Annual Assessment Letter - McGuire Nuclear Station (NRC Inspection Report 05000369-06-001 and 05000370-06-001) - Inspection/Activity Report 03-01/2006 - 09/30/2007
ML060610587
Person / Time
Site: Mcguire, McGuire  Duke Energy icon.png
Issue date: 03/02/2006
From: Ernstes M
NRC/RGN-II/DRP/RPB1
To: Gordon Peterson
Duke Energy Corp
Shared Package
ML060610567 List:
References
IR-06-001
Download: ML060610587 (2)


Text

McGuire Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2006 14:01:56 Report 22

EB1-CDBI

- COMPONENT DESIGN BASES INSPECTION Baseline Inspections 03/06/2006 03/10/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 03/20/2006 03/24/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 04/03/2006 04/07/2006 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 04/17/2006 04/21/2006 1, 2 7111121 IP Component Design Bases Inspection

OL RQ

- REQUAL INSPECTION Baseline Inspections 05/15/2006 05/19/2006 1, 2 7111111B IP Licensed Operator Requalification Program

ISFSI-O

- 60855.1 - OPERATION OF AN ISFSI Other Routine 07/03/2006 07/07/2006

60855.1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants

PSB1-RP

- RP OCCUPATIONAL PRE-INSP VISIT/ISFSI Baseline Inspections 08/28/2006 08/30/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas

PSB1-RP

- RP BASELINE OCCUPATIONAL WK1 Baseline Inspections 09/18/2006 09/22/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/18/2006 09/22/2006 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 09/18/2006 09/22/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/18/2006 09/22/2006 1, 2 71151 IP Performance Indicator Verification

EB3-ISI

- U2 INSERVICE INSPECTION Baseline Inspections 09/25/2006 09/29/2006

7111108P IP Inservice Inspection Activities - PWR

EB1-SUMP

- PWR CONTAINMENT SUMP BLOCKAGE TI (U-2)

Baseline Inspections 10/01/2006 10/06/2006

71111 IP Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity

EB3TI150

- 2515/150 U-2: RPV & VHP NOZZLES Safety Issues 10/02/2006 10/06/2006

2515/150 IP Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA-03-

PSB1-RP

- RP BASELINE OCCUPATIONAL WK2 Baseline Inspections 10/02/2006 10/06/2006 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 10/02/2006 10/06/2006 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 10/02/2006 10/06/2006 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 10/02/2006 10/06/2006 1, 2 71151 IP Performance Indicator Verification

PSB2-EP

- EP INSP Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111402 IP Alert and Notification System Testing Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111403 IP Emergency Response Organization Augmentation Testing Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 10/23/2006 10/27/2006 1, 2 7111405 IP Correction of Emergency Preparedness Weaknesses and Deficiencies Baseline Inspections 10/23/2006 10/27/2006 1, 2 71151 IP Performance Indicator Verification

EB2-TFP

- FIRE PROTECTION-TRIENNIAL PRE INSP VISIT Baseline Inspections 10/31/2006 11/02/2006 1, 2 7111105T IP Fire Protection [Triennial]

This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedures.

Enclosure

McGuire Inspection / Activity Plan 03/01/2006 - 09/30/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2006 14:01:56 Report 22

EB2-TFP

- FIRE PROTECTION-TRIENNIAL Baseline Inspections 11/27/2006 12/01/2006 1, 2 7111105T IP Fire Protection [Triennial]

Baseline Inspections 12/11/2006 12/15/2006 1, 2 7111105T IP Fire Protection [Triennial]

PB1-PI&R

- BIENNAL PI&R INSPECTION Baseline Inspections 01/22/2007 01/26/2007 1, 2 71152B IP Identification and Resolution of Problems Baseline Inspections 02/05/2007 02/09/2007 1, 2 71152B IP Identification and Resolution of Problems

EB1-MODS

- MODIFICATIONS-10CFR50.59 Baseline Inspections 02/12/2007 02/16/2007 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 02/12/2007 02/16/2007 1, 2 7111117B IP Permanent Plant Modifications

OL PREP

- INITIAL EXAM PREP Not Applicable 02/26/2007 03/02/2007

V23235 MCGUIRE/EXAMS AT POWER FACILITIES

OL EXAM

- INITIAL EXAM Not Applicable 03/19/2007 03/30/2007

V23235 MCGUIRE/EXAMS AT POWER FACILITIES

EB3-ISI

- U1 INSERVICE INSPECTION Baseline Inspections 03/26/2007 03/30/2007

7111108P IP Inservice Inspection Activities - PWR

EB3TI150

- 2515/150 U-1: RPV & VHP NOZZLES Safety Issues 03/26/2007 03/30/2007

2515/150 IP Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC ORDER EA-03-

EB3SGISI

- U1 STEAM GENERATOR ISI Baseline Inspections 04/02/2007 04/06/2007

7111108P IP Inservice Inspection Activities - PWR

EB1-SUMP

- PWR CONTAINMENT SUMP BLOCKAGE TI (U-1)

Baseline Inspections 04/08/2007 04/13/2007

71111 IP Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity

EB3-HS

- HEAT SINK Baseline Inspections 04/23/2007 04/27/2007 1, 2 7111107B IP Heat Sink Performance

EB3-MR

- MR EFFECTIVENESS Baseline Inspections 06/04/2007 06/08/2007 1, 2 7111112B IP Maintenance Effectiveness

PSB1-RP

- RP PUBLIC PRE-INSP/ISFSI Baseline Inspections 07/31/2007 08/02/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas

PSB1-RP

- RP PUBLIC BASELINE INSP Baseline Inspections 08/27/2007 08/31/2007 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 08/27/2007 08/31/2007 1, 2 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 08/27/2007 08/31/2007 1, 2 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 08/27/2007 08/31/2007 1, 2 7112203 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P Baseline Inspections 08/27/2007 08/31/2007 1, 2 71151 IP Performance Indicator Verification This report does not include INPO and OUTAGE activitie This report shows only on-site and announced inspection procedures.