IR 05000391/2015613
ML15142A663 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 05/22/2015 |
From: | Haag R NRC/RGN-II/DCP/CPB3 |
To: | Skaggs M Tennessee Valley Authority |
References | |
IR 2015613 | |
Download: ML15142A663 (21) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION May 22, 2015
SUBJECT:
WATTS BAR NUCLEAR PLANT UNIT 2 CONSTRUCTION - NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION REPORT 05000391/2015613
Dear Mr. Skaggs:
On April 10, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection of construction activities at your Watts Bar Unit 2 reactor facility. The enclosed inspection report documents the inspection results, which were discussed on April 10, 2015, with Mr. Zeringue and other members of your staff.
This problem identification and resolution (PI&R) inspection examined activities conducted under your Unit 2 construction permit as they relate to identification and resolution of problems, compliance with the Commissions rules and regulations, and with the conditions of your construction permit. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings were identified during this inspection.
In accordance with 10 Code of Federal Regulations (CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Should you have questions concerning this letter, please contact us.
Sincerely,
/RA/
Robert C. Haag, Chief Construction Projects Branch 3 Division of Construction Projects Docket No. 50-391 Construction Permit No: CPPR-92
Enclosure:
Inspection Report 05000391/2015613 w/Attachment
REGION II==
Docket No: 50-391 Construction Permit No: CPPR-92 Report No.: 05000391/2015613 Applicant: Tennessee Valley Authority (TVA)
Facility: Watts Bar Nuclear Plant, Unit 2 Location: 1260 Nuclear Plant Rd Spring City TN 37381 Inspection Dates: April 06 through April 10, 2015 Inspectors: C. Taylor, (Lead) Senior Construction Project Inspector J. Baptist, Senior Construction Project Inspector C. Jones, Senior Construction Inspector N. Staples, Senior Project Inspector E. Patterson, Construction Resident Inspector J. Fuller, Senior Construction Resident Inspector Approved By: Robert C. Haag, Chief Construction Projects Branch 3 Division of Construction Projects Enclosure
EXECUTIVE SUMMARY
Watts Bar Nuclear Plant, Unit 2
NRC Inspection Report 05000391/2015613 This inspection assessed implementation of the corrective action program (CAP) for the Watts Bar Unit 2 construction completion project and ongoing CAP transitional activities to merge Unit into the Watts Bar site wide CAP. The inspection program for Unit 2 construction activities is described in NRC Inspection Manual Chapter 2517. Information regarding the Watts Bar Unit 2 Construction Project and NRC inspections can be found at http://www.nrc.gov/info-finder/reactor/wb/watts-bar/construction-insp-info.html.
Inspection Results
- In general, the threshold for initiating problem evaluation reports (PERs) was low and PERs were appropriately categorized. For the majority of PERs reviewed, the inspectors determined that problem evaluations were effective in identifying corrective actions that addressed the problem. [Section Q.1.1]
- The inspectors determined that adequate measures have been established to evaluate and incorporate applicable operating experience into the CAP. [Section Q.1.1]
- The inspectors determined that TVA and Bechtel have established an acceptable program and environment for allowing employees to identify quality or safety-related concerns. [Section Q.1.1]
- The inspectors determined that TVA and Bechtel have established an acceptable transition process that will integrate the Unit 2 CAP into the CAP that Unit 1 is under.
[Section Q.1.1]
Table of Contents I. QUALITY ASSURANCE PROGRAM ..................................................................................... 4 Q.1 Quality Assurance Program Implementation ................................................................. 4 Q.1.1 Implementation of Corrective Action Program During Construction (IP 35007) ............... 4 IV. OTHER ACTIVITES ............................................................................................................. 7 OA.1.1 Status of PERs Issued in Response to Previous NRC Unresolved Items and Violations ........................................................................................................................ 7 V. MANAGEMENT MEETINGS .............................................................................................. 8 X.1 Exit Meeting Summary ..................................................................................................... 8
REPORT DETAILS
I. QUALITY ASSURANCE PROGRAM Q.1 Quality Assurance Program Implementation Q.1.1 Implementation of Corrective Action Program During Construction (IP 35007)
a. Inspection Scope
The inspectors assessed the adequacy of the Tennessee Valley Authority (TVA) and Bechtel program for identification, evaluation, and corrective action of conditions adverse to quality (CAQs) during the period since the previous problem identification and resolution inspection in April 2014. This was accomplished by reviewing selected problem evaluation reports (PERs), verifying corrective actions were implemented, and attending meetings where PERs were screened for significance to determine whether the licensee was identifying, accurately characterizing, and entering problems into the Corrective Action Program (CAP) at an appropriate threshold.
The inspectors reviewed a sample of PERs and Service Requests (SRs) selected from the applicants CAP for Watts Bar Unit 2. The sample included problems addressed by a diverse selection of plant departments and issues classified under all of the significance levels. The sample also covered a diverse selection of sources, including problems identified in audits and assessments, nonconforming results from inspections and tests, findings from NRC inspections, concerns from anonymous sources, and concerns identified as adverse trends. Most PERs were reviewed after corrective actions had been implemented; however, some were reviewed after the corrective action plan was developed but prior to implementation.
The inspectors also reviewed the applicants alternate issue tracking systems that address issues that were not classified as CAQs. This review targeted verification of appropriate characterization and closure of issues managed outside the CAP. The alternative issue tracking systems that were sampled included Test Deficiency Notices (TDNs), Quality Control (QC) Rejects, and Over/Short/Damaged/and Discrepant (OSD&D) receipt inspection items. These systems were defined as corrective Work Processes approved to track/implement correction, according to TVAs CAP procedure (NC-PP-3, Revision 16).
The inspectors reviewed the current CAP procedures to assess the adequacy of the CAP instructions for the identification, evaluation, and corrective action of CAQs. The inspectors assessed the process utilized to screen PERs for applicability to Unit 1. It was identified that designated staff from Unit 1 routinely reviewed all PERs to determine applicability of PERs and risk significance. For PERs that were determined to have impact on Unit 1, a separate PER was created under the CAP program for Unit 1 and all associated procedures such as root cause guidance and trend guidance would be utilized to resolve the issue. The inspectors review evaluated the applicants consideration for extent of condition, generic implications, common cause and previous occurrences (trending), including the identification of root and contributing causes along with actions to prevent recurrence for significant CAQs.
The inspectors reviewed the plans to transition the Unit 2 CAP into the TVA Nuclear Power Group (NPG) CAP that is currently in place for Watts Bar Unit 1. The inspectors interviewed staff from both Unit 1 and Unit 2 who were directly involved in developing these transition plans. The inspectors also reviewed relevant procedures, discussed staffing levels, and required training to fully support a dual-unit Watts Bar CAP.
The inspectors reviewed TVAs and the major contractors (Bechtel) programs for resolving employee concerns. The inspectors interviewed TVAs and Bechtels employee concerns representatives, reviewed a sample of PERs related to employee concerns, and PERs initiated as a result of employee concerns. The inspectors also reviewed several anonymous PERs to determine if they had been adequately captured and addressed. The inspectors reviewed and evaluated the adequacy of the programs, which provide employees with an alternate method to identify quality or safety-related concerns. The inspectors also reviewed surveys and assessments of the employee concerns programs.
The inspectors reviewed a sample of the applicants management and quality assessments, audits, and trend reports to verify adverse results were properly evaluated and dispositioned within the CAP. The inspectors reviewed the revision history for CAP implementing procedures and assessed the integration of industry operating experience into the corrective action process. Direct observations by inspectors included meetings of the Project Review Committee (PRC) and the Construction Completion Management Review Committee (CCMRC) as they screened newly reported problems and reviewed dispositions for selected issues.
Specific PERs and other documents reviewed are listed in the attachment.
b. Observations and Findings
No findings were identified.
The inspectors made the following observations as a result of their inspections:
- (1) Effectiveness of Identifying, Evaluating, and Correcting Problems Identifying Problems The inspectors determined that, for the most part, the applicant was effective in identifying problems and entering them into the CAP. PERs normally provided complete and accurate characterization of the subject issues. Employees were encouraged by management to initiate PERs. The inspectors independent review did not identify any significant adverse conditions which were not in the CAP for resolution. The use of trending at the site was comprehensive and effective in identifying areas for improvement.
Evaluating Problems Through the attendance of CAP meetings, including the PRC and CCMRC, the inspectors determined that the applicant adequately prioritized issues that were entered into the CAP. Service requests that were discussed during the meetings were appropriately dispositioned.The inspectors determined that the threshold for closing items as SRs, closing items to a WO, and creating a PER when necessary were determined to be adequate. The inspectors observed a few PERs where documentation was lacking, however, appropriate corrective actions were being taken for each example.
Correcting Problems Based on a review of numerous PER corrective actions and their implementation, the team found, for the most part, that the applicants corrective actions developed and implemented for problems were commensurate with the safety significance of the issues.
The inspectors did not identify any technical issues associated with delays the inspectors noted for some procedure changes and revisions.
- (2) Use of Operating Experience The inspectors determined that the applicants measures used to identify, evaluate and incorporate applicable industry and operating experience (I&OE) information into the CAP contained processes for including vendor recommendations and internally generated lessons learned. The I&OE information was collected, evaluated, and communicated to the affected internal stakeholders as specified in TVA and Bechtel procedures. The inspectors determined that appropriate corrective actions were developed and implemented for the sample of I&OE problem evaluation reports reviewed for the Watts Bar Unit 2 Construction Completion Project.
- (3) Safety Conscious Work Environment (SCWE)
The inspectors reviewed several anonymous PERs and PERs that either referred to the employee concerns program or PERs generated as a result of employee concerns. The inspectors also interviewed senior employee concerns coordinators and construction workers out in the field for both TVA and Bechtel. The inspectors determined that TVAs and Bechtels employee concern programs were adequate. The senior employee concerns coordinators expressed knowledge of the employee concerns program and the ability to raise safety related concerns through various available means. The inspectors noted that the construction workers that were interviewed were also knowledgeable of the employee concerns program and were comfortable raising nuclear safety concerns.
The employee concerns program staff provide several training sessions. They provide employee concerns program information in newsletters, and they also walk around the site frequently, talk daily to staff, and attend several meetings to ensure that staff is aware of the employee concerns programs and know how to raise concerns if necessary.
- (4) Corrective Action Program Performance Insights The sample of audits, assessments, and surveillances reviewed by the inspectors confirmed that management and quality personnel actively conducted observations and effectiveness reviews of the CAP. These program assessments concluded that overall, the CAP was effectively implemented. The applicant continues to track and trend issues, run summary reports on the trend data, and present results to management in several meetings, such as the site status meeting, CCMRC, etc. The inspectors reviewed the implementation of trending for adverse conditions identified in PERs, Service Requests, and Test Deficiency Notices. The review was performed to determine whether reported information provided an assessment of the health of the Corrective Action Program, and if the information compared the program performance against the program metrics. The inspectors determined that the trends showed that CAQs were being identified, and were being evaluated and dispositioned in a timely manner. No excessive backlogs or adverse trends were depicted.
- (5) Corrective Action Program Effectiveness The inspectors did observe where some PERs were lacking details which required additional questioning by the inspectors to fully understand how the PERs were dispositioned. The inspectors determined that the applicant has maintained implementation of the CAP at an effective level since the last NRC Problem Identification and Resolution inspection (April 2014).
- (6) Corrective Action Program Transition Plans Based on interviews and procedure reviews, the inspectors determined the transition of the Unit 2 CAP to the NPG CAP and associated closure activities are expected to start when hot functional testing is finished and will be completed before Unit 2 fuel load. In preparation for the transition, the licensee plans to evaluate all open Unit 2 CAP items for closure or initiation of a new item within the NPG CAP. This evaluation will include all open SRs and PERs, Watts Bar Integrated Task and Equipment List (WITEL) open items, and corrective work processes other than PERs for some non-significant CAQs.
These processes would include WOs, FCRs, QC rejects, and TDNs. The applicant stated as Unit 2 testing activities increase, there will be a greater potential for activities to impact both units. If needed, a joint Corrective Action Review Board (CARB)/CCMRC may be established.
c. Conclusions
As documented above, the inspectors determined that implementation of the CAP for the Watts Bar Unit 2 construction completion project was generally adequate. The threshold for initiating PERs was appropriate, PERs were categorized in accordance with their significance, and problem evaluations were effective in identifying appropriate corrective actions.
In regards to maintaining a Safety Conscious Work Environment, the inspectors determined that TVA and Bechtel had established an acceptable program and environment for allowing employees to identify quality or safety-related concerns.
IV. OTHER ACTIVITES OA.1.1 Status of PERs Issued in Response to Previous NRC Unresolved Items and Violations
a. Inspection Scope
The inspectors evaluated corrective action PERs issued in response to previously identified NRC unresolved items and violations to determine whether the adverse condition identified by the inspectors had been addressed, evaluated, and dispositioned commensurate with their safety significance. Responses to the following regulatory issues were reviewed:
Unresolved Issue (URI) 87-19-06, Review of Cable Separation of Non-Safety Related Cables in Close Proximity to Safety Related Cables in Electrical Panels.
Non Cited Violation (NCV) 2014605-01, Failure to Accomplish Installation in Accordance with Instructions, Procedures, or Drawings.
NCV 2014608-02, Inadequate Storage of Safety-Related Equipment.
NCV 2014608-03, Failure to Prescribe Accurate Instructions in WO 115834758.
In each case, the inspectors determined the PERs for the NRC issues had been closed and archived; however, corrective actions which are contained in WOs have not been implemented yet. The inspectors assessed whether the applicant had followed their CAP procedures for closing out PERs when the corrective action has not been completed.
b. Observations and Findings
No findings of significance were identified
c. Conclusions
Based on the regulatory issues reviewed above, the inspectors concluded that the proposed corrective actions were adequate to address the identified problems. The CAP process was followed for closing PERs with the corrective actions not yet performed.
V. Management Meetings X.1
Exit Meeting Summary
On April 10, 2015, the inspectors presented the inspection results to Mr. Zeringue and other members of his staff. Proprietary information reviewed during the inspection was returned and no proprietary information was included in this inspection report.
SUPPLEMENTAL INFORMATION
Partial List of Persons Contacted
Applicant personnel
- D. Charlton, Licensing, TVA, Unit 2
- B. Heinmiller, CAP Manager, Bechtel
- Y. Hink, Employee Concerns, Bechtel
- J. Martin, Quality Assurance Manager, Bechtel
- I. Zeringue, Engineering and Construction General Manager, TVA, Unit 2
- E. Heinrich, Project Control Specialist, TVA
- E. Hicks, Preop / Startup, Bechtel
- D. Morgan, Field Engineering, Bechtel
- A. Love, Mechanical Engineering, Bechtel
- T. Metzler, Licensing, TVA Unit 2
- R. Phillips, Metallurgical Engineer, Bechtel
- H. Schmidt, Preop/Startup, Bechtel
Inspection Procedure Used
IP 35007 Quality Assurance Program Implementation during Construction
List of Items Opened, Closed, and Discussed
Opened and Closed
None
Discussed
None
List of Documents Reviewed
Calculations
Model 11, Fixed Free evenly distributed load Calculation, 6/15/1986
N3-03-18A, Summary of Piping Analysis Problem No. N3-03-18A, Rev. 5
WCG1118, SCV Penetration Nozzle and Shell Evaluation Penetration X-12D, Rev 6
MDQ00003020010067, Minimum ESF Cooler ERCW Flow Rates vs Entering ERCS
Temperatures During LOCA Conditions, Rev. 2
Drawings
2-003-47W803-3-3-B2, Hydro Test Package Test Boundary Map, Rev. 0
2-001-47W801-1-2-B1, Hydro Test Package Test Boundary Map, Rev. 2
Field Change Request
63603, X-8A: Change the acceptance criteria to accurately reflect field conditions, 5/13/14
63815, Remove ASME Section III designation from the weld symbol, 6/24/14
63897, Request civil engineering approval to allow for cable installation, 7/17/14
249, Delete I&C support 2-47A600-1734-5, 10/6/14
252, Request engineering approval to remove factory installed motor termination box, 10/6/14
64344, Add a dummy cable to conduit 2VC9554A, 10/23/14
64365, Add two needed alarm cables, 10/28/14
Over/Short/Damaged/and Discrepant
2792, Item did not come back from TVA central lab with EMI/RFI test report, 3/12/14
2793, T5050 Traceable to Certs, 3/12/14
63146, Missile barrier enclosure physical damage, 3/19/14
63690, Missile barrier enclosure physical damage, 3/31/14
63387, Impeller and impeller key documentation, 3/24/14
63452, Heat number discrepancy, 3/25/14
63537, Material does not match requirements, 3/27/14
64101, Material markings could not be located, 4/8/14
239, Material markings could not be located, 4/11/14
Problem Evaluation Reports
803682 ASME III Hardware Non-conformance Valves welded without verification of Open
Position
838631 Potential Damaged Rebar and Tube Bending Tool Causing Damage to 3/4 SS Tubing,
5/14/2014
857198 Error in DCN 60684, dated 3/10/2014
857212 (NRC Identified) Auxiliary Feedwater Pumps Shimming Techniques,
dated 3/10/2014
865656 WBN-2-RTV-063-0360A-S ASME Hardware Non-Conformance
857667 ASME Sec III Components Assembly Quality Issues with OEM Flowserve,
03/11/2014
861465 Fukushima Seismic 2.1 - WBN U2, 03/20/2014
2705 2-PT-68-0063 & 2-PT-68-0070 supplied by Westinghouse, 03/24/2014
869834 (NRC Identified) Potential Non-Conformance identified in Non-Contact
Reinforcement Lap Splice in FESB wall, dated 4/14/2014
870437 ASME WO 110837075 Valves welded in incorrect position 2-DRV-003-0591 and
0592
2920 Damage to rigid conduit 2M3076
873413 (NRC Identified) Existing Conduit Has a Loose Flex on the FROM End
874803 Missing documentation for previous Unit 2 containment SIT overpressure test
875430 ASME Hardware Non-Conformance WBN003, Valve WBN-2-DRV-003-0895-B
875442 ASME WO113764835, System 003 instrument tubing bend ovality non conformance
876349 Procedure 25402-000-GPP-000-N1206 Non-Conformance
881252 Warehouse Temperature Loggers Not Calibrated To Correct Range, dated 5/6/2014
881750 Flowserve NDE procedure revision did not meet ASME III 1971-1973 addenda
886208 ASME III WBN003 Corrosion Identified in PER 241062
887940 NRC walk down for separation criteria to be addressed, dated 5/27/2014
890353 (NRC Identified) Conduit separation between Train A conduit and Train S
components
893685 U2 Fukushima error, dated 6/3/2014
897419 Eagle 21 Hardware Failure during Loop Calibrations, dated 6/11/2014
900136 MOV Calculations did not Evaluate Worst Case Operating Conditions,
dated 6/18/2014
908502 Issues with FSAR Change Packages, 07/10/2014
908531 Late M&TE Items for Bechtel, dated 7/10/2014
915149 NRC Identified Incorrect Tolerances in 2-SI-3-68, 07/29/2014
915562 NRC's Concern that Actions in a Confirmatory Order Not Completed, 07/30/2014
911198 NRC Identified) Splice Plate Bolt not Flush with Cable Tray Surface, dated
7/17/2014
911200 Trend in M&TE Issues for Startup, dated 7/17/2014
2633 Near Miss During Coredrilling Operations URS Worker struck conduit, 7/29/2014
915149 NRC Identified) Incorrect Tolerances in 2-SI-3-68, dated 8/5/2014
915562 NRC Concern that Actions in a Confirmatory Order May Not Have Been Completed,
dated 8/5/2014
20312 (NRC Identified) Improper Storage of Rosemount Transmitter, dated 8/11/2014
20788 Flex Conduit non-conformance, loose flex
21471 Discrepancies Identified in How Records are Indexed in EDMS, 09/25/2014
21957 U1 identified - Orifice plates were designed for schedule 40 pipe and used in
standard weight pipe, 8/14/14
23683 ASME Related: Minor Deficiencies identified in NC-PP-22, 08/19/2014
24088 NRC identified inconsistencies with Developmental Tech Specs, 08/20/2014
28895 NRC Rad Controls Operational Readiness Inspection, 09/02/2014
28941 Ground found on Hand Switch 2-HS-61-192B, dated 9/2/2014
931429 NRC identified) Weakness in Level of Detail For Review of Surveillance Instructions,
dated 9/23/2014
933573 DCN 53413, Failure to update Fire Protection Report for Construction Modifications
936244 NRC identified loose bolting, dated 9/30/2014
937748 Revision Bars Missing from Part II of Fire Protection Report, 09/25/2014
945339 Safety Injection Pump 2A was Found in Degraded Condition When Inspected at
Flowserve, dated 10/14/2014
954065 (NRC Identified) Potential Bypasses to the Data Diode, dated 11/5/2014
955650 NRC Identified During the Unit Triennial Fire Protection Inspection, 11/10/2014
958843 Reroute of conduits 2VC6051A and 2VC9611A
957985 2-PMCL-30-177 and 178 low air flow Containment Spray Room Coolers
961031 Construction WOs and processes are inadequate when performing work on turned
over systems/components, 11/25/14
961436 Near Miss, WBN UW Hotwell Pump C Expansion Bellows Disoriented, 12/02/2014
961446 NRC Identified) PER revision not addressing NUREG-0612 Requirements, dated
2/3/2014
2840 2-FCV-001-75 Broke While it Was Being Manually Operated, 12/02/2014
965013 ASME Related; Foreign Material Exclusion not being followed on Valve 2-LCV-003-
0171
968403 ASME Related: Hardware Non-Conformance Damage found to 757 Airlock door
967479 Damaged Conduit Identified Above Vital Battery IV Board Room, 12/15/2014
2069 Gaps Identified in WBN2 Confirmatory Order Commitments, 12/30/2014
986625 120v Power Found during Live-Dead-Live Pre-work Check, 02/09/2015
988081 System 003B documentation issues with copper plates added to 2-MTR-003-118-A
and 2-MTR-003-128-B
2690 ASME Related: Historical concern related to WO 116575245
Procedures and Programs
NPG-SPP-09.3.1 Section 3.4.19, Guidelines for Preparation of Design Inputs and Change
Impact Screen, Rev. 4
NPG-SPP-09.3, Section 3.2.4 and Attachment 3, Plant Modifications and Engineering Change
Control, Rev. 18
NPG-SPP-22.300, Corrective Action Program, NPG Standard Programs and Processes, Rev
.0002, 12/17/2014
NPG-SPP-22.500, Operating Experience Program, NPG Standard Programs and Processes,
Rev .0001, 2/09/2015
NC PP-8, Watts Bar Nuclear Plant Unit 2, Operating Experience/Construction Experience Plan,
Rev 2, 1/16/13
ECP-1, Conduct of Employee Concerns Program Implementation, NPG Employee Concerns
Program, Rev 6, 5/5/2014
ECP-1, Desktop Instruction 1, Employee Concerns Program, Rev 0, 1/19/2010
NPG-SPP-01.7.1, Employee Concerns Program, NPG Standard Programs and Processes,
Rev.0000, 12/3/2012
No.25402-MGT-004, Incident Investigation and Root Cause Analysis, Watts Bar Nuclear Plant
Unit 2 Construction Completion Project, Rev 4. 2/5/2013
NC-PP-3, Watts Bar Nuclear Plant Unit 2, Corrective Action Program, Rev. 16, 3/27/2014
Quality Control Rejects
25065, Cable installed without QC witness point verifications, 1/28/15
2781, Cable pulled through three 45 degree flex conduit fittings, 3/4/15
29546, Design document discrepancy on cable color codes, 2/13/15
717399, Number of conduits attached to junction box exceeds design requirements, 12/18/14
24288, Less than one inch separation exists between conduits of different trains, 1/22/15
26852, Less than one inch separation exists between conduits of different trains, 2/4/15
714322, Ovality greater than 8%, 12/8/14
716395, Snubber is damaged and cotter pin is not bent, 12/13/14
716769, Plate washer missing and dimensions are out of tolerance, 12/16/14
717086, Arc strike on pipe next to support, 12/17/14
20604, Dimension out of tolerance and weld not completed as shown by weld symbol, 1/7/15
2503, Arc strikes on item 3, 1/18/15
Service Request
859082, Unit 2 RHR Flush Generating Excessive Liquid Radioactive Waste, 03/14/2014
859101, Hardware Non-Conformance Relating to the Pin for Paul Monroe Snubbers, 03/14/204
858516, Conduit separation, 3/13/14
858675, ASME Section III & XI - U2 Relief valve set point value procedure difference, 3/13/14
2493, Proper documentation for Grounding Instrument Panels, 3/24/14
2741, EA170 type Namco Limit Switches installed Inside Containment, 3/24/14
864646, Disposition of two PER's cannot be met. Void SR-See details, 3/28/14
865584, PER 463361 QA Corrective Action Effectiveness Evaluation, 04/01/2014
866347, Safety personnel performing walkdown identified broken existing conduit, 4/1/14
869297, Disconnected / damaged mid-run flex conduit with an installed cable found, 4/8/14
869821, Previously rotated transmitter was rotated back to its original position, 4/9/14
903768, Rigid Support 2-63-345 is no longer dead loaded, 6/27/14
907118, For Cause Testing, 07/07/2014
907530, Conflict between drawings 1-47W866-1A and 2-47W866-1, 07/08/2014
910180, PM: LPM0152 drained approximately 5 to 7 gal. of water from the cooler, 7/15/14
913220, Justification to Close PER Related WO 113578803, 07/24/2014
917552, Follow up to SR 868790: U2 Upper Containment to Lower Containment Electrical
penetration, 8/5/14
930282, Motor Driven Aux. Feedwater Pump 2A-A and 2B-B - Misalignment, 09/05/2014
Test Deficiencies and Notices
14-0426, Flow velocity < 7ft./sec. 6.3 downstream of 2-ISV-62-940, through welded flow orifice,
5/18/14
14-0429, Insufficient flow velocity (<7ft./sec.) section 6.9B, 5/18/14
14-0435, The 2A auxiliary oil pump continued to run during the operation of the 2A CCP,
5/26/14
14-0436, The 2B auxiliary oil pump continued to run during the operation of the 2B CCP,
5/26/14
14-0819, M&TE instruments found out of tolerance in post-test calibration, 9/10/14
14-0965, Annunciator did not clear when expected, 10/25/14
14-1102, The ability to flow water through two valves was previously demonstrated, 11/26/14
14-1127, 2-TE-68-0330 is a two wire RT
- D. Wires terminated improperly, 12/7/14
Work Orders
09-951583, Refurbishment MD AFW Pump 2B-B, WBN-2-LCV-003-0171-B
115748769, Steam Generator Hydrostatic Test 2-001-47W801-1-1-B1, 2/24/2015
11565880, Replace Valve WBN-2-RTV-063-0360A-S, 7/7/2014
114940059, ASME III Pressure Test 2-001-47W801-1-2-B4, 1/6/2015
115339416, Terminate 2PP662B for 2-MTR-3-128-B, 1/23/2015
116491216, Conduit 2VC9611A DCN 599164 System 2-FCV-70-156-A, 4/9/2015
116057399, 2-JB-292-8180-E Tighten Loose Connectors, 4/10/2015
857667, ASME Sec III Components Assembly Quality Issues with OEM Flowserve, 03/11/2014
861465, Fukushima Seismic 2.1 - WBN U2, 03/20/2014
2705, 2-PT-68-0063 & 2-PT-68-0070 supplied by Westinghouse, 03/24/2014
869834, Non-contact Reinforcement Lap Splice Identified in FESB Wall, 04/09/2014
875857, Historical: Missing Seal between Upper and Lower Compartment, 04/23/2014
881733, PER documents U2 actions to implement U2 Cyber Security Program, 05/07/2014
908502, Issues with FSAR Change Packages, 07/10/2014
915562, NRC's Concern that Actions in a Confirmatory Order Not Completed, 07/30/2014
20312, NRC inspection at WH, 08/11/2014
21471, Discrepancies Identified in How Records are Indexed in EDMS, 09/25/2014
23683, ASME Related: Minor Deficiencies identified in NC-PP-22, 08/19/2014
24088, NRC identified inconsistencies with Developmental Tech Specs, 08/20/2014
28895, NRC Rad Controls Operational Readiness Inspection, 09/02/2014
931429, NRC identified level of detail used in review of Sis, 09/09/2014
937748, Revision Bars Missing from Part II of Fire Protection Report, 09/25/2014
955650, NRC Identified During the Unit Triennial Fire Protection Inspection, 11/10/2014
2840, 2-FCV-001-75 Broke While it Was Being Manually Operated, 12/02/2014
967479, Damaged Conduit Identified Above Vital Battery IV Board Room, 12/15/2014
2069, Gaps Identified in WBN2 Confirmatory Order Commitments, 12/30/2014
986625, 120v Power Found during Live-Dead-Live Pre-work Check, 02/09/2015
Miscellaneous
DCN 53413-A, System 70 Physical Work to Support Two Unit Operation, 04/01/2015
UT-742, Nondestructive Examination Report for piping associated with 2-CKV-003-0508 and 2-
CKV-003-0509
NC PP-36, Watts Bar Unit 2 Procedure Review and Approval, Rev. 6
MMDP-1, Maintenance Management System, Rev. 30
25403-000-GPP-0000-N1206, Work Order Processing, Rev. 19
NPG-SPP-01.2.1, Interim Administration of Site Technical Procedures for Watts Bar Units 1 and
2, Rev. 0
NPG-SPP-012, Administration of Site Technical Procedures, Rev. 11
NC-PP-32, Dev and Issue of Operating and Technical Instructions, Rev. 6
NC-WB-14-004
List of Acronyms
CAP Corrective Action Program
CCMRC Construction Completion Management Review Committee
CFR Code of Federal Regulations
EOC Extent of Condition
I&OE Industry and Operating Experience
IP Inspection Procedure (NRC)
NCV Non-Cited Violation
NRC Nuclear Regulatory Commission
OSDD Over, Short, Damaged, and Discrepant
PARS Publicly Available Records
PER Problem Evaluation Report
PI&R Problem Identification and Resolution
PRC Project Review Committee
QC Quality Control
RFI Request for Information
SCWE Safety Conscious Work Environment
SR Service Request
TDN Test Deficiency Notice
TVA Tennessee Valley Authority
URI Unresolved Item
WBN Watts Bar Nuclear Plant