IR 05000440/2009006

From kanterella
Jump to navigation Jump to search
IR 05000440-09-006, on 01/12/2009 - 01/30/2009, Perry Nuclear Power Plant, Unit 1, Routine Biennial Problem Identification and Resolution Inspection (Pi&R)
ML090570686
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 02/25/2009
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To: Bezilla M
FirstEnergy Nuclear Operating Co
References
IR-09-006
Download: ML090570686 (26)


Text

February 25, 2009

SUBJECT:

PERRY NUCLEAR POWER PLANT PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION 05000440/2009-006

Dear Mr. Bezilla:

On January 30, 2009, the U. S. Nuclear Regulatory Commission (NRC) completed a routine biennial PI&R inspection at your Perry Nuclear Power Plant. The enclosed report documents the inspection results, which were discussed on January 30 with Mr. Kruger and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

The team concluded that problems were properly identified, evaluated, and resolved within the corrective action program. The team also concluded that improvements have been made in the quality of root and full apparent cause analyses and in the handling of human performance issues. However, the team also concluded that the sites recognition and evaluation of potentially negative trends continues to be a challenge.

Based on the results of this inspection, one NRC-identified finding of very low safety significance was identified (Green). The finding was also a violation of NRC requirements.

However, because of the very low safety significance and because the issue was entered into your corrective action program, the NRC is treating the issue as a Non-Cited Violation (NCV) in accordance with Section VI.A.1 of the NRCs Enforcement Policy.

If you contest the subject or severity of the NCV in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission, Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspectors Office at the Perry Nuclear Power Plant. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Jamnes L. Cameron, Chief Projects Branch 6 Division of Reactor Projects Docket Nos. 50-440 License Nos. NPF-58 Enclosure:

Inspection Report 05000346/2009006 w/Attachment: Supplemental Information

cc w/encl:

J. Hagan, President and Chief Nuclear Officer - FENOC

J. Lash, Senior Vice President of Operations and

Chief Operating Officer - FENOC

D. Pace, Senior Vice President, Fleet Engineering - FENOC

K. Fili, Vice President, Fleet Oversight - FENOC

P. Harden, Vice President, Nuclear Support

Director, Fleet Regulatory Affairs - FENOC

Manager, Fleet Licensing - FENOC

Manager, Site Regulatory Compliance - FENOC

D. Jenkins, Attorney, FirstEnergy Corp.

Public Utilities Commission of Ohio

C. OClaire, State Liaison Officer, Ohio Emergency Management Agency

R. Owen, Ohio Department of Health

SUMMARY OF FINDINGS

IR 05000440/2009-006; 01/12/2009 - 01/30/2009; Perry Nuclear Power Plant, Unit 1; routine biennial Problem Identification and Resolution Inspection (PI&R).

This inspection was performed by four regional inspectors and the Perry Resident Inspector. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

Problem Identification and Resolution Based on the sample selected for review, the team concluded that implementation of the corrective action program (CAP) was adequate. The licensee had a low threshold for identifying problems and entering them in the CAP. Items entered into the CAP were screened and prioritized in a timely manner using established criteria; were properly evaluated commensurate with their safety significance; and corrective actions were generally implemented in a timely manner, commensurate with the safety significance.

The team noted that the licensee reviewed operating experience for applicability to station activities. Audits and self-assessments were determined to be performed at an appropriate level to identify deficiencies. On the basis of licensee self-assessments and interviews conducted during the inspection, workers at the site expressed freedom to raise safety concerns. The team observed that improvements have been made in the licensees identification and assessment of human performance issues and in root and full apparent cause analyses quality. While noting some improvement in the identification of negative trends, the team also noted that in at least one case the licensee had not identified a negative trend in an area previously highlighted by an NRC finding and associated non-cited violation.

NRC-Identified

and Self-Revealed Findings

Cornerstone: Barrier Integrity

Green.

A finding of very low safety significance and associated non-cited violation of Technical Specification 5.4, Procedures, was identified by the team for the failure to erect scaffolding in accordance with procedural requirements.

Specifically, scaffold constructed in the Intermediate Building had seismic bracing attached to a safety-related cable tray support and was connected to a duct support without an approved engineering document as specified in procedural requirements.

Although the licensee was able to demonstrate that the cable tray support and duct support were operable, the finding was determined to be more than minor because there was reasonable doubt that the licensee routinely performed engineering evaluations on similar scaffold issues. The finding was determined to be of very low safety significance because it did not represent an actual open pathway in the physical integrity of reactor containment. This finding had a cross-cutting aspect in the area of human performance, work practices, because the licensee failed to ensure supervisory and management oversight of work activities such that nuclear safety is supported. Specifically, the licensee failed to provide effective oversight of the erected seismic scaffold to ensure compliance with procedural requirements H.4(c). (Section 4OA2.1)

Licensee-Identified Violations

None.

REPORT DETAILS

OTHER ACTIVITIES

4OA2 Problem Identification and Resolution

Completion of Sections

.1 through.4 constitutes one biennial sample of problem

identification and resolution as defined in Inspection Procedure 71152.

.1 Assessment of the CAP Effectiveness

a. Inspection Scope

The team reviewed the licensees corrective action program (CAP) implementing procedures and attended CAP meetings to assess the implementation of the CAP by site personnel.

The team reviewed risk and safety significant issues in the licensees CAP since January 2007. The selection of issues ensured an adequate review of issues across NRC cornerstones. The team used issues identified through NRC generic communications, department self-assessments, licensee audits, operating experience reports, and NRC documented findings as sources to select issues. Additionally, the team reviewed condition reports (CRs) generated as a result of facility personnels performance of daily plant activities. In addition, the team reviewed CRs and a selection of completed root cause, apparent cause, and common cause assessments.

The team specifically reviewed CRs associated with the residual heat removal (RHR) system and performed a partial system walkdown of the RHR system to ensure the condition of the system was appropriately portrayed by the corrective action program. In addition, the team observed new fuel unloading, inspection, and transfer to the fuel pool to assess the effectiveness of the licensees corrective actions associated with a root cause evaluation performed on its Foreign Material Exclusion program. Further, the team reviewed condition reports associated with open control room deficiencies, operator burdens, and operator work-arounds to assess the level of review and appropriateness of corrective actions.

The teams reviews were designed to determine whether the licensees actions were in compliance with the facilitys CAP and 10 CFR Part 50, Appendix B requirements. Specifically, the teams activities were designed to determine whether licensee personnel were identifying plant issues at the proper threshold, entering issues into the stations CAP in a timely manner, and assigning the appropriate prioritization for resolution of the issues. In addition, the teams activities were to determine whether the licensee assigned the appropriate investigation method to ensure the proper determination of root, apparent, and contributing causes. The team also evaluated the timeliness and effectiveness of corrective actions for selected issue reports, completed assessments, and NRC findings, including non-cited violations.

b.

Assessment

(1) Effectiveness of Problem Identification Overall, based on the description of the CAP, the number of condition reports (CRs) generated by all plant departments, and the types of issues in the program, the team concluded that the licensee was appropriately identifying issues and entering them into the CAP.

Observations The team identified that the licensee was identifying significantly more human performance issues than in the past and using the CAP to evaluate the conditions. For example CR 08-32531, Valve Found Out Of Position And Near Miss, provided insights into the human performance issues associated with an out-of-position reactor water cleanup valve. Another example was CR 08-47779, Unrecognized OPDRV Results in LER, where an individual questioned the results from a previously performed activity thus allowing the facility to address the issues in a broader context.

During the walkdown of the RHR system two issues were identified. A drain valve on the RHR C Heat Exchanger, while locked, was not fully closed as required by the locked valve program; observation of the valve stem indicated the valve to be about 10 percent open. This issue was reported to the site operations department and a condition report was written (CR 09-52687, CR 09-52687, Locked Closed Valve Does Not Appear To Be Fully Closed).

This issue was considered minor because there was a second closed valve in the series with the valve in question, the drain line was capped, and the licensee took prompt action to lock the second valve in the line. The second issue dealt with the use of keys to high radiation area doors. During the radiation protection briefing for access to the RHR rooms, radiation protection personnel informed the team members that they would be issued an electronic door key programmed to only open doors to rooms for which they had been briefed. During the briefing it was explained that the electronic keys were a corrective action to prevent individuals from entering rooms for which they had not been briefed. Following the briefing, when attempting to enter a RHR room, a worker at the gate, noting the team member having difficulty with the lock, offered to use his key to open the gate. Using a key issued to another work group to access locked radiation area would have violated station procedure and bypassed the corrective actions to earlier problems. This issue was considered minor because the area in question was locked due to a licensee administrative limit and the individual did not actually open the gate for the inspectors. The area was conservatively posted and no regulatory limits requiring posting were exceeded. This issue was reported to the site radiation protection department and a CR was written (CR 09-52641, NRC PI&R 2009, Individual Offered To Open HRA Lock For An Individual Not In His Work Crew).

While improvements were noted in the licensees identification of negative trends, for example the root cause evaluation for the containment airlock ball valve failures, (CR 08-44698, Adverse Trend Identified in the Containment Air Lock Doors), the team identified that the licensee had not identified a similar negative trend with scaffolding. Based on the teams questions related to scaffolding, a licensee search of scaffold program issues in the last 6 months of 2008 identified 41 related CRs and a potential adverse trend in the scaffold program. In addition, as detailed below, the team identified a scaffold where a required evaluation had not been performed. The licensee entered the concern into the corrective action program, CR 09-52450, Potential Adverse Trend in Scaffold Program, with a recommendation that a common cause evaluation be conducted to determine the cause of the apparent adverse trend.

Findings

(1) Failure to Adhere to Procedures for Scaffold Affecting Containment Systems
Introduction:

A finding of very low safety significance and associated non-cited violation (NCV) of Technical Specifications (TS) 5.4, Procedures, was identified by the team for the licensee failing to adhere to Procedure GCI-0016 Scaffolding Erection, Modification, or Dismantling Guidelines.

Description:

On January 15, 2009, the team performed a walkdown of plant scaffolding. While at elevation 654-6 in the Intermediate Building, the team observed the configuration of scaffold number IB 654-05#18 for compliance with Procedure GCI-0016. The team observed that this scaffold had seismic bracing attached to an L4x3x3/8 structural angle component of cable tray support 1IB5-T7. Procedure GCI 0016 Scaffolding Erection, Modification, or Dismantling Guidelines, paragraph 5 of Attachment 4, Acceptance Pre-Approved Scaffold Points for External Seismic Bracing to Prevent Overturning and Lateral Movement Adjacent to Safety Related Components and Equipment, specified a minimum L4x4x3/8 structural angle. In addition, the team observed that vertical scaffold legs connected to Containment Drywell Purge exhaust duct support DS-IB-5015 were not in conformance with paragraph 13.b of Section 3.0, Precautions and Limitations, of Procedure GCI-0016.

The team noted that Procedure GCI-0016 specified the above procedural deviations be approved by an engineering document. The licensee confirmed that an engineering evaluation of these procedural deviations had not been performed.

Based on the observations, the team determined that the licensee failed to adhere to Procedure GCI-0016 for the installation of the scaffold 1B 654-05#18.

The licensee identified several nuclear safety-related circuits were routed through the cable tray at support 1IB5-T7 including containment atmosphere radiation monitor isolation valves associated with TS 3.6.1.3 and containment air lock isolation valves associated with TS 3.6.1.2.

In addition, the licensee identified that at-duct support DS-IB-5015, the Containment Drywell Purge exhaust duct is classified as non-nuclear safety-related. However, duct support DS-IB-5015 is classified as nuclear safety-related for Seismic II/I considerations, i.e., a structure not classified as Seismic Class I but whose failure due to a seismic event could affect the function of a seismic structure, system, or component. The licensee identified that a failure of this duct support could affect several nuclear safety related circuits routed through a nearby cable tray including containment atmosphere radiation monitor isolation valves associated with TS 3.6.1.3 and containment air lock isolation valves associated with TS 3.6.1.2.

Analysis:

The team determined that the failure to adhere to scaffold procedures affecting containment systems was contrary to TS 5.4 and was a performance deficiency.

The finding was determined to be more than minor because the finding was similar to Example 4a of IMC 0612, Appendix E. Although the licensee was able to demonstrate that cable tray support 1IB5-T7 and duct support DS-IB-5015 were operable, there was reasonable doubt that the licensee routinely performed engineering evaluations on similar scaffold issues. Therefore, this performance deficiency impacted the Barrier Integrity Cornerstone objective to provide reasonable assurance that physical barriers (containment) protect the public from radio-nuclide releases caused by accidents or events.

The team determined the finding could be evaluated using the SDP in accordance with IMC 0609, Significance Determination Process, 0609.04, Phase 1 - Initial Screening and Characterization of Findings, Table 4a, for the Barrier Integrity Cornerstone. Specifically, since all four questions under the Containment Barrier column were answered no, the finding was determined to be Green, of very low safety significance, because it did not represent an actual open pathway in the physical integrity of reactor containment.

This finding had a cross-cutting aspect in the area of human performance, work practices, because the licensee failed to ensure supervisory and management oversight of work activities such that nuclear safety is supported. Specifically, the licensee failed to provide effective oversight of erected seismic scaffold to ensure compliance with procedural requirements. H.4(c)

Enforcement:

Technical Specification Section 5.4.1 states, in part, that Written procedures shall be established, implemented, and maintained covering the following activities: The applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Paragraph 9.a of Appendix A of this Regulatory Guide states, in part, that maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures appropriate to the circumstances. The licensee established Procedure GCI-0016 as the implementing procedure for scaffolding erection, modification, or dismantling.

Paragraph 13.b of Section 3.0 of Procedure GCI-0016 states, in-part, unless specifically approved by this instruction, scaffolds shall not be connected to, or in contact with any plant equipment, piping, conduits, cable trays, HVAC supports, unless approved by an engineering document. Paragraph 5 of Attachment 4 of Procedure GCI-0016 allowed attachment of scaffold seismic bracing to cable tray support member sizes (angle size) L4x4x3/8 or larger.

Contrary to the above, on January 15, 2009, scaffold IB 654-05#18, was not erected in accordance with Procedure GCI-0016 and no engineering analysis was performed. Specifically, scaffold seismic bracing was attached to an L4x3x3/8 structural angle component of cable tray support 1IB5-T7 and the scaffold was connected to duct support DS-IB-5015 without an approved engineering document. Because this violation was of very low safety significance and it was entered into the licensees corrective action program as CRs 09-52038, Scaffold Not in Compliance with Plant Procedures, and 09-52474, Scaffold Not in Compliance with Plant Procedures - No Prompt Operability Determination Performed, this violation is being treated as an NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy (NCV 05000440/2009006-01).

(2) Effectiveness of Prioritization and Evaluation of Issues The team concluded that issue resolutions established and monitored through the management review board and the corrective action review board were correctly assigned significance and priority in accordance with station procedures. The team noted an improvement in the completeness of root and full apparent cause evaluations compared to previous inspections. While the team had questions on numerous evaluations, the evaluations were mainly categorized as limited apparent cause or fix type issues, where in the past the questions involved full apparent or root cause evaluations. The reduction in questions on full apparent and root cause evaluations indicated an overall improvement in the quality of the licensees implementation of these assessment tools.

Findings No findings of significance were identified.

(3) Effectiveness of Corrective Actions The team concluded that the corrective action program was generally effective in addressing identified issues. The effectiveness of the program is hampered by the licensee not consistently identifying negative trends thereby only addressing individual issues, as was the case with the scaffolding issue noted above. As previously noted, the team identified that the licensee was identifying more human performance issues and using the CAP to evaluate the items. In reviewing the corrective actions associated with human performance issues, the team concluded that the actions were appropriate; however, the corrective actions have not been in place for a sufficient amount of time to allow for a conclusive assessment of their effectiveness.

The team did identify a number of examples where assessments have had a positive impact on the facility. For example, in CR 08-44698, Adverse Trend Identified in the Containment Air Lock Doors, the licensee stepped back from the individual failures with the air locks and they were able to effectively identify and address a number of process deficiencies.

Findings No findings of significance were identified.

.2 Assessment of the Use of Operating Experience (OE)

a. Inspection Scope

The team reviewed the licensees implementation of its Operating Experience (OE) program. Specifically, the team reviewed implementing operating experience program procedures, attended OE program meetings to observe the use, disposition, and dissemination of OE information, and reviewed OE performance indicators. In addition, the team reviewed completed evaluations of OE issues and events identified through NRC generic communications, reports made under 10 CFR Part 21, and external and internal OE. The team also compared the information provided in the vendor manuals of the low pressure core spray (LPCS) pump and motor with the licensees procedures and equipment environmental qualification. The teams review was to determine whether the licensee effectively integrated OE experience into the performance of daily activities, whether evaluations of issues were proper and conducted by qualified personnel, whether the licensees program was sufficient to prevent occurrences of previous industry events, and whether the licensee effectively used the information in developing departmental assessments and facility audits.

The team also assessed whether corrective actions, as a result of OE experience, were identified, and effectively and timely implemented.

b.

Assessment The team noted that the OE program has improved and that, as a result of a recent self-assessment and condition report, the licensee has several corrective actions in place or being implemented to improve the program. The corrective actions seek to improve the thoroughness and timeliness of OE evaluations, the dissemination of OE information, and other areas determined to have vulnerabilities like the OE program procedure. The team did not have any major observations that were not already being addressed by the licensees CAP at the time of this inspection.

Observations Timeliness of OE evaluations has improved The team noted that the backlog of OE evaluations at the corporate level has decreased. Specifically, the licensees performance indicators show that the number of overdue OE evaluations decreased from 125 in January of 2008 to 15 in December 2008. The team noted, however, that the evaluation of NRC Information Notice (IN) 2006-022, New Ultra-low-sulfur Diesel Fuel Oil Could Adversely Impact Diesel Engine Performance, had not been complete by the time it was requested as a sample for this inspection. The licensee received this IN during the last quarter of 2006 and completed the evaluation during this inspection; exceeding its 60 day goal to evaluate OE. This timeliness issue was documented by the licensee in CR 09-51882 NRC PI&R 2009: IN 2006-022 Evaluation not complete.

Potential missed opportunities to identify an adverse condition exists The team noted that some OE evaluations determined that existing procedures were adequate to address the issues communicated by the OE notifications without a thorough explanation of the basis for this determination. Even though the conclusions may be correct, not documenting why the procedures were adequate to address the OE could lead to a potential missed opportunity to identify an adverse condition.

In addition, it was noted during this inspection that the Vendor Information Coordinator, who is responsible for tracking all Part 21 notifications, may not be receiving all the Part 21 notifications. The licensee initiated CR 09-51876, NRC PI&R 2009: All Part 21 Notifications are not routed through vendor coord, to review and address this issue.

Findings No findings of significance were identified.

.3 Assessment of Self-Assessments and Audits

a. Inspection Scope

The team assessed the licensees ability to identify and enter issues into the CAP, prioritize and evaluate issues, and implement effective corrective actions, through efforts from departmental assessments and audits.

b.

Assessment The programs for self-assessments and audits were scheduled and included a broad cross section of performance areas. Procedures for performing assessments were in place and implemented providing guidance and consistency. For the audits and assessments reviewed, observations were documented and for deficiencies that were identified, CRs were written and evaluated to address the deficiencies. Overall, self-assessments were adequately performed. The team noted that self-assessments and audits were identifying more human performance issues than in the past.

The team noted an instance where the Oversight Department identified an issue with an evaluation. Specifically, the licensee determined during a prompt operability determination that a revision to a 10 CFR 50.59 evaluation was not needed. However, because of QA intervention, the process was followed and a revision to the 10 CFR 50.59 evaluation was performed.

A self assessment of the OE program had recently been performed. This assessment was thorough and well organized. The issues that were identified were evaluated appropriately and corrective action assigned. The assessment conclusions closely matched those of the inspection team.

Findings No findings of significance were identified.

.4 Assessment of Safety Conscious Work Environment

a. Inspection Scope

The team assessed the licensees safety conscious work environment through discussions with the employee concern program coordinator, interviews with 24 individuals from various departments, and review of the licensees 2008 Safety Conscious Work Environment (SCWE) survey.

b.

Assessment As part of its ongoing assessment of SCWE, the licensee used an anonymous survey tool first developed in 2002 at the Davis-Besse facility. Results for 2008 indicated no significant areas of overall weakness in a safety conscious work environment, although some organizations were notably more negative in their perceptions of management. The team noted that the survey was returned by approximately 71 percent of the staff. The survey also included security staff and contractors. Based on its review of the survey and interviews, the team concluded that the licensee staff was willing to raise safety concerns without fear of negative consequences.

The team also noted one technical issue brought to the ECP coordinator was appropriately placed in CAP for evaluation.

c. Findings

No findings of significance were identified.

4OA6 Management Meetings

Exit Meeting Summary

On January 30, 2009, the team presented the inspection results to Mr. Kruger and other members of the licensees staff. The licensees staff acknowledged the issues presented. The team confirmed that none of the potential report inputs discussed was considered proprietary.

SUPPLEMENTAL INFORMATION

Key Points of Contact

Licensee

K. Krueger, Plant General Manager
A. Cayia, Director, Performance Improvement
K. Cimorelli, Director, Maintenance
J. Grabner, Director, Site Engineering
R. Coad, Manager, Regulatory Compliance
A. Mueller, Manager, Training
L. Lindrose, Manager, Security
M. Wesley, Manager, Maintenance
T. Hilston, Manager, Design Engineering
F. Smith, Manager Emergency Planning

P McNulty, Manger, Radiation Protection

C. Elberfeld, Supervisor, Nuclear Compliance
V. Forbuch, Human Performance

LIST OF ITEMS OPENED, CLOSED, DISCUSSED

Opened and Closed

05000440/2009006-01

NCV

Failure to Adhere to Procedures for Scaffold Affecting

Containment Systems (Section 4OA2.1)

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on

this list does not imply that the NRC inspectors reviewed the documents in their

entirety, but rather, that selected sections of portions of the documents were

evaluated as part of the overall inspection effort. Inclusion of a document on this

list does not imply NRC acceptance of the document or any part of it, unless this

is stated in the body of the inspection report.

PLANT PROCEDURES

Number

Description or Title

Date or Revision

GCI-0016

Generic Civil Instruction: Scaffolding

Erection, Modification or Dismantling

Guidelines

Rev. 15

NOPB-LP-2011

FENOC Cause Analysis

Rev. 07

NOP-LP-2001

Corrective Action Program

Rev. 19

NOBP-LP-2008

FENOC Corrective Action Review Board

Rev. 8

NOBP-OP-0012

Operator Work Arounds, Burdens &

Control Room Deficiencies

Rev. 00

NOBP-LP-2100

FENOC Operating Experience Reference

Guide

Rev. 3

NOP-LP-2100

Operating Experience

Rev. 3

NOP-WM-1001

Order Planning Process

Rev. 10

NOP-WM-4300

Order Execution Process

Rev. 6

PAP-1107

Plant Administrative Procedure:

Temporary Instruction Control

Rev. 7

SOI-P42

Emergency Closed Cooling System

9/11/2008

SOI-P47

Control Complex Chilled Water System

2/16/2008

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number

Description or Title

Date or Revision

CR 00-3709

DG Fuel Oil Strainer Differential Pressure

Switch

11/30/2000

CR 07-14232

Division 2 Emergency Service Water

Inoperable

2/08/2008

CR 07-14306

Inappropriate ASME Code Case Revision

Applied to Support Prompt Operability

Determination for CR 07-14065

2/08/2007

CR 07-16389

Initial License Class 05-01 NRC Exam

Failures

3/5/2007

CR 07-19058

EH-1201 Relay 86g1 Reset Step Missed In

Svi-R43t1328

4/22/2007

CR 07-20446

Unexpected Turbine Trip during Startup

05/13/2007

CR 07-20576

Reactor Scram During Digital Feedwater

Control System Testing under TXI-373

05/15/2007

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number

Description or Title

Date or Revision

CR 07-20585

Plant Restart and Testing and Oversight Plan

05/15/2007

CR 07-20587

Organizational Issues Evaluation - Reactor

Scram during Reactor Feedwater Pump

Turbine Digital Control Tuning

05/15/2007

CR 07-20588

Training Issues - Reactor Scram during

Reactor Feedwater Pump Turbine Digital

Control Tuning

05/15/2007

CR 07-21864

-C-07-05-17 Operations Training Program

Rated Marginally Effective

6/11/2007

CR 07-22981

RHR B Min Flow Valve Disconnect Not

Closed On Entering Cold Shutdown

7/2/2007

CR 07-23175

Potential Mis-Interpretation Of Tech Spec 3.4.1 During Recirc Pump Trip Event

7/9/2007

CR 07-24458

Common Cause of Site Issues

7/31/2007

CR 07-27641

Continuing FME Problems In Vicinity Of Open

Pools And Vessels

10/2/2007

CR 07-28746

Additional Concerns with Bolt Torque for

Recirculation Flow Control Valves

10/17/2007

CR 07-30660

RCIC System Tripped Shortly after Initiation

11/28/2007

CR 07-31437

Housekeeping and Potential Scaffold Issues

in RCIC Room

2/12/2007

CR 07-31788

RHR A Suction Press Low Alarm

2/20/2007

CR 08-34551

Limitorque Valve Operator Grease/Oil

Separation

1/28/2008

CR 08-35163

Unplanned Tech Spec Entry Which Declared

ECC B And Associated Systems Inop

2/10/2008

CR 08-35817

RHR A Suction Pressure Low Alarm

Received On Pump Start

2/23/2008

CR 08-37980

RCIC Venting for CA 07-30660-027 Is

Causing Unnecessary Unavailability Time

2/14/2008

CR 08-40969

High Pressure Core Spray Inoperable

5/28/2008

CR 08-41138

NRC NCV: Failure to Implement Appropriate

RCIC Instrument Test Procedures

5/08/2008

CR 08-41574

Cross Cutting Theme for Human Performance

Aspect H.2(c), Documentation

06/10/2008

CR 08-42164

NRC Questions on Protected Train Postings

and Risk Assessment

06/21/2008

CR 08-42974

Division 1 Diesel Generator Fuel Pump

Strainer Dp High

7/9/2008

CR 08-42982

Fuel Oil Strainer Differential Alarm Received

During Division 1 EDG Operation

7/9/2008

CR 08-43197

H.4(a) Cross Cutting Aspect Trend: Human

Error prevention Technique

7/14/2008

CR 08-43277

Oil Leaking From Valve Gearbox

7/15/2008

CR 08-43483

RHR Pump Min Flow Valve Found Closed

7/20/2008

CR 08-43997

Non-Safety Electrical Manhole Cover

Inadvertently Dropped into Manhole

7/30/2008

CR 08-44438

Alternate Decay Heat Removal Work Impact

8/06/2008

CORRECTIVE ACTION PROGRAM DOCUMENTS REVIEWED

Number

Description or Title

Date or Revision

Due to Reinstallation of Floor Plugs

CR 08-44524

Potential for Engineering Evaluation Requests

Technical Basis to be Exceeded by

Concurrent Barrier Removal

8/07/2008

CR 08-44634

Turbine Building Crane PM Activity in PMI-

0039 Needs to be Updated and Revised

8/12/2008

CR 08-44804

Weak Level of Documentation of Prompt

Operability Determination (POD)

8/14/2008

CR 08-46585

RHR C Min Flow Valve 1e12f0064c Closed

On Pump Start

9/13/2008

CR 08-47659

H.4(b) Cross Cutting Aspect Trend:

Procedural Compliance

10/09/2008

CR 08-48248

Third Quarter Trend Shows an Increase

Trend - Human Error and Inappropriate

Action

10/22/2008

CR 08-48768

Additional Controls for Movement of Light

Loads

10/31/2008

CR 08-48921

Protected Train Walkdown by Shift Manager

Revealed Issues with Postings

11/04/2008

CR 08-49842

NRC Third Quarter Inspection Report Finding:

Fail to Implement Required Risk Management

for Protected Train

10/31/2008

CR 08-50267

Oil Separation In MOV Operator

2/2/2008

CR 08-50270

Oil/Grease Separation In Operator

CR 08-50803

Excel Scaffold Not Meeting Procedure

Requirements

2/12/2008

CR 09-51818

RHR A Hx Outlet Valve Has A 200 DPM

Packing Leak

1/9/2009

CR 09-52476

NRC PI&R 2009: The EOC For Cr 08-40969

Needs Clarification

1/23/2009

CR 09-52687

Locked Closed Valve Does Not Appear To Be

Fully Closed

1/27/2009

OPERATING EXPERIENCE

Number

Description or Title

Date or Revision

200237831

FENOC Evaluation of IN 2006-22

6/30/2007

200239207

FENOC Evaluation of SER 07-06

1/7/2007

200251244

FENOC Evaluation of IN 2007-01

4/8/2007

200252088

FENOC Evaluation of IN 2007-05

4/15/2007

200252089

FENOC Evaluation of IN 2007-06

2/15/2007

200267694

FENOC Evaluation of TR 7-57

9/18/2007

200294004

PY Evaluation of SOER 07-02

7/8/2008

200294208

FENOC Evaluation of TR 7-60

1/5/2009

200318117

FENOC Evaluation of IN 2008-02

3/21/2008

OPERATING EXPERIENCE

Number

Description or Title

Date or Revision

200318386

FENOC Evaluation of IN 2008-04

4/9/2008

CR 02-03435

OE Evaluation of SOER 02-3

9/24/2002

CR 02-03435

OE SOER 02-3 Large Power Transformer

Reliability

9/24/2002

CR 04-05506

OE Evaluation of TR 4-40

10/20/2004

CR 05-02678

GE/GNF Notified the Site of a Potential Part 21

Issue Affecting TS 2.1.1.1

3/24/2005

CR 05-04199

Vendor Potential Reportable Condition due to

Non-Conservatism in the R-Factor

5/10/2005

CR 06-01358

10CFR21 Issued against Rosemount 1153

pressure transmitters

3/22/2006

CR 06-02757

Grand Gulf valve failure OE 22791 Div 1/2 DG

susceptibility

5/12/2006

CR 06-02895

Industry Experience of Unexpected Control

Rod Fail-to-Settle Events

6/28/2006

CR 07-14065

ESW B piping weld leak on outlet of ECC B

Heat Ex.

2/8/2007

CR 07-14235

NRC GL 07-01 Inaccessible or underground

power cable failures

2/8/2007

CR 08-37125

PY-PA-08-01: Organizational Response to

NRC GL 2008-01 less than adequate

3/20/2008

CR 08-44869

Late Coordination of field activities to support

GL 08-01 laser scanning

8/15/2008

CR 08-50367

Fisher 10CFR21 Notice Affects SW2930,

Sw2931 and SW2932

2/3/2008

CR 08-50515

PY Review of Fisher 10CFR21 Notice 2008-02

2/8/2008

OE 25127

Reactor Scram / Digital Feedwater Control

System Logic Flaw

7/05/2007

PAP-0607

Document and Vendor Information Control

Rev. 11

SOI-E21

LPCS System

Rev. 22

SVI-E21-T2001

LPCS Pump and Valve Operability Test

Rev. 20

AUDITS, ASSESSMENTS AND SELF-ASSESSMENTS

Number

Description or Title

Date or Revision

Audit-MS-C-06-10-07 Preventable Equipment Failures Challenges

2/7/2008

Audit-MS-C-08-05-07 Perry CDBI Pre-Assessment PY-SA-08-079

Output Documents Not Identified

4/11/2008

Audit-MS-C-08-05-07

Maintenance and Work Management

Programs

7/23/2008

Audit-MS-C-08-08-22 Composite Human Performance Indicator

For 1st Qtr 2008

4/18/2008

AUDITS, ASSESSMENTS AND SELF-ASSESSMENTS

Number

Description or Title

Date or Revision

CR 06-09998

AFI From PY-SA-08-012 GESILl -

159 Modification Not Implemented For

RWCU Filter Demineralizers

6/8/2008

CR 07-12910

Critical Component Failure Are Not Being

Classified Correctly In The Cap Program

1/18/2007

CR 07-14065

Pinhole Leak On "B" ESW Outlet From "B"

ECC Hx

7/11/2008

CR 07-14120

NRC event 43071, Potential Part 21

issue with GE snubber fluids

1/9/2007

CR 07-14120

Snapshot Sa PY-SA-07-68 Found Design Silt

Depth Exceeded In The ESW Intake Tunnel

7/22/2008

CR 07-14232

Root Cause Analysis Report: Division 2

Emergency Service Water System through

Wall Leakage Operability Review

3/09/2007

CR 07-14306

Inappropriate ASME Code Case Revision

Applied To Support Pod For Cr 07-14065

7/22/2008

CR 07-19932

LTA 50.59 Review of Div. 2 DG Slow Start

FEA

5/3/2007

CR 07-19932

Py-Pa-07-02: LTA 50.59 Review Of Div. 2 Dg

Slow Start Feature

7/22/2008

CR 07-20446

Root Cause Report Main Turbine

Unexpectedly Tripped

6/12/2007

CR 07-20576

Root Cause Analysis Report: Automatic

Level 3 Scram

6/20/2007

CR 07-20585

Plant Restart And Testing And Oversight Plan

8/6/2008

CR 07-20587

Organizational Issues Evaluation - Rx Scram

During RFPT Digital Controls Tuning

10/13/2008

CR 07-20588

Training Issues - Reactor Scram During RFPT

Digital Controls Tuning

10/22/2008

CR 07-22860

HPCS ESW Draindown Test Portion Of SVIi

P45 T2003 Failed.

11/13/2008

CR 07-24458

Common Cause Of Site Issues

11/17/2008

CR 07-24847

Maintenance Enforcement Of Worker

Standards - Continued Improvement

Required

2/11/2008

CR 07-24847

Review Of CRs For Ineffective Corrective

Actions Results In Emergent Trend

8/8/2007

CR 07-25439

Non-Safety Lubricant Utilized on Safety

Related Equipment without justification

8/21/2007

CR 07-28806

Failure Of Work Management And Condition

Report Process

10/18/2007

CR 07-29242

EDG Hallway inspections not performed as

required

10/26/2007

CR 07-30660 and

CR 07-31441

Root Cause Analysis Report: Reactor Core

Isolation Cooling (RCIC) System Trip following

Plant Scram

2/19/2008

CR 07-30676

RPV and RCS Transients vs ASME Fatigue

Limits

11/28/2007

AUDITS, ASSESSMENTS AND SELF-ASSESSMENTS

Number

Description or Title

Date or Revision

CR 07-31183

Cr 07-29026 Investigation Finds Chemistry's

Ineffective Use Of Cap

2/7/2007

CR 08-32531

Valve Found Out Of Position And Near

Miss

1/4/2008

CR 08-32972

Cross-Cutting Theme For Human Performance

Aspect H.3.A, Work Control

1/17/2008

CR 08-33656

2nd Half PYRC/PIU IPA AFI: LTA

Implementation Of PI Processes

1/17/2008

CR 08-34592

Review and process of significant event

reports

1/30/2008

CR 08-37049

MS-C-08-03-01 - MRB inappropriate corrective

action

3/18/2008

CR 08-3709

Pre-CDBI Investigate The Need To Flow

Test The EDG Fuel Oil Eductors

4/25/2008

CR 08-38929

MS-C-08-03-01 Inconsistent Implementation

Of The Corrective Action Program

4/11/2008

CR 08-39035

MS-C-08-03-01 Control Of Work On A Dg In

Standby

4/9/2008

CR 08-39275

Pre-CDBI - Minor Discrepancy In Design

Minimum Flow Rate Value Shown In SVI

4/25/2008

CR 08-39363

MS-C-08-03-01 Safety Equip Not Available To

Support PEI

4/25/2008

CR 08-39452

MS-C-08-03-01 Access To PEI Ladders Is

Inhibited

4/25/2008

CR 08-39873

MS-C-08-04-15: NOBP-NF-1013 References

Outdated Nop-Cc-4001 Steps & Requirements

5/5/2008

CR 08-40311

MS-C-08-03-01 Clearance Program Shortfalls.

5/14/2008

CR 08-40395

Root Cause Corrective Action 07-20576-8 Not

Implemented As Written

5/15/2008

CR 08-41630

Self-Assessment # PY-SA-08-092 -

Addition Of Simulator Vendor Drs To

SCMS

5/29/2008

CR 08-42032

MS-C-08-05-07: Risk Self Assessment Not

Performed

6/19/2008

CR 08-42034

MS-C-08-05-07: Use Of Loop Multipliers

During Risk Evaluations

6/19/2008

CR 08-43587

Snapshot Assmt PY-SA-08-091: Carb Actions

Not Taken, Effectiveness Review LTA

7/22/208

CR 08-43822

Ineffective Corrective Actions For Cr 04-06719

Scram Vent And Drain Valves

7/25/2008

CR 08-44698

Adverse Trend Identified In The Containment

Air Lock Doors

8/13/2008

CR 08-44852

Potential Cross Cutting Theme In Problem

Identification And Resolution (PI&R)

7/29/2008

CR 08-45397

Procedure Enhancement

8/27/2008

CR 08-45505

OE Program AFI - SOER Effectiveness

reviews

8/28/2008

AUDITS, ASSESSMENTS AND SELF-ASSESSMENTS

Number

Description or Title

Date or Revision

CR 08-45509

OE Program AFI - OE in work packages

8/28/2008

CR 08-47153

PY-PA-08-03 Finding: Adverse Trend In

Objective 3, Initial Training

10/1/2008

CR 08-47206

Neg. Note. Item ID'D In Tech. Skills Prgm. SA

- OE In Train Not Incorp HU

9/26/2008

CR 08-47779

Unrecognized OPDRV Results In LER

10/13/2008

CR 08-47895

MS-C-08-08-22: CA not responded to in

timely manner

10/15/2008

CR 08-48385

MS-C-08-09--08 - Implementation Issues

Regarding Delinquent M&TE

10/24/2008

CR 08-48388

MS-C-08-09-08 - Delinquent M&TE Not

Returned By The Due Date

10/24/2008

CR 09-51621

Untimely Review of TR 6-56

1/6/2009

FL-SA-08-004

Focused SA - Operating Experience Program

9/5/2008

PY-SA-07-025

Perform A Ongoing Self-Assessment Of The

OE Program Utilizing Guidelines For The Use

Of operating Experience

6/14/2007

PY-SA-07-087

Problem Solving and Decision Making

8/31/2008

PY-SA-08-020

Evaluate the actions taken to improve the

Human Performance in the INPO identified

AFIs have been successful

11/14/2008

PY-SA-08-058

Effectiveness of Corrective Actions for

Contamination Control AFI - Tracked by CA

07-29353-4

7/31/2008

PY-SA-08-091

Extent of Condition/Effectiveness Reviews

Assessment

7/25/2008

PY-SA-08-117

Follow up to Common Cause Analysis (CR 07-

24458)

10/28/2008

DRAWINGS

Number

Description or Title

Date or Revision

C-937-333

Intermediate Building - Elevation 654-6

Miscellaneous Duct Supports

A

D-912-604

System Diagram: Containment Vessel and

Drywell Purge

BB

D-936-742

Intermediate Building - Northwest Elevation

654-6 - Duct Support Locations

E

CONDITION REPORTS GENERATED DURING INSPECTION

Number

Description or Title

Date or Revision

CR-09-51876

NRC PI&R 2009: All Part 21 Notifications are

not routed through vendor coord.

1/12/2009

CONDITION REPORTS GENERATED DURING INSPECTION

Number

Description or Title

Date or Revision

CR-09-51882

NRC PI&R 2009: IN 2006-022 Evaluation not

complete

1/12/2009

CR-09-51896

NRC PI&R 2009; Incomplete CA Closure

Documentation

1/13/2009

CR-09-52038

Scaffold Not in Compliance with Plant

Procedures

1/15/2009

CR-09-52075

NRC PI&R 2009: Corrective Actions and PM

not appropriately cross-referenced

1/16/2009

CR 09-52385

NRC PI&R 2009 Ca Inappropriately Closed

1/22/2009

CR-09-52450

Potential Adverse Trend in Scaffold Program

1/23/2009

CR-09-52474

Scaffold Not in Compliance with Plant

Procedures - No Prompt Operability

Determination Performed

1/23/2009

CR-09-52476

NRC PI&R 2009; The EOC for CR 08-40969

Needs Clarification and Increased Scope

1/23/2009

CR-09-52641

NRC PI&R 2009 Indiv. Offered to Open HRA

Lock for an Indiv. Not in his Work Crew.

1/27/2009

CR-09-52670

NRC PI&R 2009: OE Evaluation of TR 7-57

nor IAW procedure

1/28/2009

CR-09-52687

Locked Closed Valve Does Not Appear To Be

Fully Closed,

1/27/2009

CR-09-52702

Engineering Evaluation Completed for Scaffold

Configuration Identified in CR 09-52038 Was

Incorrect

1/27/2009

CR-09-52756

NRC PI&R 2009; CR 08-34584 Analysis Did

Not Address Problem Statement

1/29/2009

CR-09-52772

Scaffolding Seismic Qualification Calculation

Issues

1/27/2009

MISCELLANEOUS

Number

Description or Title

Date or Revision

23:02.039

Calculation: Seismic Qualification of

Scaffolding

Order 200299311

Perform RCIC Instrument Line and Transmitter

Venting

2/14/2008

Order 200299322

Perform RCIC Instrument Line and Transmitter

Venting

5/15/2008

List of Acronyms Used:

CAP

Corrective Action Program

CFR

Code of Federal Regulations

CR

Condition Report

ECP

Employee Concerns Program

NCV

Non-cited Violation

NRC

Nuclear Regulatory Commission

OE

Operating Experience

PI&R

Problem Identification & Resolution

RHR

Residual Heat Removal

SCWE

Safety Conscious Work Environment

TS

Technical Specification