IR 05000338/2019004

From kanterella
(Redirected from IR 05000339/2019004)
Jump to navigation Jump to search
Integrated Inspection Report 05000338/2019004 and 05000339/2019004
ML20038A126
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 02/07/2020
From: Louis Mckown
NRC/RGN-II/DRP/RPB4
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
References
IR 2019004
Download: ML20038A126 (18)


Text

February 7, 2020

SUBJECT:

NORTH ANNA POWER STATION - INTEGRATED INSPECTION REPORT 05000338/2019004 AND 05000339/2019004

Dear Mr. Stoddard:

On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at North Anna Power Station. On January 8, 2020, the NRC inspectors discussed the results of this inspection with Ms. Lisa Hilbert and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Louis J. McKown, II, Chief (Acting)

Reactor Projects Branch 4 Division of Reactor Projects

Docket Nos. 05000338 and 05000339 License Nos. NPF-4 and NPF-7

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000338 and 05000339

License Numbers:

NPF-4 and NPF-7

Report Numbers:

05000338/2019004 and 05000339/2019004

Enterprise Identifier: I-2019-004-0030

Licensee:

Virginia Electric & Power Co.

Facility:

North Anna Power Station

Location:

Mineral, VA

Inspection Dates:

October 01, 2019 to December 31, 2019

Inspectors:

P. Capehart, Senior Operations Engineer

G. Eatmon, Resident Inspector

M. Tobin, Senior Resident Inspector

Approved By:

Louis J. McKown, II, Chief (Acting)

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at North Anna Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at approximately 10 percent power for a power escalation following a planned refueling outage. On October 4th, 2019, Unit 1 achieved rated thermal power and remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, Outside Recirc Spray and Casing Cooling, Train A and B on December 3, 2019
(2) Unit 2, Outside Recirc Spray and Casing Cooling, Train A and B on December 13, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 auxiliary feedwater system on November 26, 2019.

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1 cable vault and tunnel on October 18, 2019
(2) Unit 1 safety related battery rooms on October 18, 2019
(3) Unit 2 safety related battery rooms on October 18, 2019
(4) Unit 2 safeguards building on October 31, 2019
(5) Unit 1 and Unit 2 aux building basement during hot-work and removed fire barriers on December 12, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Unit 1 and Unit 2, charging pump cube A, B, and C on November 12, 2019

Inspection Activities - Underground Cables (IP Section 02.02c.) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Manholes 4MH03 and 4MH04 on November 29, 2019

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), Requalification Requirements, of the NRCs Operators Licenses. During the week of January 3 2020, the inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with Inspection Procedure (IP) 71111.11, Licensed Operator Requalification Program. These results were compared to the thresholds established in Section 3.02, Requalification Examination Results, of IP 71111.11.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during a main feedwater swap complicated by a failed flow switch on October 29, 2019.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a rapid down power and low power feedwater operation training evolution on October 22, 2019 in the simulator.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (3 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Unit 2 bearing cooling pumps on October 31, 2019
(2) Unit 1 and Unit 2 Appendix R lighting on December 10, 2019
(3) Unit 1 and Unit 2 Plant Computer System and Secure Plant Data Systems on December 16, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Elevated risk due to Reserve Station Service Transformer 'B' being removed from service with degraded cabling to the Station Service Transformer 'B' on October 17, 2019
(2) Unit 1 and Unit 2 elevated risk due to the service water header check valve to the Unit 2 charging pump 'C' being unavailable on November 5, 2019
(3) Unit 1 in elevated risk due to the turbine driven auxiliary feedwater pump being unavailable on November 29, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (5 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Safety related cable conduit with potential transient combustibles inside on October 17, 2019 (CR1133208)

(2)1NNSANH002 damaged cable shield and outer jacket on November 4, 2019 (CR1135004)

(3) Main feedwater recirculation flow switch automatic action disabled due to failed flow switch on November 14, 2019 (CR1134482)
(4) Unit 1 and Unit 2 diesel driven fire pump engine failure during annual testing on December 18, 2019 (CR1124204)
(5) Unit 1 and Unit 2 potential vulnerability identified with control room envelope testing methodology on December 19, 2019 (CA7771875)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1 and Unit 2 permanent storage of scaffolding racks in containment on 216' elevation on December 19, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Unit 1 emergency diesel generator following replacement of the governor on October 15, 2019
(2) Unit 1 Rod drop time testing prior to reactor startup, on October 16, 2019
(3) Unit 1 intermediate range, N-35, failed during unit shutdown for planned refueling on October 22, 2019
(4) Unit 1 and Unit 2 control room HVAC supply air operated damper diaphragm replacement and spring load testing on December 9, 2019
(5) Unit 2 steam generator blow down trip valve, 2-BD-TV-200A, failed to open during testing on November 14, 2019
(6) Unit 2 service water valve, 2-SW-MOV-204A, failed stroke time testing on November 15, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 2 'H' emergency diesel generator fast start on October 7, 2019
(2) Unit 1 charging pump, 1-CH-P-1B, periodic test on November 12,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 2018-September 2019)
(2) Unit 2 (October 2018-September 2019)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (October 2018-September 2019)
(2) Unit 2 (October 2018-September 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in supply chain management and adverse material condition of components issued from the warehouse for installation in the plant that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Unit 1 and Unit 2 common cause failure of auxiliary feedwater pump discharge due to tornado missile reevaluation
(2) Unit 1 and Unit 2 containment hatch closure requirements

INSPECTION RESULTS

Observation: Unit 1 and Unit 2 Common Cause Failure of Auxiliary Feedwater Pump Discharge due to Tornado Missile 71152 The inspectors conducted a detailed review of the licensees evaluation of Regulatory Issue Summary (RIS) 2015-06, Tornado Missile Protection with respect to a design basis tornado missile that could impact all three trains of auxiliary feedwater pump discharge pipe and results in a previously unidentified common cause failure scenario. The issue is documented for Unit 1 in CR1124894, with prompt operability determination CA7621480, and for Unit 2 in CR1124899, with prompt operability determination CA7621494. The 12-inch diameter design basis missile enters the auxiliary feedwater pump house through the vestibule, maintains the line-of-sight trajectory and orientation through the existing barriers, and strikes all three trains of auxiliary feedwater pump discharge pipe. The licensees UFSAR identifies that the auxiliary feedwater pumphouse is protected from tornado missiles. The acceptable design parameters for a tornado resistant structure are:

  • A 2-foot-thick heavily reinforced concrete with rebar (from the licensees UFSAR)
  • A 2-inch-thick steel plate (from Calculation CE-1856, Design Supplemental Missile Barrier for Aux. Feedwater Pump House, dated July 14, 2006)

For Unit 1, the licensees operability determination identifies the tornado missile would pass through 24 inches of non-reinforced concrete from the nearby structure and 1.2 inches of the metal equipment and support structures in the auxiliary feedwater pumphouse. For Unit 2, the licensees operability determination also relies on the metal equipment and support structures totaling over 2.5 inches of metal within the auxiliary feedwater pumphouse

Following Enforcement Guidance Memorandum 15-002, Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance, the licensee reviewed RIS 2015-06, concluded that a technical specification controlled structure does not comply with the current licensing basis, performed an engineering evaluation to determine the structure is operable but non-conforming, and is addressing the non-complying condition through their corrective action program.

Observation: Containment Equipment Hatch Closure Requirements 71152 The inspectors conducted a detailed review of an NRC-identified issue in CR 1130343, initiated on September 8, 2019, regarding the uncertainty involved in how many personnel would be available to assist during a postulated required containment hatch closure.

During this inspection, the resident inspectors discovered that one of the emergency operating procedures that could require a hatch closure, 1-AP-11, Loss of RHR, Revision 34, required operators to announce a containment evacuation prior to directing the hatch closure team on station to close the hatch, which by procedure is required to be closed within the time to boil or within 45 minutes, whichever is lower. However, the residents discovered that when performing hatch closure drills, non-assigned personnel would assist the team in closing the hatch. Since an evacuation was ordered prior to a hatch closure order, the licensee and the resident inspectors agreed that the closure team should not rely on outside assistance. The licensee directed the hatch closure team to expect to do any future drill or actual required closure without assistance. The licensee enhanced their process to ensure that future drills would be more accurate to real scenarios. Additionally, based on the sites self-imposed standards and alternate source term documentation, there are no requirements related to how quickly the hatch must be secured, so there are no performance deficiencies associated with this inspection.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 8, 2020, the inspectors presented the integrated inspection results to Ms.

Lisa Hilbert and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04Q Corrective Action

Documents

Resulting from

Inspection

CR1137882

Security Barrier Sheet Metal Touching Insulation for 2-RS-

TK-1 Unit 2 Casing Cooling Tank

2/13/2019

Drawings

11715-FM-074A

Flow/Valve Operating Numbers Diagram Feedwater System

Procedures

1-AR-J-B6

RS PP 2A or 2B Vibration

1-AR-J-B6

RS PP 2A LO or OL Trip

1-AR-J-G5

RS PP 1B Lockout or Auto Trip or Test

1-AR-J-G6

RS PP 2B LO or OL Trip

1-OP-7.5A

Valve Checkoff - Outside Recirculation Spray System

1-PT-71.12

AFW System Valve Position Verification

2-OP-7.5A

Valve Checkoff - Outside Recirculation Spray System

71111.05Q Calculations

NA-2011-0021

Evaluation of Permanently Stored Combustible Material

Corrective Action

Documents

Resulting from

Inspection

CR1133208

CR1134147

NRC identified issue: housekeeping issues in both units QS

and SFGDs pumphouses lower levels

CR1134150

NRC identified issue: Foreign material in cable trays above

2-RS-P-2A pump cube area

CR1137788

NRC questions about hot work in 1-CH-P-1B cubicle

2/12/2019

Fire Plans

1-FS-AB-1

Auxiliary Building (All Elevations) Fire Fighting Strategy Safe

Shutdown Equipment

2-FS-SG-1

Safeguards Area Safe Shutdown Equipment Unit 2

Procedures

0-FS-CT-1

Cable Tray Spreading and Battery Room 2-1, 1-1, 2-3, 1-3

0-PT-106.1C

Fire Protection - Simplex Fire Detectors - Outside

Containment - Channel Operational Test

1-FS-ESG-BR-1

Battery Rooms 1-2 and 1-4

003

2-FS-ESG-BR-1

Emergency Switchgear Battery Room 2-2-and 2-4

CM-AA-FPA-100

Fire Protection/Appendix R (Fire Safe Shutdown) Program

Work Orders

203270696

Fire Protection - Simplex Fire Detectors - Outside

Containment - Channel Operational Test

8/8/2019

71111.06

Corrective Action

CA3054959

Document Previous Functionality of Charging Pumps

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Corrective Action

Documents

Resulting from

Inspection

CR1134073

01-FPM-DET-458-DETECT is hanging by its wires

CR1136811

CR1137661

Why is backflow preventer 1-DB-BFP-2 not included in 0-

GOP-3.9

2/10/2019

Drawings

11715-FB-9A/B/C

Arrangement: Auxiliary Building, Floor Drainage, Sheet 1/2/3

Engineering

Evaluations

ET-N-10-0014

Engineering Technical Evaluation: Development of Flooding

TRM

9/6/2013

Miscellaneous

Safety Evaluation Report for North Anna Power Station,

Units 1 and 2

2/1979

Fire Protection System Review for North Anna Power

Station, Units 1 & 2, Supplement 2

1/3/1978

Virginia Electric and Power Company

North Anna Power Station Unit 1 and 2

Response to Generic Letter 88-20 and Supplement 1

Individual Plant Examination (IPE) for Severe Accident

Vulnerabilities

2/14/1992

2-92-4036-028

North Anna Power Station Commitment Data Form, IPE

Required Procedure Modificaiton

5/2/1994

Procedures

0-GOP-3.9

Weekly Check of Charging Pumps

0-MCM-1302-01

Mechanical Corrective Maintenance, Moving Heavy Loads

and Concrete Floor/Wall Plugs in the Auxiliary Buidling

71111.11Q Corrective Action

Documents

CR1135251

NRC requested information on Ops Initial Narrative Log

Entry

11/6/2019

Miscellaneous

Simulator Exercise Guide, course #SEG-12H

Procedures

OP-AA-100

Conduct of Operations

71111.12

Corrective Action

Documents

CA7441460

Perform MRule Functional Failure evaluation 02-ELT-

B0SB5-Battery found inoperable

11/19/2018

CA7475755

Perform MRule Functional Failure evaluation Transformer

found not working

2/26/2018

CA7476603

Perform MRule Functional Failure evaluation 1-ELT-B-HP6

not working

2/27/2018

CA7476926

Perform MRule Functional Failure evaluation Emergency

2/27/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

light found inoperable

CA7476928

Perform MRule Functional Failure evaluation 01-ELT-B-

AB13 found inoperable

2/29/2018

CA7476929

Perform MRule Functional Failure evaluation 01-ELT-B-

AB14 found inoperable

2/29/2018

CA7515388

Perform MRule Functional Failure evaluation 2-ELT-ELT-

MS12A not working

2/18/2019

CA7565438

CA7569001

Perform MRule Functional Failure evaluation 02-ELT-B-

AB20 not working

4/11/2019

CA7569002

Perform MRule Function Failure evaluation 01-ELT-B-AB13

4/11/2019

CA7569003

Perform MRule Functional Failure evaluation 01-ELT-B-

AB14 Not Working

4/11/2019

CA7569007

Perform MRule Functional Failure evaluation 01-ELT-B-HP3

4/11/2019

CA7578289

Perform MRule Function Failure evaluation for Appendix R

lantern found non-function during rounds

4/20/2019

CA7586469

Perform MRule Functional Failure evaluation Unit 2 Main

Steam Emergency Lighting Fixture Light Head

4/28/2019

CA7605957

Perform MRule Functional Failure evaluation for 01-ELT-B-

EG7-Battery failed 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> discharge test

5/15/2019

CA7644196

Perform MRule Functional Failure evaluation on 01-ELT-B-

TB5 lamps not lit

07/16/2019

CA7644207

Perform MRule Functional Failure evaluation 01-ELT-B-

AB23 lamps not lit

7/16/2019

CA7644936

Perform MRule Functional Failure evaluation 01-ELT-B-TB6

lights do not remain lit throughout 8hr discharge

7/17/2019

CA7671970

01-ELT-B-MS4-Battery

8/27/2019

CA7685370

CA7700741

2-ELT-B-AB7-Battery

10/1/2019

CA7700742

2-ELT-B-AB22-Battery

10/1/2019

CA7701647

01-ELT-ELT-CR4A-Light

09/30/2019

CA7701651

01-ELT-B-SW7-Battery

10/02/2019

CA7701655

2-ELT-B-SB7-Battery

10/2/2019

CR1120021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR1120153

CR1124240

CR1126295

CR1127232

CR1132184

EPM/ELT - Appendix R (M1) Unit 1 & 2

9/30/2019

CR1132401

CR1133828

Corrective Action

Documents

Resulting from

Inspection

CR1138186

VPAP-2606, "Safety Parameter Display System (SPDS)"

admin procedure found to contain deficiencies

Miscellaneous

MRule Tracking Group Basis Document for ELT02

MRule Tracking Group Basis Document ELT03

MRule (a)(1) Action Plan & (a)(1) Evaluation for 01-ELT-B-

MS4-Battery

10/02/2019

MRule System Basis Document for Emergency Lighting

Procedures

0-EMP-2808-01

Appendix R Emergency Light Inspection and Testing of Fire

Areas 2 (Control Room), 3-1 (U1 Cable Vault and Tunnel),

3-2 (U2 Cable Vault and Tunnel), 50 (Service Bldg

Stairwell), 5-1 (Unit 1 Normal Switchgear Room) and 5-2

(Unit 2 Normal Switchgear Room)

0-EMP-2808-03

Appendix R Emergency Light Inspection and Testing of Fire

Area 8 (Unit 1 and Unit 2 Turbine Bldg)

0-EPM-2808-05

Appendix R Emergency Light Inspection and Testing of Fire

Area 11 (Unit 1 and 2 Aux Bldg. and Fuel Bldg.)

0-EPM-2808-09

Inspection and Testing of Appendix R Emergency Light

Chargers

2-AP-42.1

Loss of Unit 2 Plant Computer System (PCS)

VPAP-2606

Safety Parameter Display System (SPDS)

VPAP-2802

Notifications and Reports

71111.13

Corrective Action

Documents

CR1134379

CR1134480

Corrective Action

Documents

CR1134443

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Resulting from

Inspection

Drawings

Figure 13.3-NA

Service Water System Diagram

04/19/07

Work Orders

WO59203300516

71111.15

Calculations

ET-CEP-09-0010

Evaluation of Compensatory Measures for Aluminum

Conduit Penetration Issues

ET-CEP-10-0006

Evaluation of Aluminum Conduit Seal Penetration Fire Tests

ET-N-10-0031

Evaluation of Aluminum Conduit Fire Penetrations

Corrective Action

Documents

CA7616237

CR1124204

CR1132231

CR1132259

CR1132332

CR1134482

CR1135934

Potential Vulnerability Identified with Control Room

Envelope Testing Methodology

11/14/2019

CR373123

CR395741

Corrective Action

Documents

Resulting from

Inspection

1133208

CR1134657

NRC identified: question concerning TS 3.7.10 during

damper testing

10/30/2019

Operability

Evaluations

CA7771875

Prompt Operability Determination for potential vulnerability

in the control room envelope testing methodology for supply

and exhaust dampers (1-HV-AOD-160-1/2 and 1-HV-AOD-

161-1/2)

11/21/2019

Procedures

0=PT-101.2

Warehouse 5 Fire Protection Pumps Annual Test

1-OP-2.1

Control of Feed Water Recircs During Power Ascension

106

ER-NA-CRH-100

Main Control Room/Emergency Switchgear Room

(MCR/ESGR) Envelope Habitability Program

OP-AA-100

Status and Configuration Control

OP-AA-100

Alternate Plant Configuration Sheet

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-AA-102

Operability Determinations

Work Orders

WO59102676139

WO59203300579

71111.18

Drawings

1500013-1-S-102

Scaffold Storage Box for Safway Scaffold Part SHR7

1500013-1-S-105

Scaffold Storage Box for Safway Scaffold Part SVP 3,7 & 10

Engineering

Changes

NA-15-00013

Scaffold Storage Rack for Unit 1 Containment 216' elevation

3/2/2016

NA-15-00014

Scaffold Storage Rack for Unit 2 Containment 216' Elevation

8/27/2015

Miscellaneous

NAPS-UCR-2015-

013

SAR Change Request to indicate scaffold storage racks

installed on the 216' elevation

3/8/2016

Procedures

CM-AA-SHK-101

Seismic Housekeeping

71111.19

Corrective Action

Documents

CR1131405

CR1134735

2-BD-TV-200A failed to open during slave relay testing

10/31/2019

CR1135883

2-SW-MOV-204A unsat stroke time

11/14/2019

Corrective Action

Documents

Resulting from

Inspection

CR1134657

NRC identified: TS 3.7.10 not entered during U1 RFO when

testing MCR dampers

10/30/2019

CR1135978

NRC inspection question regarding 0-MPM-0452-19

11/15/2019

Miscellaneous

2-DRP-02

Engineering Design Reference, Air Operated Valve

Setpoints

Procedures

0-ECM-0708-04

Removal, Bench Testing, and Installation of Woodward

Digital Reference Unit (DRU) in Emergency Diesel

Generator Electronic Governor Control System

0-ECM-0708-05

Woodward Digital Reference Unit (DRU) and 2301A Field

Adjustments

0-MPM-0452-19

Control Room HVAC Supply AODs (1-HV-AOD-161-1 and

2) Diaphragm Replacement and Spring Load Testing

MA-AA-103

Conduct of Troubleshooting

Work Orders

59101767326

2-BD-TV-200A Air Supply Regulator Replacement

  • Reactivity Management Related*

11/1/2019

59102666453

01-HV-AOD-161-1-DAMPOP, Replacement of damper

motor diaphragm and spring load test

9/17/2019

203139484

01-NI-CHA-N-35-INTCPM, Contingency Compensating

Voltage Adjustment

9/8/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

203277047

01-HV-AOD-161-2-Dampop, replace diaphragm in damper

motor and spring load test

9/17/2019

203298233

203301194

2-SW-MOV-204A-VALOP, Valvop/Limit switch

inspection/repair

11/14/2019

WO59102658574

WO59102658583

WO59102721737

71111.22

Procedures

1-LOG-12

Emergency Diesel Generator Log (Operating)

1-PT-14.2

Operations Periodic Test, Charging Pump 1-CH-P-1B

2-PT-82.2A

2H Diesel Generator Test (Simulated Loss of Off-Site

Power)

Work Orders

203291999

Charging Pump 1-CH-P-1B

11/12/2019

71151

Miscellaneous

NRC Mitigating Systems Performance Index (MSPI) Basis

Document, North Anna Power Station Units 1 and 2

71152

Corrective Action

Documents

CR1118006

2-FH-CRN-5 Gripper Air Solenoid Valve Failure

3/12/2019

CR1124894

WO needed to install tornado missile barrier at U1 MD AFW

pump house

6/11/2019

CR1124899

WO needed to install tornado missile barrier at U2 MD AFW

pump house

6/11/2019

CR1131405

1H EDG mechanical governor delayed response in

operation of the speed/load control switch

9/20/2019

CR1134627

New thermal overloads from stock failed

10/30/2019

CR1134711

New fan impellers from stock have no balancing

documentation

10/31/2019

CR1136192

New relief valve for 00-SA-RV-140-Valve failed seat integrity

test

11/18/2019

Corrective Action

Documents

Resulting from

Inspection

CR1130343

NRC Question: Containment Equipment Hatch Closure

Team

Operability

Evaluations

CA7621480

Unit 1 auxiliary feedwater pump house tornado missile

vulnerability

CA7621494

Unit 2 auxiliary feedwater pump house tornado missile

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

vulnerability

Procedures

0-MCM-1204-07

Emergency Installation of the Equipment Hatch

1-AP-11

Loss of RHR

1-OP-18.1

Operation of the Containment Personnel Air Lock

1-OP-18.3

Operation of the Unit 1 Containment Personnel Air Lock

While in Mode 5, Mode 6, or Defueled

GMP-GM-103

Establishing and Maintaining Containment Closure Team

During Unit Outage

MS-AA-TRD-1001 Supply Chain Management Material Quality Trending

MS-AA-WHS-132

Control of Shelf Life Material

MS-AA-WHS-133

In-Storage Maintenance of Items

OP-AA-102

Operability Determination

15