IE Insp Rept 50-370/82-17 on 820706-09.No Noncompliance Noted.Major Areas Inspected:Preoperational Test Procedure Reviews & Preoperational Test Package Reviews
ML20062J033
Person / Time
Site: Mcguire
Issue date: 07/21/1982
From: Jape F, Andrea Johnson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20062J000 List:
References
50-370-82-17, NUDOCS 8208160244
Download: ML20062J033 (4)


Text

'

t@ RfCO UNITED STATES

f

[.

', o,,

NUCLEAR REGULATORY COMMISSION o

REGION ll

c 101 M ARIETTA STREET, N.W.

~f ATLANTA, GEORGI A 30303 o,s,

/

.....

Report No. 50-370/82-17 Licensee:

Duke Power Company 422 South Church Street Charlotte, NC 28242 Facility Name: McGuire Unit 2 Docket No. 50-370 License No. CPPR-84 Inspection at McGuire site near Charlotte, NC Inspector:

//#M 74 /- f L A. H. Johnsbn Date Signed

'

/#

7-7/-IL Approved by:~F. Japdf fectt'on Chief Date Signed Engineering Inspection Branch Division of Engineering and Technical Programs SUMMARY Inspection on July 6-9, 1982 l

Areas Inspected This routine, unannounced inspection involved 30 inspector-hours on site in the areas of preoperational test procedure reviews and preoperational test package reviews.

j Results Of the two areas inspected, no violations or deviations were identified.

.

~

8208160244 820721 PDR ADOCK 05000370

-

O PDR

!

- _.

_ _ _ _. _ - _

- -..

.__

-

i t

,,.

.

,

'

.

a.:

.

.

-!

REPORT DETAILS i

'

1.

Persons Contacted

!

Licensee Employees i

!

"M. D. McInt'osh, Station Manager

'

W. M. Sample, Projects and Licensing Engineer

,

  • H. B. Barron, Operations Engineer
  • J. W. Boyle, Performance Engineer

.

E. E. Estep, Project Engineer

'

.

  • D. B. Lampke, Licensing Engineer
  • D. Mendezoff, Engineering Specialist

Other licensee employees contacted included security force members and office personnel.

j

  • Attended exit -interview a

.

2.

Exit Interview I

i The inspection scope and findings were summarized on July 9,1982, with i

,

i those persons indicated in paragraph I above. The licensee acknowledged

!

the inspector's comments and findings.

<

f

3.

Licensee Action on Previous Inspection Findings

Not inspected.

4.

Unresolved Items I

!

Unresolved items were not identified during this inspection.

I

!

i 5.

Preoperational Test Results Evaluation (70329)

t

>

The inspectors reviewed the test results and licensee acceptance for the

[

following preoperational tests:

,

a.

TP/2/A/1400/11, Spent Fuel Cooling System Functional Test

[

b.

TP/2/A/1200/03A, Upper Head Injection System Functional Test r

The inspector reviewed the results of the above tests to verify the i

following:

!

a.

Individual test steps and data sheets were properly initialed and

,

dated.

!

l

<

b.

Data sheets were completed.

!

!

,

!

--

, -, _ -. _ _ -., -., -.

. -.,,

_, _ -.,...

, -, -.,,.,,,,.

, _ _,.. _,, __

,.. _.. -, - _,,--

.

.

c.

Changes to procedures were made in accordance with pertinent require-ments.

d.

Test changes did not change the basic objective of the test.

e.

Test deficiencies were identified.

Within the areas inspected, no violations or deviations were identified.

6.

Preoperational Test Procedure Review (70303, 70304, 70308, and 70311)

The inspector reviewed certain preoperational test procedures to verify that adequate test procedures were developed and approved which incorporated the requirements of Regulatory Guide 1.68, and appropriate portions of FSAR Section 14.

Procedures reviewed completely or in part included the following:

a.

TP/2/A/1100/01 (DRAFT), Controlling Procedure for Hot Functional Testing b.

TP/2/A/1150/05, Pressurizer Preliminary Spray Flow c.

TP/2/A/1150/09, Reactor Coolant System Functional Test (Cold)

d.

TP/2/A/1150/19, Pressurizer Safety Relief Valve Acoustic Leak Detection e.

TP/2/A/1200/01, Component Cooling Functional Test f.

TP/2/A/1200/03A, Upper Head Injection System Functional Test g.

TP/2/A/1200/04, Containment Spray System Functional Test h.

TP/2/A/1200/05A, Residual Heat Removal System Functional Test 1.

TP/2/A/1200/10, Primary Sampling System Functional Test j.

TP/2/A/1200/15, Mechanical Penetration Leak Rate Test k.

TP/2/A/1200/17, Fuel Transfer Tube Leak Rate Test 1.

TP/2/A/1200/20, Equipment Hatch Leak Rate Functional Test m.

TP/2/A/1200/21, Piping Operation Vibration Measurement n.

TP/2/A/1400/11 Spent Fuel Cooling System Functional Test Within the areas inspected, no violations or deviations were identified.

.

..

.

7.

Miscellaneous Activities The inspector completed the test and other required activities and obtained the security badge necessary to have unfettered access to the facility.

I l

l