IR 05000445/2024012

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000445/2024012 and 05000446/2024012
ML24164A134
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 06/17/2024
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Peters K
Vistra Operating Co. (VistraOpCo)
References
IR 2024012
Download: ML24164A134 (18)


Text

June 17, 2024

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000445/2024012 AND 05000446/2024012

Dear Ken Peters:

On May 16, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Comanche Peak Nuclear Power Plant and discussed the results of this inspection with Al Marzloff, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

Three findings of very low safety significance (Green) are documented in this report. Three of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Comanche Peak Nuclear Power Plant.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Signed by Gaddy, Vincent on 06/17/24 Docket Nos. 05000445, 05000446 License Nos. NPF-87, NPF-89

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000445 and 05000446

License Numbers:

NPF-87 and NPF-89

Report Numbers:

05000445/2024012 and 05000446/2024012

Enterprise Identifier:

I-2024-012-0007

Licensee:

Vistra Operations Company LLC

Facility:

Comanche Peak Nuclear Power Plant

Location:

Glen Rose, TX

Inspection Dates:

April 29, 2024 to May 16, 2024

Inspectors:

W. Cullum, Senior Reactor Inspector

R. Kumana, Senior Reactor Inspector

F. Thomas, Reactor Inspector

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Comanche Peak Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to assure that purchased material conformed to the procurement documents for commercial grade O-rings Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-01 Open/Closed None (NPP)71111.21N.

Inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50,

Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, for failure to assure that purchased material conformed to the procurement documents for commercial grade O-rings.

Failure to review a change in design of a commercial grade item for suitability of parts and materials for safety related chillers Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-02 Open/Closed None (NPP)71111.21N.

The inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50 Appendix B, Criterion III Design Control, when the licensee failed to review a new commercial grade refrigerant filter-drier for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components specific to the unit 1 and 2 safety chillers.

Failure to test for the critical characteristics for Teflon gaskets used in the Emergency Diesel Generator Starting Air System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-03 Open/Closed None (NPP)71111.21N.

Inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50,

Appendix B, Criterion XI, Test Control, when the licensee failed to test for the identified critical characteristics for Teflon gaskets used in the Emergency Diesel Generator starting air system.

Additional Tracking Items

Type Issue Number Title Report Section Status NOV 05000445,05000446/20 22003-01 Failure to Restore Compliance for Non-Cited Violation 05000445/2019001-02 "Failure to Evaluate a Change to the Facility DC Power System" 71153 Closed

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.03 - Commercial Grade Dedication Commercial Grade Dedication

(1) IID 341695, Seal, Oil, Inboard/Outboard, Diesel Generator 1-01 Auxiliary Jacket Water Pump 1-02
(2) IID 347632, Valve, Relief, 1 1/4 Inch, Screwed Connection, Coolant Charging Pump CCP 1-01 Lube Oil Pump Discharge Pressure Regulating Relief Valve
(3) IID 410103, Helical Spring, Relief Valve, Jet Oil Pump, Safety Chiller, Safety Chiller 2-(4)

IID 432179, Flexitallic Gaskets, Coolant Charging Pump, CCP 2-02 Alternate Miniflo Pressure Relief Valve

(5) IID 450123, Gasket, Teflon, Diesel Generator 1-01 Starting Air Receiver 1-01 Inlet Valve
(6) IID 405413, Block, Terminal, Unit 2 Containment Elevation 906 Hydrogen Detector 5506D
(7) IID 430717, Block, Fuse, Cable Termination Rack 1-TC-07
(8) IID 431343, Diode, Zener, Isolation Module Annunciator Battery Fan Room
(9) IID 509723, Capacitor 12uF, 2800V, Diesel Generator 1-02 Local Control Panel 1-02
(10) IID 394966, Connector, Coax-BWC Male, Control Room Ventilation North Intake Radiation Detector 5895A
(11) IID 174872, Parker Seals O-Rings, Unit 2 SSW Train B Supply Header Pressure Indicator
(12) IID 339196, Valve, Check, Brass 3/8 Inch and 1/2 Inch, Threaded Ends, Safety Chiller 1-05
(13) IID 361576, Strainer, Safety Chiller 2-06
(14) IID 946144, Valve, Globe Hermetic, SS-316, 3/4 Inch, Pressurizer 1-01 Pressure Transmitter 0457 and Level Transmitter 0461/0462 Low Root
(15) Evaluation Number PR 846232, Commercial Grade Dedication of Engineering Service, Revision of Calculation ME-CA-0000-3264

OTHER ACTIVITIES - BASELINE

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee submittals:

(1) Reply to a Notice of Violation, NOV 05000445/2022003-01, Failure to Evaluate a Change to the Facility DC Power System (ADAMS Accession No. ML22335A518).

On November 1, 2022, the NRC issued a cited violation for the failure to restore compliance involving a revision to the updated final safety analysis report concerning Class 1E electrical power supplies shared between Units 1 and 2. In response to the cited violation, on April 20, 2023, the licensee submitted a license amendment request permitting the sharing of systems (ADAMS Accession No.

ML23110A156). On February 9, 2024, the NRC issued amendments to the facility operating licenses for Comanche Peak Units 1 and 2 (ADAMS Accession No.

ML24023A296). The amendments authorize revision to the Comanche Peak updated final safety analysis report to provide clarifications regarding conformance to Regulatory Guide 1.81, Shared Emergency and Shutdown Electric Systems for Multi-Unit Nuclear Power Plants.

The inspectors reviewed the licensees response to the cited violation and determined that the reason for the violation and the corrective actions taken are adequately addressed and captured on the docket.

INSPECTION RESULTS

Failure to assure that purchased material conformed to the procurement documents for commercial grade O-rings Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-01 Open/Closed None (NPP)71111.21N.0 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, for failure to assure that purchased material conformed to the procurement documents for commercial grade O-rings.

Description:

The inspectors reviewed a purchase of commercial grade O-rings from Parker Hannifin by the licensee. In 2012, the licensee ordered a lot of 100 O-rings from Parker Hannifin. The licensee identified several critical characteristics which included dimensions, specifically, the inner diameter and cross-section. In the purchase specification, the licensee required the vendor to perform the dimensional checks at the vendors facility in Lexington, KY. The vendor facility is subject to periodic audits by Nuclear Procurement Issues Corporation (NUPIC) which the licensee credits for their dedication plan. For each order, the licensee requires the vendor to certify that the dimension checks were completed satisfactorily. The vendor performed the checks for the O-rings and sent the results to the licensee.

The inspectors reviewed the results of the dimensional checks. The vendors documentation included the vendor specified tolerances for both dimensional tests along with the results for each O-ring. The inspectors identified that a significant number (approximately 36%) of the O-rings were outside the vendors tolerances but were not identified as failing the test. The licensee received the O-rings, including the documented dimension checks, but did not identify that the vendors test results showed discrepancies with the specification. The O-rings were then released for use and installed in 22 safety-related instruments over the next 12 years.

Corrective Actions: The licensee developed a list of locations where the O-rings had been installed. The licensee performed an operability evaluation and determined that the associated equipment is operable since the dimensional errors did not represent a substantive safety impact.

Corrective Action References: CR-2024-003033

Performance Assessment:

Performance Deficiency: The licensee failed to assure that purchased material conformed to the procurement documents.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, multiple O-rings from the defective lot were installed in safety-related instruments.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors used Exhibit 2, Mitigating Systems Screening Questions, and determined that the issue screened to Green because the finding is a deficiency affecting the design or qualification of a mitigating structure, system, or component (SSC), but the SSC maintained its operability. Specifically, the licensee performed an operability evaluation and determined the affected components were still operable.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations, Part 50, Appendix B Criterion VII, Control of Purchased Material, Equipment, and Services, states in part, that measures shall be established to assure that purchased material conformed to the procurement documents.

Contrary to the above, the licensee failed to assure that the purchased O-rings conformed to the procurement documents. Specifically, the license received O-rings that did not meet the vendors dimensional test acceptance criteria and installed the O-rings in safety related SSCs.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to review a change in design of a commercial grade item for suitability of parts and materials for safety-related chillers Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-02 Open/Closed None (NPP)71111.21N.0 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50 Appendix B, Criterion III Design Control when the licensee failed to review a new commercial grade refrigerant filter-drier for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components specific to the unit 1 and 2 safety chillers.

Description:

The inspectors reviewed the procurement of refrigerant strainers for the safety chillers under the licensees commercial grade item dedication program. The licensee had developed a dedication plan for commercial grade strainers procured from Sporlan. The licensee had identified several critical characteristics to verify, one of which was the materials of construction. The licensees verification plans included testing of the body and connections materials, as well as steps to cut open a sample of the strainers to verify that the strainers contained the required 100 count stainless-steel mesh inside. The licensee purchased an order of strainers in March 2020. During the receipt inspection, the licensee discovered the parts were a new filter-drier design that used desiccant instead of the previous wire mesh strainer design. The licensee correctly identified this an unsatisfactory receipt and requested an engineering evaluation to determine how to proceed. The licensees engineering evaluation concluded that the new filter-drier was equivalent to the old strainers because the commercial vendor had used the same part number for the filter-drier and assumed that the vendor was responsible for the change of the design of the part. Based on this conclusion, the licensee revised the verification plan acceptance criteria to only verify the materials for the body and connections. They then accepted the new filter-driers and installed them on all four safety chillers.

The inspectors questioned the licensees conclusion that the parts were equivalent. Specifically, the inspectors considered the change in the parts design from a mechanical stainless-steel strainer to a desiccant-media based filter-drier to be a change in form, function, and materials. The industry guidance on acceptance of replacement items is EPRI NP-6406, Plant Support Engineering: Guidelines for the Technical Evaluation of Replacement Items in Nuclear Power Plants. This guidance is referenced in licensee procedure ECE-5.01-04, Technical Evaluation of Replacement Items (TERI), Revision 11.

Because the change reflected a change in the materials and method for removing impurities from the refrigerant, the change would have required evaluation by the licensee. Procedure ECE-5.01-04 would require the licensee to evaluate the change, or in the case of delegating design control to the vendor, to review the vendor documentation for the change evaluation.

The licensee had not requested or reviewed information regarding the change in design. In the licensees evaluation, the licensee assumed the material was acceptable because it was viewed as an improvement. However, the licensee did not consider the potential for new failure modes. Specifically, the available vendor information on the part suggests the desiccant material is susceptible to disintegration due to vibrations. The licensee did not document any evaluation of this potential failure. While the vendor part included a device for retention of particles, the licensee failed to ensure this was sufficient to prevent failure following a design basis event. Furthermore, the licensees revised verification plan did not verify the presence of either the desiccant or the retention device. The inspectors determined that at least one subsequent order was received with no verification of the internal materials.

Corrective Actions: The licensee performed an operability determination and determined that the safety chillers were still operable with the new design of the filter drier.

Corrective Action References: CR-2024-002731

Performance Assessment:

Performance Deficiency: The licensee failed to review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components. Specifically, the licensee did not review the suitability of the desiccant material in new design of the filter-drier in the safety chillers.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the new filter-driers were installed in all four safety chillers without determining if the material was suitable for use.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors used Exhibit 2, Mitigating Systems Screening Questions, and determined that the issue screened to Green because the finding is a deficiency affecting the design or qualification of a mitigating structure, system, or component (SSC), but the SSC maintained its operability. Specifically, the licensee performed an operability evaluation and determined the safety chillers were still operable.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations, Part 50, Appendix B, Criterion III, Design Control, requires, in part, that measures shall be established for the selection and review for suitability of application of materials, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems and components. Design changes, including field changes, shall be subject to design control measures commensurate with those applied to the original design and be approved by the organization that performed the original design unless the applicant designates another responsible organization.

Contrary to the above, the licensee failed to establish measures for the selection and review for suitability of application of materials and parts essential to safety-related components. Specifically, the license failed to ensure that the new filter-drier design was suitable for use in the safety chillers.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to test for the critical characteristics for Teflon gaskets used in the Emergency Diesel Generator Starting Air System Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000445,05000446/2024012-03 Open/Closed None (NPP)71111.21N.0 Inspectors identified a Green finding and associated Non-cited Violation (NCV) of 10 CFR 50, Appendix B, Criterion XI, Test Control, when the licensee failed to test for the identified critical characteristics for Teflon gaskets used in the Emergency Diesel Generator starting air system.

Description:

Item ID 450123 is a commercially procured Teflon gasket. The licensee used procedure ECE-6.02-03 Form 1 to identify the critical characteristics used to dedicate the item for use in safety-related applications. The critical characteristics documented were description, part number, dimensions, and material. Due to the lack of information provided by the vendor regarding the material composition and dimensions, the licensee decided to perform a VT-2 post-installation test to verify the critical characteristics of material and dimensions. The acceptance criteria for the VT-2 test was no leakage from the gasket location. Inspectors questioned the use of a VT-2 post-installation test to verify these critical characteristics. Inspectors reviewed WO 4-02-144198 which installed the Teflon gasket in the body to bonnet location of DG-1-01 Starting Air Valve 1DO-0135, and WO 4-05-160488-00 which installed the Teflon gasket on the body to bonnet location of DG-2-01 Starting Air Valve 2DO-0135. The work orders did not contain any guidance to adequately verify the gasket dimensions or material.

Corrective Actions: The licensee did material analysis testing on the remaining gaskets in stock and verified that they are Teflon.

Corrective Action References: CR-2024-002692

Performance Assessment:

Performance Deficiency: The licensee failed to test for the identified critical characteristics for Teflon gasket used in the Emergency Diesel Generator starting air system.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the Teflon gaskets were installed in two plant locations without verifying the components met the acceptance criteria for the critical characteristics of material and dimensions.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The issue was screened in accordance with IMC 0609 Appendix A, Significance Determination Process for Findings At-Power, exhibit 2, Mitigating Systems Screening Questions. The issue screened to Green because there was no impact to the operability or PRA functionality of the mitigating SSC. Specifically, there were no identified failures of the gaskets and they have been installed in the plant since 2002 and 2005 for Units 1 and 2 respectively.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Title 10 of the Code of Federal Regulations, Part 50, Appendix B, Criterion XI, Test Control, requires, in part, that a test program shall be established to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. Contrary to this requirement, the licensee did not establish a test program to assure that all testing required to demonstrate that structures, systems, and components will perform satisfactorily in service is identified and performed in accordance with written test procedures which incorporate the requirements and acceptance limits contained in applicable design documents. Specifically, the gaskets used in the body to bonnet location of EDG 1-01 starting air valve 1DO-0135 and EDG 2-01 starting air valve 2DO-0135 were not tested for the critical characteristics identified in the commercial grade dedication for ECE-6.02-03 Form

1. Enforcement Action: This violation is being treated as a non-cited violation, consistent with

Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On May 16, 2024, the inspectors presented the design basis assurance inspection (programs) inspection results to Al Marzloff, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.03

Calculations

IMT-CA-EQ-

0099-MS-20A.1

Generic Qualification of Small-Bore Rockwell Valves

71111.21N.03

Calculations

ME-CA-0000-

264

Safe Shutdown Impoundment Hydrothermal Analysis

71111.21N.03

Corrective Action

Documents

CR-

2005-000488, 2005-002672, 2011-001876, 2012-001241,

2012-004468, 2012-005154, 2013-010782, 2013-010882,

2016-003267, 2020-000934, 2020-004537, 2020-007357,

21-001086

71111.21N.03

Corrective Action

Documents

Resulting from

Inspection

IR-2024-

2600, 002684, 002692, 002697, 002731, 002733,

2824, 002818, 002824, 002829, 002862, 003033,

003051

71111.21N.03

Drawings

D-364773-01

P.C.B

D. SCHEMATIC, ISOLATION MODULE 4 CH.

25VDC I/O

A

71111.21N.03

Drawings

E1-0067, Sheet

108

Unit 1 Diesel Generator 1EG1 Excitation Schematic

CP-1

71111.21N.03

Drawings

E1-0067, Sheet

109

Unit 1 Diesel Generator 1EG2 Excitation Schematic

CP-1

71111.21N.03

Drawings

E1-0076, Sheet

30A

ANNUNCIATOR LAMP CABINET 1-ALB-11B

SCHEMATlC DIAGRAM

CP-2

71111.21N.03

Drawings

E1-0076, Sheet

30B

ANNUNCIATOR LAMP CABINET 1-ALB-11B

SCHEMATIC DIAGRAM

CP-2

71111.21N.03

Drawings

E1-0080, Sheet

03A

SOLID STATE ISOLATION CABINET CP1-ECPRCR-07

EXTERNAL CONNECTION DIAGRAM

CP-5

71111.21N.03

Drawings

E2-0067, Sheet

108

Unit 2 Diesel Generator 2EG1 Excitation Schematic

CP-1

71111.21N.03

Drawings

E2-0067, Sheet

109

Unit 2 Diesel Generator 2EG2 Excitation Schematic

CP-1

71111.21N.03

Miscellaneous

05-356643-01

Edwards Size 3/4 Figure 15104

71111.21N.03

Miscellaneous

1038748

Purchase Order 1038748

10/16/2020

71111.21N.03

Miscellaneous

1196650

Purchase Order 1196650

6/23/2022

71111.21N.03

Miscellaneous

2978

Nuclear Procurement Issues Committee (NUPIC)

5/10/2011

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Commercial Grade Item Survey of Parker Hannifin

Corporation, O-Ring Division

71111.21N.03

Miscellaneous

23-MS-20A.1

Manual and Self-Actuated Steel Valves

71111.21N.03

Miscellaneous

40119

Receipt for Parker Seal O-Rings

2/7/2012

71111.21N.03

Miscellaneous

21562

Purchase Order 521562

6/13/2018

71111.21N.03

Miscellaneous

611-6S853006

Procurement Document Review Summary for Item#

509723

04/15/2015

71111.21N.03

Miscellaneous

2777

Purchase Order 662777

1/21/2020

71111.21N.03

Miscellaneous

2741-01

TEST PROCEDURE, ISOLATION MODULE (AI-AII),

ACCEPT/REJECT CRITERIA

E

71111.21N.03

Miscellaneous

A-374026-01

TEST PROCEDURE FOR ISOLATION MODULE, 4

CHANNEL 125 VDC IN/OUT

71111.21N.03

Miscellaneous

CP-0080B-002

Hermetic Turbopak Safety Related Chillers

71111.21N.03

Miscellaneous

CP-202000219

Sporlan C-052 Filter Materials

71111.21N.03

Miscellaneous

CPES-M-1057

Specification Pre-Engineered Items

71111.21N.03

Miscellaneous

CPSES 9804622

REPLACEMENT PARTS FOR FORNEY CORPORATION

SUPPLIED SOLID STATE ISOLATION EQUIPMENT

08/27/1998

71111.21N.03

Miscellaneous

NEE0601

Pre-Engineered Item Data Sheet (PEIDS) NEE 0601 -

Coaxial and Triaxial Cable Connections for Harsh and

Mild Environments

71111.21N.03

Miscellaneous

NEE0606

Pre-Engineered Item Data Sheet (PEIDS) NEE0606 -

Block, Fuse (For Class H, J, K, R, CC, and Midget Fuses)

for Mild Environments

71111.21N.03

Miscellaneous

NEE0623

Pre-Engineered Item Data Sheet (PEIDS) NEE0623 -

Block, Terminal, Safety Related, Class 1E, Harsh and

Mild Environments

71111.21N.03

Miscellaneous

NEE07492012

Block, Terminal, Safety Related, Class 1E, Harsh

Environments

71111.21N.03

Miscellaneous

NEM10532012

Pre-Engineered Item Data Sheet (PEIDS) Parker Seals

O-rings

71111.21N.03

Miscellaneous

NEM11192018

Strainer

71111.21N.03

Miscellaneous

NEM1328

Pre-Engineered Item Data Sheet (PEIDS) Valve, Check,

Brass

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.03

Miscellaneous

PO-319127

Purchase Order 319127 - Terminal Block, 600V, 35 Amp,

  1. 22-#10 AWG Wire Range, #8 Screw

01/29/2016

71111.21N.03

Miscellaneous

PO-337080

Purchase order for seal, oil, inboard/outboard

4/11/2016

71111.21N.03

Miscellaneous

PO-719668

Purchase order for flexitallic gaskets

7/22/2020

71111.21N.03

Miscellaneous

RAL-2937

Design Report - Size 3/4 Figure 15104

71111.21N.03

Miscellaneous

RR-018280

Connector, Coax-BNC Male

09/02/1995

71111.21N.03

Miscellaneous

RR-023384

Diode - 1N4005; Transistor - 2N7000; Varistor -

1.5KE160C; Opto Coupler - 6N139; Zener Diode -

1N5245; Opto Coupler - TLP595G

05/12/1998

71111.21N.03

Miscellaneous

RR-028556

Verification plan for Teflon gaskets

10/2/2002

71111.21N.03

Miscellaneous

RR-037790

Block, Terminal, Safety Related, Class IE, Harsh and Mild

Environment

08/18/2010

71111.21N.03

Miscellaneous

RR-038202

Module, Isolation

01/17/2011

71111.21N.03

Miscellaneous

RR-038799

Block, Fuse

06/08/2011

71111.21N.03

Miscellaneous

RR-043880

Capacitor, Metalized Polypropylene Film, Self-Healing

04/23/2015

71111.21N.03

Miscellaneous

RR-057243

Block, Terminal, Safety Related, Class IE, Harsh

Environment

04/12/2012

71111.21N.03

Miscellaneous

RR-

059057_1_NA

Verification plan for seal, oil, inboard/outboard

2/6/2007

71111.21N.03

Miscellaneous

RR-

2065_1_NA

Verification plan for flexitallic gaskets

8/19/2020

71111.21N.03

Miscellaneous

RR-103498

Receipt for globe valve

2/15/2020

71111.21N.03

Miscellaneous

RR-20934

Verification plan for relief valve 1-1/4 Inch

2/1/1995

71111.21N.03

Miscellaneous

RR-23278

Verification plan for helical spring, relief valve, jet oil

pump, safety chiller

2/5/1997

71111.21N.03

Miscellaneous

RR-26281

Receipt for brass check valves

6/9/2000

71111.21N.03

Miscellaneous

RR-85624

Receipt for engineering services

2/19/2019

71111.21N.03

Miscellaneous

RR-96297

Receipt for strainer

4/21/2020

71111.21N.03

Miscellaneous

s02101546s4

Purchase order for relief valve, stainless steel

11/14/1996

71111.21N.03

Miscellaneous

s02563036s4

Purchase order for spring, helical

4/13/1998

71111.21N.03

Miscellaneous

S02579316S4

Purchase Order S02579316S4

04/29/1998

71111.21N.03

Miscellaneous

S03265016S4

Purchase Order S03265016S4

6/29/2000

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.03

Miscellaneous

S06641476S4

Purchase Order S06641476S4

10/14/2010

71111.21N.03

Miscellaneous

S07060626S4

Purchase Order S07060626S4 - Block, Fuse, 600V, 1/10

to 30 AMP, 3 Pole, Screw Terminals 1200 Volts AC,

NEE0606

04/22/2011

71111.21N.03

Miscellaneous

S07291856S4

Purchase Order S07291856S4

10/6/2011

71111.21N.03

Miscellaneous

VDRT-5875664

Sealed Type Specifications

3/19/2020

71111.21N.03

Miscellaneous

VP 98-0024

PCB, 4 Channel Isolation Module

04/27/1998

71111.21N.03

Miscellaneous

VP-98-0023

Diode - 1 N4005* Transistor - 2N7000; Varistor -

1.5KE160C; Opto Coupler - 6N139; Zener Diode - 1

N5245; Opto Coupler - TLP595G

04/27/1998

71111.21N.03

Procedures

ECE 6.02-02

Procurement Engineering Review of Procurement

Documents

71111.21N.03

Procedures

ECE 6.02-03

Critical Characteristics Development

71111.21N.03

Procedures

ECE 6.02-06

Preparation of Verification Plans

71111.21N.03

Procedures

ECE-5.01-04

Technical Evaluation of Replacement Items

71111.21N.03

Procedures

ECE-5.01-04

Technical Evaluation of Replacement Items (TERI)

71111.21N.03

Procedures

ECE-5.01-04

Technical Evaluation of Replacement Items (TERI)

71111.21N.03

Procedures

ECE-5.08-01

Comanche Peak (Utility) Design Change Process

71111.21N.03

Procedures

ECE-6.02-01

Procurement Levels

71111.21N.03

Procedures

ECE-6.02-03

Critical Characteristics Development

71111.21N.03

Procedures

EPG-731

ASME Section XI Repair / Replacement Activities

71111.21N.03

Procedures

INC-2319

Functional Testing of Solid-State Isolation Modules

71111.21N.03

Procedures

MSE-C0-7333

Centrifugal Water Chiller Overhaul

71111.21N.03

Procedures

MSE-P0-7333

Centrifugal Water Chiller Maintenance

71111.21N.03

Procedures

STA-421

Initiation of SmartForms

71111.21N.03

Procedures

STA-422

PROCESSING SMARTFORMS

71111.21N.03

Procedures

STI-422.01

Operability Determination Program

71111.21N.03

Procedures

STI-716.06

Design Attribute Review (DAR)

71111.21N.03

Procedures

WHS-002

Handling and Storage

71111.21N.03

Procedures

WHS-011

Warehouse Surveillance

71111.21N.03

Work Orders

5-95-500716, 3581645, 3801009, 4174383, 4748348,

5502005, 22-203492, 1-97-110113-00, 5000505_1,

28428_1, 5769058_1, 4-02-144198, 4-05-160488-00,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5871390, 5957364, 5999400, 21-846435