IR 05000338/2019004
| ML20038A126 | |
| Person / Time | |
|---|---|
| Site: | North Anna |
| Issue date: | 02/07/2020 |
| From: | Louis Mckown NRC/RGN-II/DRP/RPB4 |
| To: | Stoddard D Virginia Electric & Power Co (VEPCO) |
| References | |
| IR 2019004 | |
| Download: ML20038A126 (18) | |
Text
February 7, 2020
SUBJECT:
NORTH ANNA POWER STATION - INTEGRATED INSPECTION REPORT 05000338/2019004 AND 05000339/2019004
Dear Mr. Stoddard:
On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at North Anna Power Station. On January 8, 2020, the NRC inspectors discussed the results of this inspection with Ms. Lisa Hilbert and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Louis J. McKown, II, Chief (Acting)
Reactor Projects Branch 4 Division of Reactor Projects
Docket Nos. 05000338 and 05000339 License Nos. NPF-4 and NPF-7
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000338 and 05000339
License Numbers:
Report Numbers:
05000338/2019004 and 05000339/2019004
Enterprise Identifier: I-2019-004-0030
Licensee:
Virginia Electric & Power Co.
Facility:
North Anna Power Station
Location:
Mineral, VA
Inspection Dates:
October 01, 2019 to December 31, 2019
Inspectors:
P. Capehart, Senior Operations Engineer
G. Eatmon, Resident Inspector
M. Tobin, Senior Resident Inspector
Approved By:
Louis J. McKown, II, Chief (Acting)
Reactor Projects Branch 4
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at North Anna Power Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 began the inspection period at approximately 10 percent power for a power escalation following a planned refueling outage. On October 4th, 2019, Unit 1 achieved rated thermal power and remained at or near rated thermal power for the remainder of the inspection period.
Unit 2 operated at or near rated thermal power for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.04Q - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (2 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 1, Outside Recirc Spray and Casing Cooling, Train A and B on December 3, 2019
- (2) Unit 2, Outside Recirc Spray and Casing Cooling, Train A and B on December 13, 2019
71111.04S - Equipment Alignment
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 auxiliary feedwater system on November 26, 2019.
71111.05Q - Fire Protection
Quarterly Inspection (IP Section 03.01) (5 Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Unit 1 cable vault and tunnel on October 18, 2019
- (2) Unit 1 safety related battery rooms on October 18, 2019
- (3) Unit 2 safety related battery rooms on October 18, 2019
- (4) Unit 2 safeguards building on October 31, 2019
- (5) Unit 1 and Unit 2 aux building basement during hot-work and removed fire barriers on December 12, 2019
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
- (1) Unit 1 and Unit 2, charging pump cube A, B, and C on November 12, 2019
Inspection Activities - Underground Cables (IP Section 02.02c.) (1 Sample)
The inspectors evaluated cable submergence protection in:
- (1) Manholes 4MH03 and 4MH04 on November 29, 2019
71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance
Requalification Examination Results (IP Section 03.03) (1 Sample)
- (1) The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), Requalification Requirements, of the NRCs Operators Licenses. During the week of January 3 2020, the inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with Inspection Procedure (IP) 71111.11, Licensed Operator Requalification Program. These results were compared to the thresholds established in Section 3.02, Requalification Examination Results, of IP 71111.11.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the Control Room during a main feedwater swap complicated by a failed flow switch on October 29, 2019.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a rapid down power and low power feedwater operation training evolution on October 22, 2019 in the simulator.
71111.12 - Maintenance Effectiveness
Routine Maintenance Effectiveness Inspection (IP Section 02.01) (3 Samples)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
- (1) Unit 2 bearing cooling pumps on October 31, 2019
- (2) Unit 1 and Unit 2 Appendix R lighting on December 10, 2019
- (3) Unit 1 and Unit 2 Plant Computer System and Secure Plant Data Systems on December 16, 2019
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) Elevated risk due to Reserve Station Service Transformer 'B' being removed from service with degraded cabling to the Station Service Transformer 'B' on October 17, 2019
- (2) Unit 1 and Unit 2 elevated risk due to the service water header check valve to the Unit 2 charging pump 'C' being unavailable on November 5, 2019
- (3) Unit 1 in elevated risk due to the turbine driven auxiliary feedwater pump being unavailable on November 29, 2019
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 02.02) (5 Samples)
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) Safety related cable conduit with potential transient combustibles inside on October 17, 2019 (CR1133208)
(2)1NNSANH002 damaged cable shield and outer jacket on November 4, 2019 (CR1135004)
- (3) Main feedwater recirculation flow switch automatic action disabled due to failed flow switch on November 14, 2019 (CR1134482)
- (4) Unit 1 and Unit 2 diesel driven fire pump engine failure during annual testing on December 18, 2019 (CR1124204)
- (5) Unit 1 and Unit 2 potential vulnerability identified with control room envelope testing methodology on December 19, 2019 (CA7771875)
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Unit 1 and Unit 2 permanent storage of scaffolding racks in containment on 216' elevation on December 19, 2019
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the following post maintenance tests:
- (1) Unit 1 emergency diesel generator following replacement of the governor on October 15, 2019
- (2) Unit 1 Rod drop time testing prior to reactor startup, on October 16, 2019
- (3) Unit 1 intermediate range, N-35, failed during unit shutdown for planned refueling on October 22, 2019
- (4) Unit 1 and Unit 2 control room HVAC supply air operated damper diaphragm replacement and spring load testing on December 9, 2019
- (5) Unit 2 steam generator blow down trip valve, 2-BD-TV-200A, failed to open during testing on November 14, 2019
- (6) Unit 2 service water valve, 2-SW-MOV-204A, failed stroke time testing on November 15, 2019
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
- (1) Unit 2 'H' emergency diesel generator fast start on October 7, 2019
- (2) Unit 1 charging pump, 1-CH-P-1B, periodic test on November 12,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
MS06: Emergency AC Power Systems (IP Section 02.05)===
- (1) Unit 1 (October 2018-September 2019)
- (2) Unit 2 (October 2018-September 2019)
MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)
- (1) Unit 1 (October 2018-September 2019)
- (2) Unit 2 (October 2018-September 2019)
71152 - Problem Identification and Resolution
Semiannual Trend Review (IP Section 02.02) (1 Sample)
- (1) The inspectors reviewed the licensees corrective action program for potential adverse trends in supply chain management and adverse material condition of components issued from the warehouse for installation in the plant that might be indicative of a more significant safety issue.
Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Unit 1 and Unit 2 common cause failure of auxiliary feedwater pump discharge due to tornado missile reevaluation
- (2) Unit 1 and Unit 2 containment hatch closure requirements
INSPECTION RESULTS
Observation: Unit 1 and Unit 2 Common Cause Failure of Auxiliary Feedwater Pump Discharge due to Tornado Missile 71152 The inspectors conducted a detailed review of the licensees evaluation of Regulatory Issue Summary (RIS) 2015-06, Tornado Missile Protection with respect to a design basis tornado missile that could impact all three trains of auxiliary feedwater pump discharge pipe and results in a previously unidentified common cause failure scenario. The issue is documented for Unit 1 in CR1124894, with prompt operability determination CA7621480, and for Unit 2 in CR1124899, with prompt operability determination CA7621494. The 12-inch diameter design basis missile enters the auxiliary feedwater pump house through the vestibule, maintains the line-of-sight trajectory and orientation through the existing barriers, and strikes all three trains of auxiliary feedwater pump discharge pipe. The licensees UFSAR identifies that the auxiliary feedwater pumphouse is protected from tornado missiles. The acceptable design parameters for a tornado resistant structure are:
- A 2-foot-thick heavily reinforced concrete with rebar (from the licensees UFSAR)
- A 2-inch-thick steel plate (from Calculation CE-1856, Design Supplemental Missile Barrier for Aux. Feedwater Pump House, dated July 14, 2006)
For Unit 1, the licensees operability determination identifies the tornado missile would pass through 24 inches of non-reinforced concrete from the nearby structure and 1.2 inches of the metal equipment and support structures in the auxiliary feedwater pumphouse. For Unit 2, the licensees operability determination also relies on the metal equipment and support structures totaling over 2.5 inches of metal within the auxiliary feedwater pumphouse
Following Enforcement Guidance Memorandum 15-002, Enforcement Discretion for Tornado-Generated Missile Protection Noncompliance, the licensee reviewed RIS 2015-06, concluded that a technical specification controlled structure does not comply with the current licensing basis, performed an engineering evaluation to determine the structure is operable but non-conforming, and is addressing the non-complying condition through their corrective action program.
Observation: Containment Equipment Hatch Closure Requirements 71152 The inspectors conducted a detailed review of an NRC-identified issue in CR 1130343, initiated on September 8, 2019, regarding the uncertainty involved in how many personnel would be available to assist during a postulated required containment hatch closure.
During this inspection, the resident inspectors discovered that one of the emergency operating procedures that could require a hatch closure, 1-AP-11, Loss of RHR, Revision 34, required operators to announce a containment evacuation prior to directing the hatch closure team on station to close the hatch, which by procedure is required to be closed within the time to boil or within 45 minutes, whichever is lower. However, the residents discovered that when performing hatch closure drills, non-assigned personnel would assist the team in closing the hatch. Since an evacuation was ordered prior to a hatch closure order, the licensee and the resident inspectors agreed that the closure team should not rely on outside assistance. The licensee directed the hatch closure team to expect to do any future drill or actual required closure without assistance. The licensee enhanced their process to ensure that future drills would be more accurate to real scenarios. Additionally, based on the sites self-imposed standards and alternate source term documentation, there are no requirements related to how quickly the hatch must be secured, so there are no performance deficiencies associated with this inspection.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On January 8, 2020, the inspectors presented the integrated inspection results to Ms.
Lisa Hilbert and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.04Q Corrective Action
Documents
Resulting from
Inspection
CR1137882
Security Barrier Sheet Metal Touching Insulation for 2-RS-
TK-1 Unit 2 Casing Cooling Tank
2/13/2019
Drawings
11715-FM-074A
Flow/Valve Operating Numbers Diagram Feedwater System
Procedures
1-AR-J-B6
RS PP 2A or 2B Vibration
1-AR-J-B6
1-AR-J-G5
RS PP 1B Lockout or Auto Trip or Test
1-AR-J-G6
1-OP-7.5A
Valve Checkoff - Outside Recirculation Spray System
1-PT-71.12
AFW System Valve Position Verification
2-OP-7.5A
Valve Checkoff - Outside Recirculation Spray System
71111.05Q Calculations
NA-2011-0021
Evaluation of Permanently Stored Combustible Material
Corrective Action
Documents
Resulting from
Inspection
CR1133208
CR1134147
NRC identified issue: housekeeping issues in both units QS
and SFGDs pumphouses lower levels
CR1134150
NRC identified issue: Foreign material in cable trays above
2-RS-P-2A pump cube area
CR1137788
NRC questions about hot work in 1-CH-P-1B cubicle
2/12/2019
Fire Plans
1-FS-AB-1
Auxiliary Building (All Elevations) Fire Fighting Strategy Safe
Shutdown Equipment
2-FS-SG-1
Safeguards Area Safe Shutdown Equipment Unit 2
Procedures
0-FS-CT-1
Cable Tray Spreading and Battery Room 2-1, 1-1, 2-3, 1-3
0-PT-106.1C
Fire Protection - Simplex Fire Detectors - Outside
Containment - Channel Operational Test
1-FS-ESG-BR-1
Battery Rooms 1-2 and 1-4
003
2-FS-ESG-BR-1
Emergency Switchgear Battery Room 2-2-and 2-4
CM-AA-FPA-100
Fire Protection/Appendix R (Fire Safe Shutdown) Program
Work Orders
203270696
Fire Protection - Simplex Fire Detectors - Outside
Containment - Channel Operational Test
8/8/2019
Corrective Action
CA3054959
Document Previous Functionality of Charging Pumps
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Documents
Corrective Action
Documents
Resulting from
Inspection
CR1134073
01-FPM-DET-458-DETECT is hanging by its wires
CR1136811
CR1137661
Why is backflow preventer 1-DB-BFP-2 not included in 0-
GOP-3.9
2/10/2019
Drawings
11715-FB-9A/B/C
Arrangement: Auxiliary Building, Floor Drainage, Sheet 1/2/3
Engineering
Evaluations
ET-N-10-0014
Engineering Technical Evaluation: Development of Flooding
9/6/2013
Miscellaneous
Safety Evaluation Report for North Anna Power Station,
Units 1 and 2
2/1979
Fire Protection System Review for North Anna Power
Station, Units 1 & 2, Supplement 2
1/3/1978
Virginia Electric and Power Company
North Anna Power Station Unit 1 and 2
Response to Generic Letter 88-20 and Supplement 1
Individual Plant Examination (IPE) for Severe Accident
Vulnerabilities
2/14/1992
2-92-4036-028
North Anna Power Station Commitment Data Form, IPE
Required Procedure Modificaiton
5/2/1994
Procedures
0-GOP-3.9
Weekly Check of Charging Pumps
0-MCM-1302-01
Mechanical Corrective Maintenance, Moving Heavy Loads
and Concrete Floor/Wall Plugs in the Auxiliary Buidling
71111.11Q Corrective Action
Documents
CR1135251
NRC requested information on Ops Initial Narrative Log
Entry
11/6/2019
Miscellaneous
Simulator Exercise Guide, course #SEG-12H
Procedures
Conduct of Operations
Corrective Action
Documents
CA7441460
Perform MRule Functional Failure evaluation 02-ELT-
B0SB5-Battery found inoperable
11/19/2018
CA7475755
Perform MRule Functional Failure evaluation Transformer
found not working
2/26/2018
CA7476603
Perform MRule Functional Failure evaluation 1-ELT-B-HP6
not working
2/27/2018
CA7476926
Perform MRule Functional Failure evaluation Emergency
2/27/2018
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
light found inoperable
CA7476928
Perform MRule Functional Failure evaluation 01-ELT-B-
AB13 found inoperable
2/29/2018
CA7476929
Perform MRule Functional Failure evaluation 01-ELT-B-
AB14 found inoperable
2/29/2018
CA7515388
Perform MRule Functional Failure evaluation 2-ELT-ELT-
MS12A not working
2/18/2019
CA7565438
CA7569001
Perform MRule Functional Failure evaluation 02-ELT-B-
AB20 not working
4/11/2019
CA7569002
Perform MRule Function Failure evaluation 01-ELT-B-AB13
4/11/2019
CA7569003
Perform MRule Functional Failure evaluation 01-ELT-B-
AB14 Not Working
4/11/2019
CA7569007
Perform MRule Functional Failure evaluation 01-ELT-B-HP3
4/11/2019
CA7578289
Perform MRule Function Failure evaluation for Appendix R
lantern found non-function during rounds
4/20/2019
CA7586469
Perform MRule Functional Failure evaluation Unit 2 Main
Steam Emergency Lighting Fixture Light Head
4/28/2019
CA7605957
Perform MRule Functional Failure evaluation for 01-ELT-B-
EG7-Battery failed 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> discharge test
5/15/2019
CA7644196
Perform MRule Functional Failure evaluation on 01-ELT-B-
TB5 lamps not lit
07/16/2019
CA7644207
Perform MRule Functional Failure evaluation 01-ELT-B-
AB23 lamps not lit
7/16/2019
CA7644936
Perform MRule Functional Failure evaluation 01-ELT-B-TB6
lights do not remain lit throughout 8hr discharge
7/17/2019
CA7671970
01-ELT-B-MS4-Battery
8/27/2019
CA7685370
CA7700741
2-ELT-B-AB7-Battery
10/1/2019
CA7700742
2-ELT-B-AB22-Battery
10/1/2019
CA7701647
01-ELT-ELT-CR4A-Light
09/30/2019
CA7701651
01-ELT-B-SW7-Battery
10/02/2019
CA7701655
2-ELT-B-SB7-Battery
10/2/2019
CR1120021
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CR1120153
CR1124240
CR1126295
CR1127232
CR1132184
EPM/ELT - Appendix R (M1) Unit 1 & 2
9/30/2019
CR1132401
CR1133828
Corrective Action
Documents
Resulting from
Inspection
CR1138186
VPAP-2606, "Safety Parameter Display System (SPDS)"
admin procedure found to contain deficiencies
Miscellaneous
MRule Tracking Group Basis Document for ELT02
MRule Tracking Group Basis Document ELT03
MRule (a)(1) Action Plan & (a)(1) Evaluation for 01-ELT-B-
MS4-Battery
10/02/2019
MRule System Basis Document for Emergency Lighting
Procedures
0-EMP-2808-01
Appendix R Emergency Light Inspection and Testing of Fire
Areas 2 (Control Room), 3-1 (U1 Cable Vault and Tunnel),
3-2 (U2 Cable Vault and Tunnel), 50 (Service Bldg
Stairwell), 5-1 (Unit 1 Normal Switchgear Room) and 5-2
(Unit 2 Normal Switchgear Room)
0-EMP-2808-03
Appendix R Emergency Light Inspection and Testing of Fire
Area 8 (Unit 1 and Unit 2 Turbine Bldg)
0-EPM-2808-05
Appendix R Emergency Light Inspection and Testing of Fire
Area 11 (Unit 1 and 2 Aux Bldg. and Fuel Bldg.)
0-EPM-2808-09
Inspection and Testing of Appendix R Emergency Light
Chargers
2-AP-42.1
Loss of Unit 2 Plant Computer System (PCS)
VPAP-2606
Safety Parameter Display System (SPDS)
VPAP-2802
Notifications and Reports
Corrective Action
Documents
CR1134379
CR1134480
Corrective Action
Documents
CR1134443
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Resulting from
Inspection
Drawings
Figure 13.3-NA
Service Water System Diagram
04/19/07
Work Orders
Calculations
ET-CEP-09-0010
Evaluation of Compensatory Measures for Aluminum
Conduit Penetration Issues
ET-CEP-10-0006
Evaluation of Aluminum Conduit Seal Penetration Fire Tests
ET-N-10-0031
Evaluation of Aluminum Conduit Fire Penetrations
Corrective Action
Documents
CA7616237
CR1124204
CR1132231
CR1132259
CR1132332
CR1134482
CR1135934
Potential Vulnerability Identified with Control Room
Envelope Testing Methodology
11/14/2019
CR373123
CR395741
Corrective Action
Documents
Resulting from
Inspection
1133208
CR1134657
NRC identified: question concerning TS 3.7.10 during
damper testing
10/30/2019
Operability
Evaluations
CA7771875
Prompt Operability Determination for potential vulnerability
in the control room envelope testing methodology for supply
and exhaust dampers (1-HV-AOD-160-1/2 and 1-HV-AOD-
161-1/2)
11/21/2019
Procedures
0=PT-101.2
Warehouse 5 Fire Protection Pumps Annual Test
1-OP-2.1
Control of Feed Water Recircs During Power Ascension
106
ER-NA-CRH-100
Main Control Room/Emergency Switchgear Room
(MCR/ESGR) Envelope Habitability Program
Status and Configuration Control
Alternate Plant Configuration Sheet
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Work Orders
Drawings
1500013-1-S-102
Scaffold Storage Box for Safway Scaffold Part SHR7
1500013-1-S-105
Scaffold Storage Box for Safway Scaffold Part SVP 3,7 & 10
Engineering
Changes
NA-15-00013
Scaffold Storage Rack for Unit 1 Containment 216' elevation
3/2/2016
NA-15-00014
Scaffold Storage Rack for Unit 2 Containment 216' Elevation
8/27/2015
Miscellaneous
NAPS-UCR-2015-
013
SAR Change Request to indicate scaffold storage racks
installed on the 216' elevation
3/8/2016
Procedures
CM-AA-SHK-101
Seismic Housekeeping
Corrective Action
Documents
CR1131405
CR1134735
2-BD-TV-200A failed to open during slave relay testing
10/31/2019
CR1135883
2-SW-MOV-204A unsat stroke time
11/14/2019
Corrective Action
Documents
Resulting from
Inspection
CR1134657
NRC identified: TS 3.7.10 not entered during U1 RFO when
10/30/2019
CR1135978
NRC inspection question regarding 0-MPM-0452-19
11/15/2019
Miscellaneous
2-DRP-02
Engineering Design Reference, Air Operated Valve
Setpoints
Procedures
0-ECM-0708-04
Removal, Bench Testing, and Installation of Woodward
Digital Reference Unit (DRU) in Emergency Diesel
Generator Electronic Governor Control System
0-ECM-0708-05
Woodward Digital Reference Unit (DRU) and 2301A Field
Adjustments
0-MPM-0452-19
Control Room HVAC Supply AODs (1-HV-AOD-161-1 and
2) Diaphragm Replacement and Spring Load Testing
Conduct of Troubleshooting
Work Orders
59101767326
2-BD-TV-200A Air Supply Regulator Replacement
- Reactivity Management Related*
11/1/2019
59102666453
01-HV-AOD-161-1-DAMPOP, Replacement of damper
motor diaphragm and spring load test
9/17/2019
203139484
01-NI-CHA-N-35-INTCPM, Contingency Compensating
Voltage Adjustment
9/8/2019
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
203277047
01-HV-AOD-161-2-Dampop, replace diaphragm in damper
motor and spring load test
9/17/2019
203298233
203301194
2-SW-MOV-204A-VALOP, Valvop/Limit switch
inspection/repair
11/14/2019
Procedures
1-LOG-12
Emergency Diesel Generator Log (Operating)
1-PT-14.2
Operations Periodic Test, Charging Pump 1-CH-P-1B
2-PT-82.2A
2H Diesel Generator Test (Simulated Loss of Off-Site
Power)
Work Orders
203291999
Charging Pump 1-CH-P-1B
11/12/2019
71151
Miscellaneous
NRC Mitigating Systems Performance Index (MSPI) Basis
Document, North Anna Power Station Units 1 and 2
Corrective Action
Documents
CR1118006
2-FH-CRN-5 Gripper Air Solenoid Valve Failure
3/12/2019
CR1124894
WO needed to install tornado missile barrier at U1 MD AFW
pump house
6/11/2019
CR1124899
WO needed to install tornado missile barrier at U2 MD AFW
pump house
6/11/2019
CR1131405
1H EDG mechanical governor delayed response in
operation of the speed/load control switch
9/20/2019
CR1134627
New thermal overloads from stock failed
10/30/2019
CR1134711
New fan impellers from stock have no balancing
documentation
10/31/2019
CR1136192
New relief valve for 00-SA-RV-140-Valve failed seat integrity
test
11/18/2019
Corrective Action
Documents
Resulting from
Inspection
CR1130343
NRC Question: Containment Equipment Hatch Closure
Team
Operability
Evaluations
CA7621480
Unit 1 auxiliary feedwater pump house tornado missile
vulnerability
CA7621494
Unit 2 auxiliary feedwater pump house tornado missile
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
vulnerability
Procedures
0-MCM-1204-07
Emergency Installation of the Equipment Hatch
1-AP-11
Loss of RHR
1-OP-18.1
Operation of the Containment Personnel Air Lock
1-OP-18.3
Operation of the Unit 1 Containment Personnel Air Lock
While in Mode 5, Mode 6, or Defueled
GMP-GM-103
Establishing and Maintaining Containment Closure Team
During Unit Outage
MS-AA-TRD-1001 Supply Chain Management Material Quality Trending
MS-AA-WHS-132
Control of Shelf Life Material
MS-AA-WHS-133
In-Storage Maintenance of Items
15