MONTHYEARML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 ML24023A0652024-01-23023 January 2024 Inservice Inspection Request for Information IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle ML23178A0892023-06-26026 June 2023 August 2023 Emergency Preparedness Program Inspection-Request for Information ML23118A3202023-05-0808 May 2023 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information (05000313;05000368/2023010) ML22229A4862022-08-23023 August 2022 ANO Inspection Plan Letter 2022 Mid Cycle-FINAL ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22075A2052022-03-31031 March 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection (05000313/2022002 and 05000368/20220020 and Request for Information ML22083A2182022-03-30030 March 2022 NRC Initial Operator Licensing Operating Test Approval 05000313/2022301 IR 05000313/20210062022-03-0202 March 2022 Annual Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Report 05000313/2021006 and 05000368/2021006) ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21232A2232021-09-0101 September 2021 ANO Mid-Cycle Inspection Plan Transmittal Letter 2021 ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21215A2932021-08-0303 August 2021 Inservice Inspection Request for Information ML21109A2432021-04-19019 April 2021 Arkansan Nuclear One, Unit 1 - Notification of Inspection (NRC Inspection Report 05000313/2021003) and Request for Information ML21077A0162021-03-22022 March 2021 Notification of NRC Design Bases Assurance Inspection (Team) (05000313/2021010 and 05000368/2021010) and Initial Request for Information IR 05000313/20200062021-03-0303 March 2021 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2020006 and 05000368/2020006) ML21053A4032021-02-23023 February 2021 Document Request List - ANO IR 2021402 IR 05000313/20200052020-09-0101 September 2020 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Reports 05000313/2020005 and 05000368/2020005) ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 IR 05000313/20190062020-03-0303 March 2020 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2019006 and 05000368/2019006) ML19331A3132019-11-27027 November 2019 ANO Unit 2 Request for Information IR 05000313/20190052019-08-30030 August 2019 Updated Inspection Plan for Arkansas Nuclear One, Unit 1 and 2, Report 05000313/2019005 and 05000368/2019005 ML19080A0372019-03-21021 March 2019 Notification of Inspection (NRC Inspection Report 05000313/2019003 and Request for Information ML18324A8052018-11-19019 November 2018 Notification of an NRC Triennial Fire Protection Baseline Inspection Report 05000313/2019010 and 05000368/2019010) and Request for Information IR 05000313/20180052018-08-31031 August 2018 Updated Inspection Plan for Arkansas Nuclear One (Report 05000313/2018005 and 05000368/2018005) ML18164A3892018-06-14014 June 2018 Arkansas, Notification of NRC Design Bases Assurance Inspection (Teams) (05000313/2018011 and 05000368/2018011), and Initial Request for Information IR 05000313/20170052017-08-28028 August 2017 Arkansas, Units 1 and 2, Update Inspection Plan (Report 05000313/2017005 and 05000368/2017005) IR 05000313/20160062017-03-0101 March 2017 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016006 and 05000368/2016006) IR 05000313/20160052016-09-12012 September 2016 Errata for Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) IR 05000313/20164012016-08-31031 August 2016 Non-Public Security Inspection Plan for Arkansas Nuclear One NRC Physical Security Inspection Report Numbers 05000313/2016401 and 05000368/2016401) ML16237A4122016-08-31031 August 2016 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2016005 and 05000368/2016005) ML16223A4622016-08-0909 August 2016 Inspection Planning Considerations for ANO CAL Follow-Up Pkg IR 05000313/20150062016-03-0202 March 2016 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015006 and 05000368/2015006) IR 05000313/20154012015-09-0101 September 2015 Non-Public Security Inspection Plan for Arkansas Nuclear One(Nrc Physical Security Inspection Report Numbers 05000313/2015401 and 05000368/2015401) IR 05000313/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2015005 and 05000368/2015005) IR 05000313/20144022014-09-0202 September 2014 Non-Public Security Inspection Plan for Arkansas Nuclear One (NRC Physical Security Inspection Report Numbers 05000313/2014402 and 05000368/2014402) IR 05000313/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2014006 and 05000368/2014006) IR 05000313/20130012014-03-0404 March 2014 Annual Assessment Letter for Arkansas Nuclear One Units 1 and 2 (Report 05000313/2013001 and 05000368/2013001) IR 05000313/20130062013-09-0303 September 2013 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313-13-006 and 05000368-13-006) IR 05000313/20128012013-03-0404 March 2013 Annual Assessment Letter for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2012801 and 05000368/2012801) IR 05000313/20120062012-09-0404 September 2012 Mid-Cycle Assessment Letter for Arkansas Nuclear One, Units 1 & 2 (Reports 05000313-12-006 and 05000368-12-006) IR 05000313/20120012012-03-0505 March 2012 Annual Assessment Letter for Arkansas Nuclear One - Units 1 and 2 (Report 05000313/2012001 and 05000368/2012001) ML1124403662011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One, Units 1 and 2 IR 05000313/20110012011-03-0404 March 2011 Annual Assessment Letter for Arkansas Nuclear One Units 1 & 2 (Report 05000313-11-001 and 05000368-11-001) ML1024305372010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Arkansas Nuclear One IR 05000313/20100012010-03-0303 March 2010 Annual Assessment Letter - Arkansas Nuclear One (Report 05000313-10-001 and 05000368-10-001) 2CAN110904, Snubber Testing Program for Fourth Inspection Interval2009-11-10010 November 2009 Snubber Testing Program for Fourth Inspection Interval 2024-04-17
[Table view] Category:Letter
MONTHYEARML24295A1202024-10-21021 October 2024 Relief Request ANO2-RR-24-001, Half-Nozzle Repair of Reactor Vessel Closure Head Penetration 71 IR 05000368/20253012024-09-0909 September 2024 Notification of NRC Initial Operator Licensing Examination 05000368/2025301 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000313/20240112024-09-0505 September 2024 Comprehensive Engineering Team Inspection Report 05000313/2024011 and 05000368/2024011 IR 05000313/20244042024-08-29029 August 2024 Cybersecurity Inspection Report 05000313/2024404 and 05000368/2024404 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24198A0722024-08-21021 August 2024 Correction to Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000313/20240052024-08-21021 August 2024 Updated Inspection Plan for Arkansas Nuclear One – Units 1 and 2 (Report 05000313/2024005, 05000368/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 IR 05000313/20240022024-08-0606 August 2024 Integrated Inspection Report 05000313/2024002 and 05000368/2024002 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24101A1792024-06-25025 June 2024 Issuance of Amendment No. 333 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information IR 05000313/20240012024-05-0808 May 2024 Integrated Inspection Report 05000313/2024001 and 05000368/2024001 ML24128A2472024-05-0808 May 2024 Project Manager Assignment ML24017A2982024-04-18018 April 2024 Summary of Regulatory Audit Regarding the License Amendment Request to Revise Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information IR 05000313/20243012024-04-16016 April 2024 NRC Examination Report 05000313/2024301 ML24086A5412024-04-10010 April 2024 Authorization of Request for Alternative ANO1-ISI-037 Regarding Extension of Reactor Vessel Inservice Inspection Interval IR 05000313/20244022024-04-0808 April 2024 Security Baseline Inspection Report 05000313/2024402 and 05000368/2024402 (Full Report) ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24031A6442024-03-14014 March 2024 Issuance of Amendment No. 282 to Modify Technical Specification 3.3.1, Reactor Pressure System (RPS) Instrumentation, Turbine Trip Function on Low Control Oil Pressure ML24102A1342024-03-12012 March 2024 AN1-2024-03 Post Exam Submittal IR 05000313/20230062024-02-28028 February 2024 Annual Assessment Letter for Arkansas Nuclear One- Units 1 and 2 Report 05000313/2023006 and 05000368/2023006 IR 05000313/20230042024-02-0808 February 2024 Integrated Inspection Report 05000313/2023004 and 05000368/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023002 ML24012A0502024-02-0202 February 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0054 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23326A0392024-01-24024 January 2024 Issuance of Amendment No. 281 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24017A1582024-01-17017 January 2024 Submittal of Emergency Plan Revision 50 IR 05000313/20234202024-01-10010 January 2024 Security Baseline Inspection Report 05000313/2023420 and 05000368/2023420 IR 05000313/20234022024-01-0202 January 2024 Security Baseline Inspection Report 05000313/2023402 and 05000368/2023402 ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23354A0022023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology – Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment IR 05000313/20234052023-12-12012 December 2023 – Security Baseline Inspection Report 05000313/2023405 and 05000368/2023405 ML23341A0832023-12-11011 December 2023 – Material Control and Accounting Program Inspection Report 05000313/368/2023404- Cover Letter ML23305A0922023-12-0707 December 2023 Summary of Regulatory Audit Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times RITSTF Initiative 4b ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23275A2072023-11-28028 November 2023 Issuance of Amendment No. 280 Removal of Technical Specification Condition Allowing Two Reactor Coolant Pump Operation IR 05000313/20230032023-11-21021 November 2023 Revised - ANO Revised Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/ 2023001 ML23325A1412023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23243B0452023-11-13013 November 2023 Request for Withholding Information from Public Disclosure ML23313A0962023-11-13013 November 2023 Integrated Inspection Report 05000313/2023003 and 05000368/2023003 and Independent Spent Fuel Storage Installation Inspection Report 07200013/2023001 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000313/20230112023-10-10010 October 2023 Commercial Grade Dedication Inspection Report 05000313/2023011 and 05000368/2023011 IR 05000313/20230052023-08-21021 August 2023 Updated Inspection Plan for Arkansas Nuclear One, Units 1 and 2 (Report 05000313/2023005 and 05000368/2023005) - Mid Cycle 2024-09-09
[Table view] |
Text
ust 30, 2019
SUBJECT:
UPDATED INSPECTION PLAN FOR ARKANSAS NUCLEAR ONE, UNITS 1 AND 2, REPORT 05000313/2019005 AND 05000368/2019005
Dear Mr. Anderson:
The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for Arkansas Nuclear One, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC)
provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
On March 12, 2018, the NRC issued a Confirmatory Order (ADAMS Accession No.
ML18072A191) (EA-17-132 and EA-17-153), to the Entergy fleet that included Arkansas Nuclear One, Units 1 and 2. The NRC plans to conduct a Confirmatory Order followup inspection at Entergy Corporate Headquarters in Jackson, MS of the actions required to be completed by the end of calendar year 2019, in accordance with Inspection Procedure 92702, Followup on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, Confirmatory Orders, And Alternative Dispute Resolution Confirmatory Orders.
This inspection will be conducted during the first quarter of 2020 on a date to be determined by the NRC and Entergy.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390 of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1574 with any questions you have regarding this letter.
Sincerely,
/RA/
John L. Dixon, JR, Chief Project Branch D Division of Reactor Projects Docket Nos. 50-313; 50-368 License Nos. DPR-51; NPF-6 Enclosure:
Inspection Plan
ML19235A087 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: BKC Yes No Publicly Available Sensitive Nrc-002 OFFICE PBD:ASPE PBD:C NAME BCorrell JDixon SIGNATURE /RA/ /RA/
DATE 08/22/19 08/30/19
IP 22 Inspection Activity Plan Report 07200013 - ANO 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count ANO ISFSI Loading Inspection 2 1 06/17/2019 08/30/2019 IP 60855 001001 Operation Of An ISFSI 1 06/17/2019 08/30/2019 IP 60857 001004 Review of 10 CFR 72.48 Evaluations This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:45:34 AM
IP 22 Inspection Activity Plan Report Arkansas Nuclear One 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count ANO 2019 BRQ (UNIT 1) 2 1 07/07/2019 07/13/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance ANO Biennial PI&R Inspection 4 1, 2 08/05/2019 08/09/2019 IP 71152B 000747 Problem Identification and Resolution 1, 2 08/19/2019 08/23/2019 IP 71152B 000747 Problem Identification and Resolution EP PROGRAM INSPECTION 1 1, 2 08/26/2019 08/30/2019 IP 71114.02 000717 Alert and Notification System Testing 1, 2 08/26/2019 08/30/2019 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 08/26/2019 08/30/2019 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 08/26/2019 08/30/2019 IP 71151 001397 Performance Indicator Verification Security Access Control .02 1 1, 2 09/02/2019 09/13/2019 IP 71130.02 000734 Access Control 1, 2 09/02/2019 09/13/2019 IP 71151 001338 Performance Indicator Verification Inservice Inspection 1RF18 - ANO 1 1 10/20/2019 10/26/2019 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP INSPECTION (1,3) 2 1, 2 10/21/2019 10/25/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/21/2019 10/25/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation ANO 10CFR50.59 INSPECTION 3 1, 2 11/18/2019 11/22/2019 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments ANO ENTERGY CO FOLLOWUP - 2 3 1, 2 12/01/2019 03/31/2020 IP 92702 CONF 001581 Enforcement Related Order Follow-Up-Only ANO 2020 INITIAL EXAM (UNIT 1) 7 1 03/01/2020 03/07/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 03/29/2020 04/04/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Inservice Inspection 2RF27 - ANO 1 2 03/23/2020 04/03/2020 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:45:34 AM
IP 22 Inspection Activity Plan Report Arkansas Nuclear One 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count RS 12PI Radiation Safety 2 1, 2 03/23/2020 03/27/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/23/2020 03/27/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls Security Access Control .02 1 1, 2 05/11/2020 05/15/2020 IP 71130.02 000734 Access Control 1, 2 05/11/2020 05/15/2020 IP 71151 001338 Performance Indicator Verification Arkansas Nuclear 1, 2 - Design Bases Assurance Inspection (Programs) 3 1, 2 06/08/2020 06/12/2020 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
1, 2 06/22/2020 06/26/2020 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
RS5678 Radiation Safety PS Team 4 1, 2 06/15/2020 06/19/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 06/15/2020 06/19/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 06/15/2020 06/19/2020 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 06/15/2020 06/19/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation MC&A - Material Control & Accounting 1 1, 2 06/15/2020 06/19/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)
ANO 2020 BRQ (Unit 2) 2 2 07/05/2020 07/11/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EP Exercise and PI Inspection 4 1, 2 09/14/2020 09/18/2020 IP 71114.01 000716 Exercise Evaluation 1, 2 09/14/2020 09/18/2020 IP 71151 001397 Performance Indicator Verification Security Equipment .04 and Training .07 2 1, 2 10/05/2020 10/09/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 10/05/2020 10/09/2020 IP 71130.07 000739 Security Training ANO UNIT 2 2021 INITIAL EXAM 7 2 02/28/2021 03/06/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2 03/28/2021 04/03/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:45:34 AM
IP 22 Inspection Activity Plan Report Arkansas Nuclear One 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Security Access Auth .01 and Access Control .02 w/PIV 2 1, 2 03/08/2021 03/12/2021 IP 71130.01 000733 Access Authorization 1, 2 03/08/2021 03/12/2021 IP 71130.02 000734 Access Control 1, 2 03/08/2021 03/12/2021 IP 71151 001338 Performance Indicator Verification Inservice Inspection 1RF29 - ANO 1 1 04/12/2021 04/23/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,3,PI 2 1, 2 04/19/2021 04/23/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/19/2021 04/23/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Design Bases Assurance (Teams) 21M - ANO 6 1, 2 06/14/2021 07/02/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
ANO1 2021 BRQ 2 1 06/27/2021 07/03/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.
8/23/2019 9:45:34 AM