IR 05000354/1980011

From kanterella
Jump to navigation Jump to search
Mgt Meeting Repts 50-354/80-11 & 50-355/80-11 on 800805.Subj Discussed:Project & FSAR Status,Resident Insp Program & Licensee Performance
ML19338E741
Person / Time
Site: Hope Creek  PSEG icon.png
Issue date: 08/25/1980
From: Bateman W, Robert Carlson, Mcgaughy R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19338E737 List:
References
50-354-80-11, 50-355-80-11, NUDOCS 8010060073
Download: ML19338E741 (2)


Text

.

n

'

.

m U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I Report No.

50-354/80-11 50-355/80-11 Docket Nos.

50-354 50-355 License Nos.

CPPR-120 Priority Category A

CPPR-121 Licensee:

Public Service Electric and Gas Company 80 Park Place Newark, New Jersey 07101 Facility Name:

Hope Creek Generating Station, Units 1 and 2 Inspection at:

PSE&G Corporate Office, Newark, New Jersey Inspection conducted:

August 5, 980 f')jl9 b Inspectors:

.

Resident Inspector dt te'si ned

-

w W. H. Batenfan, Seni hW 5h Rt W. 'McGaugby,f t, Projects Section Aate $1gned Approved by:

MM 7f and Engineer,gipyT, Reactor Construction I. Carlson 4ated signed

.

iny5upport Branch Meeting Summary:

Meeting on August 5, 1980 (Report Nos. 50-354/80-11 and 50-355/80-11)

Areas Covered:

Ihis was a routine meeting held with the management of the licensee to discuss the following:

(a) Hope Creek project status, (b) status of FSAR, (c) resident inspection program, (d) NRC independent measurements program, (e) NRC programs underway to evaluate licensee performance, (f) 10 CFR 50.55(e) reporting, and (g) enforcement policy.

8010060 07 )

l

-

&

..

DETAILS 1.

Personnel Attending Public Service Electric and Gas Company R. Bast, General Manager - Engineering A. Giardino, Project QA Engineer D. Jagt, Manager, Salem Projects M. Koenig, Project Control Engineer P. Kudless, Principal Construction Engineer P. Landrieu, Project Engineer T. Martin, Vice President Engineering and Construction R. Mittl, General Manager, Licensing and Environmental F. Omohundro, Assistant Manager, QA J. Recknagel, Project Licensing Manager E. Schwalje, Manager, QA U.S. Nuclear Regulatory Commission - Region I W. Bateman, Senior Resident Inspector, Hope Creek R. Carlson, Chief, Reactor Construction and Engineering Support Branch R. McGaughy, Chief, Projects Section L. Tripp, Chief, Engineering Support Section 2 2.

Areas Discussed A.

Overview of construction status and schedule B.

NRC organization and recent changes C.

Status of Hope Creek FSAR D.

NRC Resident Inspect:r program E.

NRC Independent Measurements program F.

Performance Appraisal Team (PAT) program i

G.

Systematic Assessment of Licensee Performance

'

(SALP)

H.

10 CFR 50.55(e) reporting I.

Enforcement and enforcement responses J.

Other construction inspection program changes K.

Inspection findings at Hope Creek L.

Licensee / Contractor /AE relationship M.

QA Program i