IR 05000395/2021010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Programs) Inspection Report 05000395/2021010
ML21215A044
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 08/02/2021
From: James Baptist
Division of Reactor Safety II
To: Stoddard D
Dominion Energy Virginia
References
IR 2021010
Download: ML21215A044 (15)


Text

August 2, 2021

SUBJECT:

VIRGIL C. SUMMER NUCLEAR STATION, UNIT 1 - DESIGN BASIS ASSURANCE INSPECTION (PROGRAMS) INSPECTION REPORT 05000395/2021010

Dear Mr. Stoddard:

On June 25, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Virgil C. Summer Nuclear Station, Unit 1. On July 29, 2021, the NRC inspectors discussed the results of this inspection with Mr. G. Lippard and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Virgil C. Summer Nuclear Station, Unit 1.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 05000395 License No. NPF-12

Enclosure:

As stated

Distribution via LISTSERV

ML21215A044 X

SUNSI Review

X Non-Sensitive Sensitive

X Publicly Available Non-Publicly Available

OFFICE RII/DRS RII/DRS RII/DRS RII/DRS

NAME P. Braxton J. Nicely G. Ottenberg J. Baptist

DATE 7/30/2021 7/29/2021 7/30/2021 8/2/2021

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000395

License Number:

NPF-12

Report Number:

05000395/2021010

Enterprise Identifier: I-2021-010-0036

Licensee:

Dominion Energy

Facility:

Virgil C. Summer Nuclear Station, Unit 1

Location:

Jenkinsville, SC

Inspection Dates:

June 07, 2021 to June 25, 2021

Inspectors:

P. Braxton, Reactor Inspector

G. Nicely, Contractor

G. Ottenberg, Senior Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (programs) inspection at Virgil C. Summer Nuclear Station, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Fully Address Previous NCV Related to Maximum Expected Differential Pressure for the XVG08811A(B)-SI and XVG08812A(B)-SI Valves Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000395/2021010-01 Open/Closed None (NPP)71111.21N.

The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI, "Corrective Action," when the licensee failed to correct a condition adverse to quality associated with the calculation of the maximum expected differential pressure (DP) for the containment sump valves.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.21N.02 - Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements POV Review (IP Section 03)

The inspectors:

a. Evaluated whether the sampled POVs are being tested and maintained in accordance with NRC regulations along with the licensees commitments and/or licensing bases.

b. Evaluated whether the sampled POVs are capable of performing their design-basis functions.

c. Evaluated whether testing of the sampled POVs is adequate to demonstrate the capability of the POVs to perform their safety functions under design-basis conditions.

d. Evaluated maintenance activities including a walkdown of the sampled POVs (if accessible).

(1) XVG03111B-SW; RBCU 1B & 2B CI System Return Isolation Valve
(2) XVG08811B-SI; Containment Sump RH Pump B Suction Isolation Valve
(3) LCV00115C-CS; Volume Control Tank Outlet Isolation Valve
(4) XVG08000A-RC; Pressurizer PORV Inlet Isolation Valve
(5) XVB03116A-SW; Service Water Pump A Discharge Valve
(6) XVB09503A-CC; RH Heat Exchanger A CC Inlet Valve
(7) PCV00444B-RC; Pressurizer Power Operated Relief Valve (PORV)
(8) IFV02030-MS; EF Pump Turbine Steam Supply Flow Control Valve
(9) XVG06067-HR; Alternate Purge Exhaust Isolation Valve

INSPECTION RESULTS

Failure to Fully Address Previous NCV Related to Maximum Expected Differential Pressure for the XVG08811A(B)-SI and XVG08812A(B)-SI Valves Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems

Green NCV 05000395/2021010-01 Open/Closed

None (NPP)71111.21N.0 The inspectors identified a Green finding and associated Non-cited Violation (NCV) of Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion XVI, "Corrective Action," when the licensee failed to correct a condition adverse to quality associated with the calculation of the maximum expected differential pressure (DP) for the containment sump valves.

Description:

One of the required safety functions of the residual heat removal (RHR) system is to establish long-term recirculation reactor cooling after loss of coolant accidents (LOCAs). The RHR pump containment sump suction valves, XVG08811A/B-SI and XVG08812A/B-SI, must open to establish a suction path from the containment sump to the RHR pumps. NRC inspection report 2006008 (ADAMS ML062080036) identified a 10 CFR 50, Appendix B, Criterion XVI violation (NCV 2006008-01), for the licensee's failure to identify a condition adverse to quality that was discussed in industry OE20884. The OE identified that small break (SB) LOCAs could produce more limiting DP scenarios for the RHR pump containment sump suction valves due to the potential for the RHR pump to operate under minimum flow conditions. The higher DPs require higher MOV actuator thrust to successfully operate.

Condition report, CER 06-02041, was written in response to NCV 2006008-01, but it was closed relying on actions to be taken in another condition report, CER-05-03241. Following issuance of NCV 2006008-01, CER-05-03241 re-evaluated the increase in differential pressure across the XVG08811A/B-SI and XVG08812A/B-SI valves, and stated:

The maximum possible SBLOCA opening differential pressures was re-estimated to be ~

460 psid for XVG08812A/B-RH & ~ 455 psid for XVG08811A/B-RH assuming the RHR pump suction pressure is controlled at the RHR inlet relief valve setpoint. Based on current design basis assumptions, all of the RHR sump MOVs, except XVG08811B, were found to have sufficient open thrust capability for their maximum expected differential pressure. Further review indicates that the voltage drop calculations for XVG08811B are overly conservative and that the use of more realistic assumptions results in a 30 V increase in terminal voltage. When crediting the higher terminal voltage, the open thrust capability for XVG08811B was found to exceed the minimum required opening thrust for the SBLOCA scenario by approximately 4.35%. This re-confirmed the prior conclusion that the existing containment sump valves/actuators can successfully perform their design function of opening during the transition to CL recirculation during a SBLOCA.

At the time of this inspection, the station's record calculation identified the maximum expected DP in the open direction as 49 psid as opposed to the 460 & 455 psid identified above.

While the higher DP condition had been evaluated in CER-05-03241 as acceptable, it initially resulted in negative calculated margin for the XVG08811B-SI valve. The DP calculation, DC01520-049, the associated minimum required thrust calculation, DC01520-059, and the actuator capability calculation, DC01520-067, were planned to be updated to reflect the evaluation in CER-05-03241. However, the calculations were never updated because engineering change request ECR 72009 was not implemented as intended, explaining why the station's record calculation still incorrectly identified 49 psid as the design basis assumption. As a result, the licensee was over-estimating the margin available for the MOVs to perform their safety functions. The MOV program relies on the calculated margins to determine valve operability and the required periodic verification test intervals.

Corrective Actions: Upon the inspector's discovery, the licensee reconfirmed that the XVG08811A/B-SI and XVG08812A/B-SI valves remained capable of performing their intended functions, and would have positive margin after accounting for the higher DP and taking credit for adjustments to the actuator capability.

Corrective Action References: CR -21-01620

Performance Assessment:

Performance Deficiency: The licensees failure to correct a condition adverse to quality associated with the calculation of maximum expected differential pressure for the containment sump valves, was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee had to change assumptions to obtain favorable results as they revised the actuator capability calculations for the XVG08811B-SI valve in order to demonstrate the valve had positive design margin.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Specifically, the inspectors used IMC 0609, Appendix A, Exhibit 2, "Mitigating Systems Screening Questions," and determined the finding was a deficiency affecting the design or qualification of a mitigating structure, system, or component (SSC), and the SSC maintained its operability or PRA functionality.

Cross-Cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, required Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected. Contrary to this, the licensee failed to assure that a condition adverse to quality was promptly identified and corrected. Specifically, previously identified incorrect calculation of the maximum expected differential pressures was not corrected.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 29, 2021, the inspectors presented the design basis assurance inspection (programs) inspection results to Mr. G. Lippard and other members of the licensee staff.
  • On June 25, 2021, the inspectors presented the initial inspection results to Mr. R. Justice and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21N.02 Calculations

DC 08200-001

ESF Degraded Voltage Logic and Settings

Rev. 29

DC01520-035

Maximum Differential Pressures for SW GL 89-10 Motor

Operated Butterfly Valves

Rev. 3

DC01520-039

Maximum Differential Pressures for CCWS Quarter-turn

MOV Operation

Rev. 1

DC01520-049

Maximum Differential Pressure for Safety Injection System

MOV Operation

Revs. 3, 4, &

DC01520-050

Motor Operated Valve Weak Link Analysis Reports

Revs. 0, 1, &

DC01520-059

Minimum Required Thrust for Rising Stem MOVs in the

Safety Injection System

Rev. 12

DC01520-062

Minimum Required Thrust for Rising Stem MOVs - RC

System,

Rev. 10

DC01520-065

Design, Review and Capability of Rising Stem MOVs

Rev. 14

DC01520-065

Design, Review and Capability of Rising Stem MOVs

Rev. 14

DC01520-066

Minimum Required Thrust for Rising Stem MOVs

Rev. 11

DC01520-067

Design, Review and Capability of Rising Stem MOVs

Rev.16

DC01520-067

Design, Review and Capability of Rising Stem MOVs in

the CS, RH and SI System

Rev. 16

DC01520-069

MOV Thermal Overload Calculation

Rev. 3

DC01520-089

GL-89-10 MOV Scope, Grouping and Engineering

Justification

Revs. 6 & 11

DC01520-090

Design, Review and Capability of Henry Pratt Generic Letter 89-10 Motor Operated Butterfly Valves

Rev. 5

DC01520-093

Measurement Conversions and Error Determination for

MOV Parameters

Rev.3

DC01520-093

Measurement Conversions and Error Determination for

MOV Parameters Obtained Per ES-513

Rev. 3

DC01520-094

Max Operating Torque for Henry Pratt GL89-10 Motor

Operated Butterfly Valves

Rev. 3

DC01520-102

Force Required to Overcome Pressure Locking

XVG08000A

Rev. 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC01521-011

Determination of the Limiting Line Pressure and Maximum

Expected Differential Pressure for Category 1 Air

Operated Valves In The MS System

Rev. 1

DC0152A-007

Determination of Limiting Line Pressure and Maximum

Expected Differential Pressure for Air-Operated Valves,

HR Purge CIV's

Rev. 1

DC0152A-008

KVAP Analysis for Air Operated Valves

XVG06056/6057/6066/6067-HR

Rev. 1

DC0152A-012

KVAP Analysis for Air-Operated Valves IFV02030-MS,

IPV/02000/0210/2020-MS & XVM02801A/B/C-MS

Rev. 1

DC08200-003

Class 1E 460V MOV Starting Voltages

Rev. 8

DC08760-007

MCC Control Circuit Analysis

Rev. 2

Corrective Action

Documents

CR-11-01045,

CR-11-00991,

CR-11-01027,

CR-11-00631,

CR-11-00750,

CR-11-00782,

CR-11-00956,

CR-20-03556,

CR-20-03557,

CR-20-03560,

CR-21-00678,

CR-05-03241,

CR-06-02041,

CR-20-02322,

CR-20-02274

Corrective Action

Documents

Resulting from

Inspection

21-011679

Review appropriateness of Commonwealth Edison White

Paper 125 Revision 3 in the VCS actuator capability

calculations.

06/21/2021

21-01559

TR01520-001 stated in the notes for XVG08811A&B-SI

that this valve did not have a closed safety function.

06/08/2021

21-01574

MOV program needs to update it engineering review of

static test data to include the refined gate unwedging

6/10/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

equation.

21-01586

Evaluate the need to revise SAP-143 to resolve the

potentially contradictory guidance and revise SAP-143 as

required

06/10/2021

21-01620

ECR 72009 not completed and the calculations updated in

a timely manner.

6/14/2021

21-01629

Procedure Enhancement of EMP0445.007 to include QSS

check prior to MOVATs

06/15/2021

21-01657

Magnesium rotor degradation

06/17/2021

21-01678

Track review and revision of MOV calculations and

program documents as needed regarding degraded

voltage MOV calculation and MOV diagnostic test data.

6/21/2021

21-01680

Calculation DC0152A-008 needs to be updated

06/21/2021

21-01685

review the application of IEEE 741-2017 in DC08200-001

and determine if it is applies to DC08200-003 Section 7.1

06/21/2021

21-01698

Difference in COF numbers between DC01520-090 and

DC01520-094

06/23/2021

21-01699

Two maximum differential pressure values (30 psid and 75

psid) are reflected in various 152 series MOV calculations

(DC01520-050,-090) and program documents for

XVB09503A-CC.

06/23/2021

21-01700

Issues with design calculation DC01520-102

06/23/2021

21-01701

Drawing or maintenance procedure doesn't provide

installation orientation regarding flow and flow direction not

physically marked on valve.

06/23/2021

Drawings

1MS-025-067

ASME Assembly Drawing MOV LCV00115C-CS

Rev. 6

1MS-025-115

ASME Assembly Drawing MOV XVG08000A

Rev. 5

1MS-25-118

Motor Operated Gate Valve Model 14000GM84FEH00

Rev. 5

1MS-25-290-2

inch 150 Gate Valve-R.S. Bolted Bonnet-Butt Welds

Ends Motor Oper-Sgl Pack

Rev. B

1MS-25-572

16" thru 24" 1100 Nuclear Valve Cross-section and

Materials List ASME Section III Class Flange X Flange

Rev. 2

1MS-25-935

ASME Assembly Drawing AOV PCV00444B-RC

Rev. 3

1MS-50-105

Emergency Feedwater Pump Turbine Control Valve

Rev. 10

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

B-201-359

Electrical MCC Listing XMC1DA2Y, Sht 1

Rev. 12

B-201-362

Electrical MCC Listing XMC1DB2Y, Sht 1

Rev. 10

B-208-011

Electrical-Elementary Diagram RHR Heat Exchanger Inlet

Valve (XVB9503A)

Rev. 5

B-208-021

Electrical Elementary Diagram LCV-115C, Sheet 34

Rev. 10

B-208-054

inch Continuous Purge Line to HR System Isolation

Valve XVG-6067 & 6057, Sht 23

Rev.8

B-208-067

Main Steam to EFW Pump Turbine Isolation Valve IFV-

2030, Sht 46

Rev. 11

B-208-082

Electrical Elementary Diagram XVG08000A,Sht 10

Rev. 8

B-208-095

Electrical-Elementary Diagram Recirc Sump to RHR

Pump B Isol VV 8811B (XVG8811B)

Rev. 12

B-208-101

Electrical-Elementary Diagram Service Water Pump A

Discharge Valve (XVB3116A)

Rev. 9

B-208-101

Isolation Valve XVG3111B, Sht 40

Rev. 7

B-816-083

Instrument Air Supply Diagram

Rev. 9

B-817-130

PORV Control Air Signal Diagram

Rev. 5

C-4454

Pratt 1100 Nuclear Water Valve HB Operator SMB000

Motor Replaceable Packing Bonnet Flange X Flange

Rev. 2

D-302-011

Main Steam

Rev. 41

D-302-611

System Flow Diagram Component Cooling

Rev. 24

E-302-69

System Flow Diagram Safety Injection

Rev. 23

IMS-25-756-1-0

inch 150 Weld End Gate Valve, Sht 1

Rev. 0

Engineering

Evaluations

0310-0028-

CALC-001

Calculation of EDG Voltage and Frequency Variations on

Safety-Related MOVs

Rev. 2

2865C

V. C. Summer Nuclear Station JOG MOV Periodic

Verification Classification

Rev. 0

R015239

Comanche Peak MOVs VS VCSNS MOVs

07/23/1997

Miscellaneous

Power Operated Valves Self-Assessment

Rev. 0

DBD-MV2

Motor Operated Valve Design Review, Capability and

Setup Volume 2 (MV2)

Rev. 6

ECR 50316

Automatic Transfer to the RB Sump

Rev. A

ECR 70460

Limitorque SMB-000 Motor Replacement

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EI-3-009

Teledyne Check-out Procedure for Quick Stem Sensors

Rev.0

ER-AA-IST-10

ASME Inservice Testing Program

Rev. 7

MRF 22765B

Pressure Locking of SI Sump Recirc Valves

11/13/1995

TEP-3-023

Teledyne In-Situ Calibration of Thrust/Torque Strain

Gages

Rev. 3

TR-01520-004

AOV Setup, Test and Performance Validation Summary

Report

Rev. 9

TR-01520-007

PORV Qualification for Inadvertent Safety Injection

Rev. 0

TR01520-001

GL 89-10 MOV Setup, Test and Performance Validation

Summary Report

Rev. 9

TR01520-004

SAP-0159 Air Operated Valve ( Category 1) Setup, Test,

and Performance Validation Summary Report

2/10/2021

TWR RO15239

Comanche Peak MOVs vs. VCSNS MOVs

07/23/1997

VCSNS - DBD -

SI

SAFETY INJECTION SYSTEM (SI)

Rev. 16

VCSNS - EDBD -

CC

Component Cooling Water System CC

Rev. 13

VCSNS-DBD-ES

Electric Power System

Rev. 6

VCSNS-DBD-HS

Post-Accident Sampling, Nuclear Sampling, and Hydrogen

Removal Systems

04/08/21

VCSNS-DBD-MS

Main Steam

05/03/2021

VCSNS-DBD-RC

Reactor Cooling System

Rev. 13

VCSNS-DBD-SW Service Water System

07/25/19

WCAP-13097

System Operating Basis for Motor Operated Valves

Rev. 0

Procedures

EMP-445.007

Testing of Motor Operated Valves

Rev. 15

EMP-445.019

MOV Magnesium Rotor Inspection

Rev. 1

ER-AA-IST-102

ASME IST Program - Inservice Testing of Valves

Rev. 8

ER-AA-IST-107

ASME IST Program - Inservice Testing of Active Motor

Operated Valves

Rev. 0

ES-510

Sizing of Thermal Overloads

Rev. 2

ES-513

MOV Program Implementation

Rev. 2

ES-527

Control and Maintenance of the Plant Lubrication Manual

Database

Rev. 1

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

GTP-302

Inservice Testing of Valves Fourth Ten Year Interval

Rev. 17

ICP-240.169

Valve Diagnostic Procedure

Rev. 4

MMP-445.057

Maintenance of IFV02030-MS and IFV02030-O-MS

Rev. 3

SAP-0143

Preventive Maintenance Program

Rev. 16C

SAP-0999

Corrective Action Program

Rev. 19C

SAP-160

Motor Operated Valve Program

Rev. 1

Work Orders

1602584-

001,1711121-

001, 217450041,

1716500-001,

1716501-001,

2017872-001,

2100008-001,

1902265-001,

1902451-001,

1902989,

2100011-001,

1902989-001,

1711218-001,

1711217-002,

1712429-001,

1712429-003,

1712429-004,

1711219-001,

2017465-001,

2008733-002,

2101920-001,

1109922-001