IR 05000373/1987010

From kanterella
Jump to navigation Jump to search
Safety Insp Repts 50-373/87-10 & 50-374/87-10 on 870311-12. No Violations or Deviations Noted.Major Areas Inspected: Previous Insp Findings & Followup on Licensee Identified Anomaly W/Standby Liquid Control Sys Cable Jacket
ML20204F865
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 03/20/1987
From: Falevits Z, Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20204F805 List:
References
50-373-87-10, 50-374-87-10, NUDOCS 8703260289
Download: ML20204F865 (7)


Text

o

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-373/87010(DRS);50-374/87010(DRS)

Docket Nos. 50-373; 50-374 Licenses No. NPF-11; NPF-18 Licensee: Commonwealth Edison Company Post Office Box 767 Chicago, IL 60690 Facility Name: LaSalle County Station, Units 1 and 2 Inspection At: LaSalle Site, Marseilles, Illinois Inspection Conducted: Ma ch 11-12, 1987 4.

Inspector:

Z. Falevits 3[20/87 Date

'h'h 3!2o)87 Approved By:

R. N. Gardner, Chief

Plant Systems Section Date Inspec_ tion Summary Inspection on_ March 11-12,1987_ JR_eports No. 50-373/87010j'0R_S)_; 50_ _37_4/87010j0_RS)1 Areas Inspected: Routine, announced saf'Ety lnspection lif llcensee action on

__

_

_

previous inspection findings; followup on licensee identified ancmaly with Standby Liquid Control System cable jacket; drywell-temperature program.

(92701, 92702,62705,42700)

Results: Of the three areas inspected, no violations or deviations were identified.

8703260289 870320 PDR ADOCK 05000373 G

PDR

'

.

.

DETAILS 1.

lersonsContacted

~

. Comonwealth Edison _ CompandCEC_o);

  • R. Bishop,. Station Services Superintendent

'*K. L. Graesser. Division Vice President, NSD-

  • R. W. Stobert, Station QA Superintendent K. C. Wittenburg, Technical Staff Engineer D. Smythe, Electrical Engineer, EM The inspector also contacted and interviewed other licensee personnel

.during this inspection.

  • Denotes those personnel attending the March 12, 1987, exit interview.

2.

Licensee A_ction on_Pr_evious Inspection Findings a.

(Closed) Violation (373/85026-04(DRS); 374/85027-04(DRS)): This violation concerned the licensee's failure to initiate prompt corrective action to review and evaluate recalculated containment monitoring temperature setpoints for alarm points recorded on recorders ITR-CM037, ITR-CM038, 2TR-CM037, and 2TR-CM038.

During and subsequent to this inspection, additional temperature readings were taken in the Units 1 and.2 drywells. Based on these readings, S&L recomended that the Units 1 and 2 CM recorder setpoints remain at 140*F. This recomendation was addressed in S&L's October 11, 1985, letter to SNED.

In a letter from SNED to LaSalle Station, dated November 6,1985, SNED also recomended that the setpoints remain at 140*F. Additionally, SNED requested that AIR's and modifications on this topic be closed. The inspectoc determined that the Units 1 and 2 modifications had been cancelled on November 11, 1985, and. AIR's for both units had been cancelled on December 5,1985.

b.

-(Closed) Deviation (373/85026-05(DRS)): Deviations were identified from comitments made by the licensee regarding temperature monitoring activities associated with safety-related equipinent located in the containment drywell.

During this inspection, the inspector determined that corrective action taken by the licensee included issuance and implementation of drywell temperature monitoring Procedure LTP-300-17.

This procedure is used to monitor and record temperature data from all pennanent and temporary sensors on a weekly basis.

In addition, multipoint recorders had been installed in Units 1 and 2 Reactor Buildings to allow for continuous monitoring of all drywell temporary temperature sensors.

.

-,

c.

(Closed) Violation (374/85027-02(DRS)): On August 12 and 28, 1985, operator yellow caution tags, attached in September 1984, to control room containment monitoring Recorders 2TR-CM037 and 2TR-CM038, indicated that the recorder alarms were set at 150 F.

The inspector, accompanied by a CECO I&C supervisor, conducted a visual inspection of the recorders setpoints. During the visual inspection, the CECO supervisor stated that the setpoints were set at 140 F and 141 F.

During this inspection, the inspector determined that the licensee had conducted a thorough review of calibration records pertaining to the above recorders. The licensee's review indicated that the initial calibrations of the high temperature alarms were completed on January 31, 1982, with the recorder alarm points set at 140 F and 141*F.

In September 1984, the alarm setpoints were raised to 150'F, in accordance with onsite Review 84-22, under Nuclear Work Requests L35938 and L35939. This was done in order to allow the alarm to annunciate only when temperatures higher than normal were encountered

't. the vicinity of the sensors. The licensee stated that the CECO I&C supervisor assisting the inspector in the verification of the recorders setpoints was apparently in error when he stated, in 1985, that the then current setpoints were 140 F and 141 F.

d.

(Closed) Violation (373/85034-02(DRS)): This violation concerned licensee failure to identify the Safety Relief Valve (SRV) adjacent to SRV 1821-F013J and to provide permanent stamping or identification tags on the remaining Unit 1 SRV's.

Subsequently, the inspector was informed by the licensee that each SRV had a manufacturer's serial number and that a record of the serial number and setpoint of each_SRV was kept by location. This violation was retracted by Region III.

(Closed)OpenItem(373/85034-04(DRS)): During a previous e.

inspection in the Unit 1 drywell, the inspector noted that Safety-Related Cables INB081 and INB082 were tightly pulled inside Junction Box 1dB455C; this configuration appeared to violate cable bend radius requirements.

Subsequently, the licensee inspected the above cables and determined that the bend radiuses had been violated; that a crimp existed on both outer jackets at Cable Pan Node 15728; and that cable repairs were necessary.

Work Request L57145 dated April 11, 1986, was issued to replace both cables between Junction Box IJB139J and Penetration E-7 (173' long);

this relieved the tightness in IJB455C and increased the bend radius.

The new section of the cables was spliced to the existing cables in Junction Box idB139C using appropriate Raychem heat shrink splices.

QC hold and witness points were noted in the traveler for the splice process. At the completion of the cable repair activities, the licensee conducted a main steam safety relief valve manual cycling test under Procedure LOS-MS-R2 to assure that circuits affected by the repaired cables functioned as designed. No anomalies were noted.

The cable deficiencies appeared to represent an isolated occurence.

y;,

,

.-

,

y

$

f.--

~(Closed) Violation'(373/85034-05(DRS);374/85035-04(DRS)):.As a result of the drywell inspection conducted in Units I and 2, the inspectors identified conditions adverse to quality such as damageds conduits, damaged and loose mirror insulation panels (a condition that co'uld cause lccalized hot spots), missing covers on' pull boxes, opening in SRV cable ripper tubing, metallic' grinding products on limitorque. valve stem screw, etc.

Subsequently, the licensee initiated extensive correction actions to correct the identified deficiencies. -Junction box covers were reinstalled, broken flexible conduits were'repiired and the insulation panels were inspected by the _ licensee;and repaired. All the limitorque ' valves were inspected as part of another inspection

-

effort. All valves were cleaned and covers reinstalled. The licensee indicated that in addition to reviewing Work Request Procedure' LAP-1300-1 to determine if post-completion drywell inspection' guidance was adequate, training would be provided to ensure:that the ge'neral area in which work was performed would be'

included in the inspections.

Finally, all station personnel would be-reminded that any abnormal condition.found in the plant for any reason -

,l requires that a WorO Request be initiated.

g.

,(Closed) Violation (373/85034-06(DRS);- 374/85035-04(DRS)):

Comonwealth Edison Standard C-2325, Note.'12 stated that not more_ than two wires shall be connected to any one stud. The inspector noted that limitorque operators on various valves contained three conductors connected to one stud.

~

The licensee responded that the basis of this requirement was the physical ' limitations on electrical terminal blocks 'and that due to the limited space available on the electrical terminal blocks, the stacking of more than two lugs on one screw could result in insufficient electrical connection. The licensee further stated that this situation,did not apply' to limitorque valve operators since the connection'in the-limitorque operators allows for adequate contact of all three conductors and the barrel' lugs were not stacked-in.such a way as,to prohibit proper electrical connection.

~

s

=

Y.

h.

(Closed)UnresolvedItem(373/85034-07(DRS);374/85035-06(DRS)):

During a previous / inspection, the inspectors identified MOV Limitorque limit switches' which were set at higher than the vendor nameplate recomended maximum and higher than.specified on -the' plant

" Motor Operated Data" (MOD) list. The' inspectors determined that there was inconsistency among licensee personnel as to where and how the switches were set and the relationship between the vendors nameplate recomendation and the M00.

Subsequently, the licensee completely revised Procedure LEP-GM-102, titled "Limitorque Valve Post Maintenance Verification." The inspector reviewed Revision 9 of Procedure LEP-GM-102, dated December 10, 1986. The procedure appeared to be adequate; it contained detailed specific actions to be taken when, checking

~

.

4

-. --

--

r

~

.

-.

or setting M0V switches.

In addition, the licensee conducted

-

a limitorque M0V inspection which included verification of torque switch settings; Work Requests L52947 and L52489 were used to conduct the limitorque inspections and to reset the switches found to be out of specified limits.

i.

(Close'd) Open Item (374/85035-01(DRS)): This item concerned the environmental' qualification and the physical condition of conductors within cables routed from the Unit 2 Safety Relief Valves to Drywell Junction Box 1JB115C.

During this inspection, the inspector determined that the licensee had written Work Request L59697 to conduct a visual inspection of these conductors and to make necessary repairs.

Although no degraded conductors were noted during the licensee's visual inspection, all 108 safety-related terminations from the E

SRV's to the LVDT's had been reterminated with Raychem splices (WRL60230 through WRL60235). These reterminations were necessary due to the lack of EQ test data establishing the adequacy of the Okonite tape with the Kapton wire insulation'on the SRV and LVDT conductors.

J.

(Closed) Unresolved Item (373/85039-03(DRS); 374/85040-03(DRS)):

During a review of WRL52489, the inspector noted that several inspection checklists had been backdated to reflect' licensee corrective action taken to disposition discrepancies identified on previous inspections. These corrections had been signed by the maintenance foreman.

During this inspection, the inspector determined that the licensee concluded that the dates initiated on the WR were, unintentionally, in error; that all information contained therein, however, was true and accurate. Licensee management discussed this incident with the Electrical Maintenance Staff to preclude its recurrence. Discrepancy Report (DR) 01-85-448, dated December 12, 1985, was written to resolve all documentation wiring and operability discrepancies.

k.

(0 pen)UnresolvedItem(373/85039-04(DRS);374/85040-04(DRS)):

During a previous inspection, the inspector selected two valves that had been previously inspected by the licensee. RHR Containment Spray Outboard Valve 2E12-F016B was inspected and observed to contain a nicked and unidentifiable conductor between limit switch Points 4 and 8.

At the inspectors request, the valve was manually opened and closed. The inspectors noted that limit switch Rotors 2 and 4 changed positien ten hand wheel turns from valve fully closed position, Rotor No. I changed position eight hand wheel turns from the valve fully open position, and Rotor No. 3 changed position 12 turns from the fully open position. Under normal operation Rotors 1 and 3 change positions at the same time due to the rotor contacts which are interlocks in other circuits. Section F6 of LaSalle "Limitorque Valve Post Maintenance

$

p77 sv.

..:

Verification" Procedure LEP-GM-102, dated October 7,1985, required that for Size "0" valves and larger, the rotor be set at 20 valve

hand wheel turns. The licensee could not explain why the rotors changed positions at different intervals.

Subsequently, the -licensee determined that plant personnel made an -

errcr when they originally set the switches. The switches were subsequently reset to the correct values resolving the problem identified with valve 2E12-F016B; however, the licensee could not assure the inspector that all other safety-related valves in the plant'were set correctly. Pending further review of this issue by the licensee, this item remains open.

1.

(Closed) Unresolved Item (373/85040-06(DRS); 374/85041-06(DRS)):

This item concerned motor meggering tests performed by the licensee using an unapproved Operational Analysis Department (OAD) Station Procedure No. ECTP-1.

During this inspection, the inspector determined that on February 16, 1986, the ECTP 1 procedure was reviewed and approved "as is" by onsite review personnel using approved review Procedure LAP-820-9, Revision 0, and QAS 1-86-05.

3.

Followup on Licensee Identified Anomaly _}I_i_th__S_t_andby _Liqu_id_ C_o_ntrol Cable Jacket During maintenance activities conducted on Standby Liquid Control Squib valve 2C41-F0004B, the licensee had identified that the cable (No. 2SC023) feeding the Squib valve contained blisters on the outside surface of the cable jacket. The blisters appeared every 1"-2" throughout the length of the cable which is routed from the valve to the Cable Spreading Room (approximately 450' long). The cable is a Rockbestos, two ' pair, No.16, 600 volt cable, Type 88085, ID No. 02166. Review of Material and Equipment Receiving and Inspection Report, MRR No. 6790, dated July 20, 1979, indicated that 4426' of this type of cable was purchased for the LaSalle project.

'The inspector reviewed the Cable Reel Record for Reel No. 4266-02166-65 which indicated that the following cables had been used: 2HP225, 2FW266, 267, 268, 271, and 272, 2SC023, 2NB327, 2RH585, and 569. The inspector visually inspected a section of installed Cable 2RH585 located in the Reactor Building; no blisters were noted.

In addition, field inspection of cabling associated with Squib valve 2C41-F004A and the Unit 1 Squib valves did not reveal the same anomaly. The licensee informed the inspector that a section of Cable 25C023 was sent to the laboratory for analysis. Based on the results of the analysis, the licensee will determine the appropriate corrective actions to be taken.

Pending licensee corrective action and NRC review, this item is considered open (374/87010-01(DRS).

4.

Drywell Temperature Proir,am Data _ Rev_iew

_

The inspector interviewed the licensee's engineers assigned to monitor and implement the drywell temperature program to assure that the

l

,

_

.

.

remaining qualified life of the safety-related equipment located inside the drywell was not exceeded. The inspector examined drywell temperature data collected by the engineers on March 7, 1987, using checklist Attachment A of Procedure LTP-300-17, Revision 2.

The data is collected daily and sent to SNED for review and evaluation to determine the effect of a high temperature detected by Sensor ITE-UP211 located at MSIV D.

' The licensee determined the cause of the high temperature at MSIV D to be due to a valve packing leak.

In a letter to CECO dated January 8, 1987, Sargent & Lundy evaluated the daily temperatures collected by LaSalle Station for the ITE-VP211 sensor. This data was collected during the period of September 15, 1986, to December 31, 1986. The data indicated that the subject sensor had reached 226.6 F- (for four hours). This temperature exceeded the specified EQ Trigger setpoint (150 F), and the Alert setpoint (180 F). S&L calculations for the qualified life and remaining life demonstrated that the remaining life, as of January 1, 1987, for the MSIV D NAMC0 limit switch, at the present operating temperature of 176 F, is 1.02 years. Additional calculations of remaining life were given for the valve seal assembly and for solenoid parts. The licensee indicated that these parts will be replaced as safety components reach the end of their qualified life.

The NRC will continue to followup on the licensee's drywell temperature monitoring program during future inspections.

5.

Open Items Open items are matters which have been discussed with the licensee, which will be reviewed further by the inspector, and which involve some action on the part of the NRC or licensee or both. Open items disclosed during this inspection are discussed in Paragraph 3.

6.

Exit Interview The Region III inspector met with licensee representatives (denoted under Paragraph 1) at the conclusion of the inspection on March 12, 1987. The inspector summarized the purpose and findings of the inspection.

The licensee acknowledged this information. The inspector also discussed the likely informational content of the inspection report with regard to documents or processes reviewed by the inspector during the inspection.

The licensee did not identify any such documents / processes as proprietary.

7