement Instrumentation
2
System Health Report - Component Cooling Water
10/02/2024
23-MS-81
Emergency Fan Coil Units Specification
05/02/1988
Code,Section III,
Division 1
Rules for Construction of Nuclear Power Plant Components,
Subsection NF, Component Supports 1974 Edition
07/01/1974
HMTA 6 Stage Turbine Driven Auxiliary Feedwater Pump
Vendor Manual for Air Handling Units
DBD-EE-040
6.9kV Electrical Power System
DBD-ME-011
Diesel Generator Sets
DBD-ME-215
Diesel Generator Fuel Oil Storage and Transfer System
Miscellaneous
DBD-ME-311
Safety Chilled Water System
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
OER-2022-
008061
Operating Experience Report
11/9/2022
ABN-401
Main Turbine Malfunction
015
ABN-502
Component Cooling Water System Malfunctions
ALM-4000A
Digital Alarms
009
CHM-160
Diesel Fuel Oil Testing Program
CLI-650
Determination of Specific Gravity
COP-610
General Use Diesel Fuel Oil
CPES-S-1062G
Fastener Substitution and Heli-Coil Specification
ECE 5.08
Standard Design Process
004
ECE-2.15
Risk and Reliability Functions
ECE-5.05
Design Drawings And Special Documents
EOP-0.0A-R9-
P10
Emergency Response Guidelines for Reactor Trip or Safety
Injection
MSM-C0-8811
Fischer Globe Valve Designs EC, EAC, ES, and EAS
OPT-435B
Train B Integrated Test Sequence
OPT-453B
Train A Safeguards Slave Relay K644 Actuation Test
R&R-PN-004
Auxiliary Feedwater Water
R&R-PN-017A
Electric Power-1E 6.9kV and 480V
R&R-PN-017B
118VAC & DC Electric Power
R&R-PN-019
Safety Chilled Water
SOP-502B
Component Cooling Water System
STA 707
CFR 50.59 And 10 CFR 72.48 Reviews
23
STA-202
Nuclear Generation Procedure Change Process
STA-602
Temporary Modifications and Transient Equipment
Placements
20
STA-661
Non-Plant Equipment Storage and Use Inside Seismic
Category I Structures
STA-716
Modification Process
033
STI-422.01
Operability Determination and Functionality Assessment
Program
STI-606.01
Work Control Process
013
Procedures
STI-744.09
Structural Monitoring Inspection Guide
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
STI-762.02
Risk Managed Technical Specifications - PRA Model
Configuration Control
TSP-503
Emergency Diesel Generator Reliability Program
Work Orders
(WO)
2-006525, 22-547416, 5975767, 22-361464, 22-361458,
5969916, 5125742, 5224954, 5232843, 5232850, 5557839,
5975767, 22-510374, 5593235, 5919995, 24-256522,
4839825, 4913384, 22-448167, 5887235, 5418666,
257170, 5689999, 21-956016, 22-223464, 4778777,
5364176, 5366151, 5847411, 5257170, 5418666, 5887235,
2-394284, 22-431814, 23-390933, 4778777, 5364176,
5366151, 5847411, 22-212685, 22-490334, 21-838956, 22-
27484, 24-546221, 4841076, 22-196613, 22-399074, 22-
24820, 23-473363, 24-449951, 5977516, 21-436153, 21-
570063, 21-701940, 21-702083, 21-880674, 21-880992, 22-
111618, 22-133497, 23-48416, 21-796720, 23-173976,
5661748, 23-178513, 5155927, 5895942, 23-178513, 21-
28466, 23-828438, 4039380, 5364746, 22-1204