IR 05000382/1989006

From kanterella
Jump to navigation Jump to search
Ack Receipt of 890706 Supplemental Response Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-382/89-06
ML20247R455
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/28/1989
From: Milhoan J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Dewease J
LOUISIANA POWER & LIGHT CO.
References
NUDOCS 8908080008
Download: ML20247R455 (2)


Text

_-__-_-___ _ _-_

_

.

.

' '

Jul. 28 519

'

.

In Reply Refer To:

Docket: 50-382/89-06 Louisiana Power & Light Company ATTN: J. G. Dewease, Senior Vice President Nuclear Operations 317 Baronne Street New Orleans, Louisiana 70160 Gentlemen:

Thank you for your letter of July 6,1989, in response to our request of June 6,1989, for a supplemental response to our letter and Notice of Violation, dated March 28, 1989. We have reviewed your reply and find it responsive to the concerns raised in our Notice of Violation. We will review the implementation of your corrective actions during a future inspection to determine that full compliance has been achieved and will be maintaine

Sincerely, Original Signsd By:

James L. Milhcan James L. Milhoan, Director Division of Reactor Projects cc:

Louisiana Power & Light Company ATTN: R. P. Barkhurst, Vice President Nuclear Operations P.O. Box B K111ona, Louisiana 70066 Louisiana Power & Light Company ATTN: J. McGaha, Jr. , Plant Manager

"

P.0, box B Killona, Louisiana 70066

'

dDO t RIV:DRP/A ATHowell;df C:DRP/A DDChamberlain D DRP JLMil an r\\

7/k/89 i 7/24/89 gU 74 89 p;8*R888! 818?$y G

_ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

p R

~ j

.

. .,

,

..

,

' Louisiana Power & Light Company -2-Louisiana Power & Light Company-ATTN: R. F. Burski, Manager, Nuclear Safety S Regulatory Affairs '

317 Baronne Street P.O. Box 60340-New Orleans, Louisiana 7016 Louisiana Power & Light Company ATTN: L. W. Laughlin, Site Licensing Support ~ Supervisor P.O. Box B Killona Louisiana 70066 Louisiana-Power & Light Company ATTN: G. M. Davis, Manager, Events l Analysis Reporting & Response l P.O. Box B i Killona, Louisiana 70066 Middle South Services ATTN: Mr. R. T. Lally I P.O. Box 61000 .j New Orleans, Louisiana 70161

"

Louisiana Radiation Control Program Director bcc to DMB (IE01) w/ copy of licensee lt bcc distrib. by RIV w/ copy of licensee ltr.:

RRI R. D. Martin, RA SectionChief(DRP/A) DRP RPB-DRSS MIS System Project Engineer (DRP/A) RSTS Operator RIV File DRS D. Wigginton, NRR Project Manager (MS: 13-D-18) Lisa Shea, RM/ALF l

_ _ - _ _ _ - _ _ - _ - _ - _ _ - _ - _ _ _ _ _ _ _ _ _ _ - - _ _

- _- _ _


.. . _ _ _ _ , - _ _ _ _ - _ _ _ _ _ _ _ _

,

is

'

, .

s I

  • P. O. BOX 60340 LO UIBi ANA / 317NEW POWER & LIGHT BARONNESTREET ORLEANS, LOUISlANA 70160 * (504) 595 3100 UYOikIsvsNU *

W3P89 .1075 A4.05 l

QA July 6, 1989 hMb

e

--.

,

U.S. Nuclear Regulatory Commission ATIN: Document Control Desk ( M ,7 @ {

!

Wastington, D.C. 20555 lg, a

__ Su"> ject: Waterford 3 SES Docket No. 50-382 License No. NPF-38 Violation 8906-01, Failure to Follow Procedures . . .

References: LP&L Letter No. W3P89-3006 dated 04/27/89 from R.F. Burski to U.S. Nuclear Regulatory Commission NRC Letter dated 06/06/89 from J.L. Milhoan to l J.G. Dewease Gentlemen:

Louisiana Power & Light hereby submits the following information on the  !

subject violation as a supplement to the response that was provided in the j Reference 1 letter. This information, which is contained in Attachment 1,

'

addresses your request expreesed in the Reference 2 letter for LP&L to  !

provide a description of the actions that will be taken to preclude further violations in the area of safety-related fastener torque requirement If you have any questions concerning this response, please contact T.J. Gaudet at (504) 464-332 ,

ery truly yours, s

jn s ._ %

. Burski nsger Nuclear Safety & Regulatory Affaf*p RFB/TJG/ssf Attachnent cc: Messrs. R.D. Martin (NRC Region IV), F.J. Hebdon (NRC-NRR),

D.L. Wf gginton (NRC-NRR), E.L.' Blake, W.M. Stevenson NRC Resident Inspectors Office

"AN EQUAL OPPORTUNITY EMPLOYER"

~E-Wgg} fff-7/Zg/6(p 3 - - -


---_--

'y '

Attcchm2nt to j i W3P89-3075 Pcga 1 of 2

, ,

' '

,

.

ATTACHKENT 1 l

Supplemental Response to Violation 8906-01, Example 1 k Although LP&L believes that the torquing program at Waterford 3 is adequate, there is potential for improvement to preclude the recurrence of noncompliance related to torque requirements. After receiving Violation 8906-01 (Example 1), actions to prevent recurrence were initiated, but a discussion of these actions was not provided in LP&L's response to the violation. First, a review by maintenance planners of repetitive tasks, e.g., alignment checks, was initiated to ensure that specific torque values from the Vendor Manuals are included in applicable work packages. This ongoing project is being handled on a case-by-case basis as the tasks bacome due. In addition, departmental meetings were used to heighten personnel awareness of the 8906-01 torquing issu Additional actions will be taken to emphasize management's desire to have an effective, comprehensive torquing progra To elevate the awareness of the torquing noncompliance and bring such ,.

conditions to the attention of the proper personnel lessons learned training will be given to maintenance personnel, including the first line supervisory level, Also, during periodic maintenance " shop" and first line supervisors' meetings, the issue of torquing compliance will be re-emphasized and f eedback on torquing concerns will be solicite t l

The upper tier torquing procedure, MM-6-011. " General Torquing and Detensioning," will be revised and human factor engineered to increase user l awareness and understandability and to reduce the chances for personnel erro Upon completion of the rewrite, training on the procedure will be conducted with cognizant maintenance personne Finally, a review of applicable maintenance procedures will be initiated to I alleviate any inconsistencies or hard spots in the area of fastener torquin Based on the above actions, which are scheduled for completion by December 29, 1989, LP&L is confident that recurring noncompliance in the control of safety-related fastener torque requirements will be prevented in the futur As stated in your letter, LP&L's original response to Violation 8906-01, Example 1, neglected to address the failure to torque the coupling bolts in accordance with the vendor Manual requirements. Failure to reply to this ;

part of the violation resulted from confusion in having to address two separate torquing issues that occurred during the performance of Work Authorization 01028798 and the use of Vendor Instruction Manual 457000254. The following information is being provided to supplement LP&L's original response to Violation 8906-01, Example _ _ - _ - _ - _ _ _ _ _ _ - _ _ _ _ _ _ _ . _ _ _ _ _

AttOchc nt to

,g W3P89-3075 l

.

Pcg2 2 of 2

,, ,

The. alignment check that was performed on ACCW Pump IB under Work Authorization 01028798 took place at approximately 2:00 a.m. on 2/8/89. At the point in which the coupling bolts had to be tightened, the responsible mechanics went to the applicable Vendor Instruction Manual (No. 457000254,

"B&W Pumps") to obtain the instructions for coupling assembly. When the mechanics determined that additional instructions for Koppers fast couplings were needed but not included in the Manual, they contacted their supervisor at home to request his assistance. The supervisor, based on his J knowledge of Koppers couplings, informed the mechanics that no torquing was required and instructed them to install the coupling using toolbox knowledge. Subsequently, it was learned that a later revision to the Koppers fast coupling instruction sheet did in fact contain requirements for torquing the coupling bolts. A Quality Notice (QN QA-89-078) was then generated on 3/3/89 to initiate corrective action for this condition. In response to the QN, it was determined that the lack of precise torquing of the coupling bolts had no detrimental effect on the operation of the coupling. The purpose for bolt torquing is strictly to avoid overstressing the bolt as was confirmed by the vendo .

Koppers Installation and Alignment Instuction Sheet 1900-01, which includes l the torquing requirement (Note: The earlier revision, Sheet 1900, did not I include the torquing requirement), has since been incorporated into Vendor'~ j Instruction Manual 457000254 Incorporation of this document into other j applicable Manuals is in progres l

l

_ - _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ - _ _ _ _ _ . _ _ . __ - _ _ _ _ _ _ _ _ _ . _ -