IR 05000440/1981004

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-440/81-04 & 50-441/81-04 on 810205.No Noncompliance Noted.Major Areas Inspected:Preservice Insp Procedures,Work Activities & Weld Preparations & Equipment
ML20003E539
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 02/24/1981
From: Danielson D, Ward K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20003E538 List:
References
50-440-81-04, 50-440-81-4, 50-441-81-04, 50-441-81-4, NUDOCS 8104060068
Download: ML20003E539 (3)


Text

.

.

O

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report Nos. 50-440/81-04; 50-441/81-04 Docket Nos. 50-440; 50-441 License Nos. CPPR-148; CPPR-149 Licensee: Cleveland Electric Illuminating Company Post Office Box S000 Cleveland, OH 44101 Facility Name: Perry Nuclear Power Plant, Units 1 and 2 Inspection At: Perry Site, Perry, OH Inspection Conducted: February 5, 1981 tyth-vlh~

Inspector:

K. D. Ward kG

/

brxLMh-

'

Approved By:

D. H. Danielson, Chief J Wh/

Materials and Processes Section Inspection Summary Inspection on February 5, 1981 (Report Nos. 50-440/81-04; 50-441/81-04)

Areas Inspected: Preservice inspection (PSI) procedures, work activities, nondestructive examination (NDE) personnel certifications, equipment and weld preparations. The inspection involved a total of seven inspector-hours by one NRC inspector.

Results: No items of noncompliance or deviations were identified.

810406004%

-

,

%

DETAILS Persons Contacted Cleveland Electric Illuminating Company (CEI)

  • H. balls, QE, Senior NDE Level III, Administrator Gilbert Associates Incorporated (GAI)

J. Gilstrap, CQE Kaiser Engineers Incorporated KEI)

R. Sheer, CQC, Mechanical Nuclear Energy Services, Inc. (NES)

R..Bott, Site Manager The inspector also contacted and interviewed other licensee and contract.r employees.

  • Denotes those attending the exit interview.

Licensee Action on Previous Inspection Findings (0 pen) Unresolved Item 440/80-05, Unit 1, result of Dikker valve radiography.

(0 pen) Unresolved Item 441/80-05, Unit 2, result of Dikker valve radiography.

The interpretation of radiographs between the licensee and G.E. is a continuing item.

Functional or Program Areas Inspected Recirculation piping system Loop A IB33 - weld A4 was observed as the workmanship sample, also welds A10 and B9 were observed as prepared for PSI.

It was discussed that the welds would not have sharp edges and how the welds would be blended to the base material.

G.E. and Pullman are preparing the welds for PSI.

Peabody Magnaflux Corporation will be performing the radiography (RT) prior to the ultrasonic examinations (UT).

It was discussed how important it is to have permanent identification markers of how the welds are RT'd so the RT can correlate with the UT if an indication is found.

NES has the contract to perform the PSI. 'To date it is not known to what Code and Addenda the PSI will be performed to.

The year 'and addenda will be stated in each procedure.

-2-L

-

e

-.

_.

..

.

... - -.

-. _ -.

- _ -.....-. -. _ -. -. - - -.-

.. -... - - -

.

'

,

-

't

'

,

i Ultrasonic, liquid penetrant and visual examinations are the only methods of NDE that may be performed by NES.

NDE personnel certifications will be on site and approved prior to the NDE.

Calibration blocks and instruments will be on site and approved prior to

,

- the UT.

No items of noncompliance or deviations were identified.

Exi t - Inte rview -

I The inspector met with Mr. H. Walls (denoted in Persons Contacted paragraph)

~

at the conclusion of the-inspection. The inspector summarized the scope and findings of the inspection noted in this report.

.t I

i i

i

,

4-3-

'

.

.-