IR 05000338/2019003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000338/2019003 and 05000339/2019003
ML19318D724
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 11/13/2019
From: Bradley Davis
Division Reactor Projects II
To: Stoddard D
Virginia Electric & Power Co (VEPCO)
Geanette D
References
IR 2019003
Download: ML19318D724 (24)


Text

November 13, 2019

SUBJECT:

NORTH ANNA POWER STATION - INTEGRATED INSPECTION REPORT 05000338/2019003 AND 05000339/2019003

Dear Mr. Stoddard:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at North Anna Power Station. On October 9, 2019, the NRC inspectors discussed the results of this inspection with Ms. Lisa Hilbert, Plant Manager and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Bradley J. Davis, Chief Reactor Projects Branch 4 Division of Reactor Projects

Docket Nos. 05000338 and 05000339 License Nos. NPF-4 and NPF-7

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000338 and 05000339

License Numbers:

NPF-4 and NPF-7

Report Numbers:

05000338/2019003 and 05000339/2019003

Enterprise Identifier:

I-2019-003-0029

Licensee:

Virginia Electric & Power Co.

Facility:

North Anna Power Station

Location:

Mineral, VA

Inspection Dates:

July 1, 2019 to September 30, 2019

Inspectors:

B. Collins, Reactor Inspector

J. Diaz-Velez, Senior Health Physicist

G. Eatmon, Resident Inspector

R. Kellner, Senior Health Physicist

W. Pursley, Health Physicist

M. Tobin, Senior Resident Inspector

Approved By:

Bradley J. Davis, Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at North Anna Power Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000338,05000339/20 19010-03 Potential 50.9 Violation for Incomplete Information Submittal 71111.21N Closed LER 05000339/2019-001-00 LER 2019-001-00 for North Anna Unit 2, Manual Reactor Trip on Degrading Condenser Vacuum due to a Failed Weld.

71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On September 7, the unit was down powered for a planned refueling outage. The unit remained shut down for the remainder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Summer Readiness Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems on July 30, 2019.

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 train "J" electrical lineup during the 3-year overhaul of the "H" diesel on July 13, 2019
(2) Unit 1 Low Head Safety Injection (LHSI) System train B on August 23, 2019.
(3) Unit 1 primary grade water flow path isolation secured closed in Mode 3, 4, 5, and 6 on September 28, 2019

71111.04S - Equipment Alignment

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 High Head Safety Injection system train B on July 29, 2019.

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1 motor driven auxiliary feedwater pump house and turbine driven auxiliary feedwater pump house on August 14, 2019
(2) Unit 1 and Unit 2 service water pump house on August 20, 2019
(3) Unit 1 and Unit 2 Auxiliary building (all elevations) on September 24, 2019
(4) Unit 1 Containment building (all elevations) on September 24, 2019
(5) Unit 1 and Unit 2 Emergency Diesel Generator pump rooms on September 25, 2019

71111.07A - Heat Sink Performance

Annual Review (IP Section 02.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Unit 1, main control room cooler condenser, 1-HV-E-4B-2, and Unit 2, main control room cooler condenser, 2-HV-E-4B-2, on September 18, 2019.

71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01)

(1) The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from September 16 - 20, 2019:
(1) Ultrasonic Examination (UT)a. 31" reactor coolant pipe-to-elbow weld (11715-WMKS-1019E-1/31-RC-2/SW-17), ASME Class 1 (reviewed)b. 14" reactor coolant valve-to-pipe weld (11715-WMKS-0110B-2/4-RC-14/9),

ASME Class 1 (reviewed)

(2) Radiographic Examination (RT)a. 8" chemical and volume control system pipe-to-valve and valve-to-pipe welds (1-CH-MOV-1115B-VALVE-1,-2), ASME Class 2, WO59203140221 (weld sample; reviewed)
(3) Liquid Penetrant Examination (PT)a. 8" chemical and volume control system pipe-to-valve and valve-to-pipe welds (1-CH-MOV-1115B-VALVE-1,-2), ASME Class 2, WO59203140221 (weld sample; reviewed)b. 14" reactor coolant valve-to-pipe weld (11715-WMKS-0110B-2/4-RC-14/9),

ASME Class 1 (reviewed)

(4) Visual Examination (VT)a. bottom-mounted reactor vessel instrumentation, ASME Class 1 (reviewed)

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during Unit 1 transition from approximately 80% power to Mode 3 on September 7 and 8, 2019.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the operators in the simulator during an emergency preparedness requal drill on July 16, 2019.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Unit 1 and Unit 2 emergency diesel generators on August 21, 2019
(2) Review of Unit 1 and Unit 2 (a)(3) periodic evaluation on September 16, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Units 1 and 2 at elevated risk due to a PJM hot weather alert on July 22, 2019
(2) Unit 1 emergent work control for loss of Vital Bus 1-III on August 10, 2019
(3) Unit 2 packing adjustment for steam leak on 'A' main feedwater regulating valve with work order, WO 59203296739
(4) Unit 1 heavy lift for the reactor head on September 12, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (5 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Units 1 and 2 instrument air safety related accumulators on July 22, 2019
(2) Units 1 and 2 service water operability due to seismic concerns with staged equipment in the service water pump house on July 19, 2019
(3) Unit 1, low head safety injection 'A' main discharge snubber with low oil on September 5, 2019
(4) Unit 2, OD7651286, "Pressure readings on one of the nitrogen reserve tanks show a leak in the system which challenges the operability of the associated pressurizer power operated relief valve" on September 9, 2019
(5) Units 1 and 2 emergency diesel generators during extreme hot weather on September 20, 2019

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (3 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1 and Unit 2 reactor containment polar crane safety classification downgrade (ETE-NA-2019-0005)
(2) Lowering fuel assembly 51N to seated position in spent fuel pool location using temporary rigging on August 21, 2019
(3) Unit 1 and Unit 2 emergency diesel generator surveillance test interval evaluation from monthly to quarterly (STI-N12-2017-003)

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post maintenance tests:

(1) Unit 1, Quench Spray Pump 'A' after planned maintenance, on July 10, 2019
(2) Unit 1, ventilation damper 1-HV-AOV-228-2 after replacement of the Part-21 required change out of the Hytork actuator on August 19, 2019
(3) Unit 1, component cooling supply check valve to residual heat removal heat exchanger unplanned maintenance due to PT failures, WO59203279199
(4) Unit 1, Service water return header from the recirc spray heat exchangers motor operated valve (MOV) 1-SW-MOV-105C following planned maintenance on September 27, 2019

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1)

(Partial) The inspectors evaluated 1R27 activities from September 8, 2019 to September 30, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Unit 1 quench spray pump 'A' pressure test, on July 24, 2019 (2)1-PT-48, Unit 1 Mode 5 walkdown on September 8, 2019 (3)1-PT-138, Unit 1 LHSI system functional verification on September 24, 2019

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Units 1 and 2 service water pump flow surveillance test re-baselining on September 30, 2019

Containment Isolation Valve Testing (IP Section 03.01) (2 Samples)

(1)1-PT-61.3, service water to and from the recirc spray heat exchanger 'D' on September 25, 2019 (2)1-HV-MOV-100A, Containment Purge valve on September 26, 2019

FLEX Testing (IP Section 03.02) (1 Sample)

(1) Units 1 and 2 beyond design basis flooding barrier yearly equipment testing on July 16, 2019

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Emergency preparedness drill on July 16,

RADIATION SAFETY

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walk Downs and Observations (IP Section 02.01) (1 Sample)

The inspectors walked down gaseous and liquid radioactive effluent monitoring and filtered ventilation systems to assess the material condition and verify proper alignment according to plant design.

(1) Systems included the following:

Gaseous or Liquid Radioactive Effluent Monitoring Systems

  • Process Vent Normal & High Range Effluent Monitor (GW-RM-178)
  • Vent Stack A Normal & High Range Effluent Monitor (VG-RM-179)
  • Liquid Waste Clarifier Radiation Monitor (RM-LW-111)

Filtered Ventilation Systems

  • Unit 1 and 2 Containment Purge Exhaust Ventilation System
  • Unit 1 and 2 Auxiliary Building General Exhaust Ventilation System
  • Unit 1 and 2 Auxiliary Building Central Exhaust Ventilation System
  • Unit 1 and 2 Safeguards Exhaust Ventilation System
  • Fuel Building Exhaust Ventilation System

Calibration and Testing Program (Process & Effluent Monitors) (IP Section 02.02) (1 Sample)

The inspectors reviewed the following gaseous and liquid effluent monitor instrument calibrations and tests:

(1) Systems included the following:

Process Vent Normal & High Range Effluent Monitor Work Order (WO) # 59102886914 - 0-PT-44.2.4 WO # 59103065651 - 0-PT-44.2.4 WO # 59103065651 - 0-PT-44.2.48 WO # 59102985571 - 0-PT-44.2.52

Vent Stack A Normal & High Range Effluent Monitor WO # 59102882205 - 0-PT-44.2.50 WO # 59103051507 - 0-PT-44.2.50

Vent Stack B Normal & High Range Effluent Monitor WO # 59102756143 - 0-PT-44.2.5 WO # 59102985571 - 0-PT-44.2.5

Sampling and Analysis (IP Section 02.03) (1 Sample)

The inspectors reviewed the following:

(1) Radioactive Effluent Sampling and Analysis Activities
  • Observed sampling of U-1 and U-2 High Capacity (S/G) Blowdown
  • Observed Process Vent (Main Stack) Gaseous Sampling
  • Observed Vent Vent A Particulate, Iodine, and Noble Gas Sampling
  • Observed Vent Vent B Particulate, Iodine, and Noble Gas Sampling

Effluent Discharges

  • No batch effluent discharges were available for review during the inspection. Open continuous release permits were reviewed.

Instrumentation and Equipment (IP Section 02.04) (1 Sample)

The inspectors reviewed the following radioactive effluent discharge system surveillance test results:

(1) ECCS PREACS WO # 59203269622 - 0-PT-77.4A (1-HV-FL-3A) Charcoal Efficiency WO # 59102939905 - 0-PT-77.4B (1-HV-FL-3B) Charcoal Efficiency WO # 59103005349 - 0-PT-77.14A (1-HV-FL-3A) HEPA-Charcoal In-Place Test WO # 59103062602 - 0-PT-77.14B (1-HV-FL-3B) HEPA-Charcoal In-Place Test

Unit 1 Containment Radio Gas Radiation Monitor WO # 59102803829 - 1-PT-38.2.1.20 WO # 59102986302 - 1-PT-38.2.1.20

Liquid Waste Clarifier Radiation Monitor WO # 59102897494 - 1-PT-38.2.2 WO # 59103108509 - 1-PT-38.2.2 WO # 59103069394 - 0-ICP-LW-RM-110

Dose Calculations (IP Section 02.05) (1 Sample)

The inspectors reviewed the following to assess public dose:

(1) Liquid and Gaseous Discharge Permits
  • Unit 1 Condenser Air Ejector Gas Permit # G-20190801-278-C
  • Unit 2 Condenser Air Ejector Gas Permit # G-20190801-279-C
  • Clarifier Continuous Liquid Permit # L-20190728-068-C

Annual Radiological Effluent Release Reports (ARERR)

Abnormal Gaseous or Liquid Tank Discharges

  • No abnormal gaseous or liquid effluent discharges were available for review during this inspection

71124.07 - Radiological Environmental Monitoring Program

Inspectors evaluated licensee performance in ensuring REMP is implemented in accordance with licensing documentation and REMP is validating doses are within the legal dose limits. Inspectors also reviewed the licensees effort to continue to implement the NEI/Industry Groundwater Protection Initiative.

Site Inspection (IP Section 02.01) (1 Sample)

The inspectors performed walkdowns of sampling stations, thermoluminescent locations and meteorological instrumentation. Inspectors also performed observations of preparation and collections of different environmental sample types. Inspectors reviewed sampling results and maintenance, calibration, quality control and ground water records.

(1) Records reviewed, and samples observed included but were not limited to the following:

Walkdowns, Calibrations, and Maintenance Record Review

  • Environmental Air Sample Kit #1, Station 5A, 10/09/2018
  • Environmental Air Sample Kit #4, Station 1, 10/09/2018
  • Environmental Air Sample Kit #8, Station 8, 10/09/2018
  • Environmental Air Sample Kit #11, Station 3, 10/09/2018

Environmental Sample Collections and Preparation Observation

  • Environmental Air Sample Kits #1, Kit #4, Kit #8, Kit #11, particulate and charcoal air sample preparation for shipment to environmental lab

Licensee Actions in Response to Missed Sample, Inoperable Sampler, Lost TLD or Anomalous Measurement

  • Condition Report CR1081346 - Monthly Milk Sample not Available
  • Condition Report CR1084829 - Quarterly TLDs Missing
  • Condition Report CR1111079 - GWP Well #3 showed elevated tritium

Sampling Program for the Potential of Licensed Material Entering Groundwater

  • Unit 2 Reactor Water Storage Tank
  • Unit 1 Reactor Water Storage Tank
  • Unit 1 & 2 Circulating Water Discharge Tunnels

Groundwater Protection Initiative (GPI) Implementation (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees continuing implementation of the voluntary NEI/Ground Water Protection Initiative.

71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,

and Transportation

Radioactive Material Storage (IP Section 02.01)

The inspectors evaluated radioactive material storage areas for compliance with postings, labels, radiological controls and physical controls during plant walk downs. Inspectors also evaluated the material condition of observed containers of radioactive materials for signs of degradation.

(1) Walkdown of radioactive material storage areas included the following:
  • Warehouses 5 and 9
  • Generator Rewind Building
  • Outside Yard
  • Auxiliary Building including the Solid Waste area

Radioactive Waste System Walkdown (IP Section 02.02) (1 Sample)

The inspectors evaluated liquid and solid radioactive waste processing systems and processes during plant walkdowns for alignment with licensing descriptions, material condition, administrative and physical controls. Inspectors also evaluated changes to the systems, waste stream mixing methodologies and process control program descriptions.

(1) Radioactive Waste Resin and/or Sludge Discharges Processes
  • Advanced Liquid Processing System (ALPS)
  • Low-Level Liquid Waste Subsystem
  • Spent Resin Dewatering Tank

Waste Characterization and Classification (IP Section 02.03) (1 Sample)

The inspectors evaluated radioactive waste stream characterization and classification.

(1) Radioactive waste streams:
  • ALPS Charcoal (11/2016)
  • 1-RP-FL-2 BARS (4/25/2017)
  • 2-CH-I-1B (6/28/17)
  • 1-RL-FL-1A (8/17)
  • Common DAW (8/17)
  • 1-LW-TK-1 Resin
  • 2-CH-I-1A (10/17)
  • 1-LW-TK-1 Resin
  • 1-CH-I-2 (4/13/18)
  • 1-RP-FL-1B Smear
  • 2-CH-I-1B Resin
  • ALPS Charcoal (4/19)

Shipment Preparation (IP Section 02.04) (1 Sample)

The inspectors evaluated and observed the radioactive material shipment preparation process.

(1) Shipment Number:
  • 19-1051

Shipping Records (IP Section 02.05) (1 Sample)

The inspectors evaluated the following non-excepted package shipment records:

(1) Shipment Numbers:
  • 17-DUR-08
  • 18-BCO-06,
  • 18-BCO-10
  • 17-ERS-01
  • 19-BCO-04
  • 19-BCO-05

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - June 30, 2019)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - June 30, 2019)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (July 1, 2018 - June 30, 2019)
(2) Unit 2 (July 1, 2018 - June 30, 2019)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample.

(IP Section 02.16) (1 Sample)

The inspectors verified licensee performance indicators submittals for the period:

(1) January 31, 2018 - July 31, 2019

71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000339/2019-001-00, Manual Reactor Trip on Degrading Condenser Vacuum due to a Failed Weld (ADAMS accession: ML19123A099). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors also concluded that no violation of NRC requirements occurred.

INSPECTION RESULTS

Unresolved Item (Closed)

Potential 50.9 Violation for Incomplete Information Submittal URI 05000338,05000339/2019010-03 71111.21N

Description:

During the 2019 Design Bases Assurance Inspection (EQ Program) inspection, the team identified a URI associated with a proposed technical specification change the licensee had submitted on June 22, 2000, wherein the licensee omitted information potentially material to the NRCs review. Specifically, the URI was established to allow the NRC to determine whether the issue was material in accordance with the NRC Enforcement Policy (ADAMS ML19123A129), Section 2.3.11, Inaccurate and Incomplete Information, and the NRC Enforcement Manual (ADAMS ML18018B134), Part II, Section 1.5, Material False Statements and Completeness and Accuracy of Information.

After review by staff in the Office of Nuclear Reactor Regulation (NRR), the NRC determined that the information which was omitted was not material to the decision-making process for the proposed technical specification change and is therefore not a violation of 10 CFR 50.9.

Corrective Action Reference(s): CR1123701

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 9, 2019, the inspectors presented the integrated inspection results to Ms.

Lisa Hilbert, Plant Manager and other members of the licensee staff.

  • On September 19, 2019, the inspectors presented the North Anna Unit 1 ISI Debrief inspection results to Larry Lane, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04Q Corrective Action

Documents

ACE000342

ACE to Engineering for unplanned inoperability of 1-SI-P-1B

to add oil

3/19/2007

CR1086669

1-SI-P-1B leaking oil

2/27/2017

Drawings

11715-FE-1D

4160V One Line Diagram - Sheet 3, Emergency Bus 1H

and 1J

1175-FE-1BB

One Line Diagram Electrical Distribution System

Engineering

Evaluations

ER-AP-BAC-101

BACCP Evaluation Screening

Miscellaneous

Engineering log of oil addition vs. leakage for mission time

of 1-SI-P-1B

2/28/2018

North Anna Power Station Lubrication Manual for low head

safety injection pump motor, and bearings

Procedures

0-GOP-4.34

Administrative Lock List

1-OP-1.4

Unit Startup from Mode 4 to Mode 3

1-OP-4A

Mode Change Checklist Mode 5 to Mode 6 or defueled to

Mode 6

1-OP-7.1A

Valve Checkoff - Low Head Safety Injection System

1-OP-8.1A

Valve Checkoff - Chemical and Volume Control System

Auxiliary Building

CM-NA-STI-101

Technical Specification Surveillance Test Interval (STI) List

Work Orders

WO59203131674

Refueling Water Storage Tank Level Channel III (1-QS-L-

100A) Calibration

6/17/2019

71111.04S

Corrective Action

Documents

CR1094210

Air Void found during 1-PT-14.5

4/8/2019

Miscellaneous

Large AC Motors - Life-line D Horizontal Induction Motor,

Frames 5000, 5800, 6800, Drip proof, Weather Protected,

Type I Sleeve or Rolling Bearings

1/25/2013

1-CH-P-1B

North Anna Power Station Lube Oil Manual for charging

pump motor, gear reducer, and bearings

10/21/2008

Procedures

1-OP-7.2A

Valve Checkoff - High Head Safety Injection System

1-PT-138.1

HHSI Flow Balance

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CM-NA-STI-101

Technical Specification Surveillance Test Interval List

Work Orders

203277804

Venting ECCS Lines

3/27/2019

WO59103025464

Combined Charging Pump "1A" Head Curve Verification

and HHSI Branch Flow Verification Using Smart

Transmitters

4/18/2018

71111.05Q Corrective Action

Documents

Resulting from

Inspection

CR1128815

Smoke Detector in U1 TDAFW room is hanging by the wires 8/13/2019

CR1129074

Unit 1 Aux. Feedwater fire strategy

8/16/2019

Fire Plans

North Anna Power Station Appendix R Report

1-FS-AF-1

Safe Shutdown Equipment Auxiliary Feedwater Pumphouse

1-FS-SW-1

Service Water Pumphouse Units 1 and 2

Miscellaneous

Summary for 1-FP-1315 Valve Cycle

7/6/2019

71111.07A

NDE Reports

Eddy Current Inspection of Control Room Chiller Tube

Bundle 1-HV-E-4B-2 (condenser bundle)

6/9/2015

Eddy Current Inspection of Control Room Chiller Bundle 2-

HV-E-4B-2 (condenser bundle)

5/12/2016

Procedures

ER-AA-HTX-1002

Heat Exchanger Program Visual and Leak Testing

Work Orders

WO59102439016

Heat Exchanger Visual Inspection Form - Tubeside (1-HV-

E-4B-2)

6/10/2015

71111.08P

Corrective Action

Documents

CR1117235

Excessive Boric Acid Leak on 2-RC-HCV-2544

03/04/2019

CR1117434

Discolored Boric Acid Found on 1-RC-MOV-2592

03/06/2019

CR1117772

Discolored Boric Acid Found on Body-to-Bonnet Connection

of 2-CH-FCV-2160

03/09/2019

Corrective Action

Documents

Resulting from

Inspection

CR1131188

Neutron Shield Tank Cooling Pump 1-NS-P-1A Packing

Leak

09/18/2019

CR1131224

Presence of Oil Noted on NRC Walkdown of Containment

09/18/2019

CR1131366

NRC Observation for Weld Traveler Documentation

09/19/2019

Engineering

Changes

RCN59203140221

Record Change Notice for Work Order 59203140221

Rev. 0

Engineering

Evaluations

ETE-NA-2018-

0003

North Anna Unit 1 Spring 2018 Steam Generator Condition

Monitoring and Operational Assessment

Rev. 0

ETE-NA-2019-

North Anna Unit 1 5th Interval Risk-Informed Inservice

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0007

Inspection Program, N-716-1 Conversion

ETE-NA-2019-

0033

North Anna Unit 1 - Steam Generator Degradation

Assessment and Inspection Interval Review - September

2019 Refueling Outage (N1R27)

Rev. 0

Miscellaneous

Curtiss-Wright Personnel Certification Statement: UT-LII

(Fuechtmann)

07/27/2019

Curtiss-Wright Personnel Certification Statement: UT-LII

(Fuechtmann)

07/27/2019

Curtiss-Wright Certification of Visual Acuity and Color Vision

(Fuechtmann)

8/7/19

Curtiss-Wright Personnel Certification Statement: UT-LII

(Sauter)

08/16/2019

Curtiss-Wright Certification of Visual Acuity and Color Vision

(Sauter)

8-15-19

Industrial Testing Services, LLC Certificate of Qualification

and Certification Summary: PT-LII (Flood)

2/22/2019

ITLS Vision Acuity Certification (Flood)

2/22/2019

Applied Technical Systems, Incorporated Nuclear

Construction Qualification and Certification of

Nondestructive Inspection Personnel: Radiography

(Lubinski)

March 3,

2017

Curtiss-Wright Certification of Visual Acuity and Color Vision

(Zollner)

7/24/19

Curtiss-Wright Personnel Certification Statement: UT-LII

(Zollner)

07/27/2019

Applied Technical Systems, Incorporated Vision Acuity

Examination (Lubinski)

01/08/2018

214

C-T Manufacturing Revised Certificate of Test-Mill Products:

UT Calibration Block VGB-33

December

11, 1991

677388

Equipment Specification: Reactor Coolant Centrifugally Cast

Pipe to ANSI B31.7 Class I

Rev. 0

801

Weld Procedure Specification

Rev. 8

830

Procedure Qualification Record

7/20/01

831

Procedure Qualification Record

7/20/01

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

JH-2438

Welder Performance Qualification: Manual GTAW P1 to P1

04/15/2011

JH-2632

Welder Performance Qualification: Manual GTAW P1 to P1

03/01/2010

TM-5756

Welder Performance Qualification: Manual GTAW P1 to P1

04/16/2006

NDE Reports

1-PT-48.4

Bare Metal Inspection of Vessel BMI Nozzles

09.08.19

PT-19-028

Liquid Penetrant Examination (11715-WMKS-0110B-2/4-

RC-14/9)

9/13/2019

UT-19-082

UT Calibration/Examination Record (11715-SMKS-0103N/6-

RC-17/SW-23)

9/10/2019

UT-19-085

UT Calibration/Examination Record (11715-WMKS-0109E-

1/31-RC-2/SW-17)

9/11/2019

UT-19-100

UT Calibration/Examination Record (11715-WMKS-0110B-

2/4-RC-14/9)

9/13/2019

Procedures

0-MCM-1801-01

Welding Safety-Related and Seismic-Related Equipment

Rev. 28

1-PT-48.3

Visual Inspection Borated Systems in Containment

Rev. 6

1-PT-48.4

Bare Metal Inspection of Vessel BMI Nozzles

Rev. 8

CM-AA-NWP-101

Control of Welding

Rev. 2

CM-AA-NWP-102

Control of Welding Materials

Rev. 2

ER-AA-NDE-PT-

301

Balance-of-Plant Liquid Penetrant Examination Procedure

Rev. 7

ER-AA-NDE-RT-

400

Radiographic Examination Procedure

Rev. 1

ER-AA-NDE-UT-

700

Ultrasonic Examination of Cast Stainless Steel Piping Welds Rev. 1

ER-AA-NDE-UT-

2

Ultrasonic Examination of Austenitic Piping Welds in

accordance with ASME Section XI, Appendix VIII

Rev. 7

ER-AP-BAC-10

Boric Acid Corrosion Control Program

Rev. 13

ER-AP-BAC-101

Boric Acid Corrosion Control Program (BACCP) Inspections

Rev. 12

MA-AA-102

Foreign Material Exclusion

Rev. 23

Work Orders

WO59203140221

Replace 1-CH-MOV-1115B-VALVE

Rev. 0

71111.11Q Procedures

1-OP-3.7

Unit Shutdown from Mode 1 to Mode 5 for Refueling

71111.12

Corrective Action

Documents

CR1124035

CR1124035

71111.13

Corrective Action

CR1128672

1-III inverter output voltage and frequency not stable

8/10/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Miscellaneous

WM-AA-301

14

Medium Risk Plan Actions: Adjust packing on 2-FW-FCV-

2478 (U2 "A" MFRV) IAW WO59203296739

9/6/2019

Procedures

1-AR-F-A4

Main FD PPS Disch HDR Lo Press

1-AR-H-A3

Vital Bus 1-III Invert Trouble

1-OP-26.5

20-Volt Vital Bus Distribution

1-PT-80.1

AC Distribution and Reactor Coolant Pump Operability

Verification

2-AP-31

Loss of Main Feedwater

Work Orders

WO59203296739

Packing adjust to last known torque on U2 A MFRV (2-FW-

FCV-2478)

9/6/2019

71111.15

Calculations

ME-0193

Minimum Required No. of Cycles for Auxiliary Feedwater

PCV & HCV Valves

Corrective Action

Documents

CR1125173

CR1127682

CR1129031

01-SI-HSS-104A discovered with oil level at 1/3

8/15/2019

Engineering

Evaluations

CE-0039

Civil Engineering Technical Report - Justification of Seal

Service Life of Small Bore Grinnell Snubbers at North Anna

Power Station

8/26/1994

ER-NA-ISI-SN-615 Safety Related Snubbers, Determination of Proper Snubber

Reservoir Level

8/15/2019

ET-CEM-04-0011

Recommendation for Extension of Service Life for

Grinnell/Anvil Hydraulic Snubbers - North Anna Units 1 and

2/17/04

ME-0098

EDG Room Temperature Rise Study

Operability

Evaluations

OD7651286

Pressure readings on one of the Nitrogen Reserve Tanks

(NRT) for Unit 2, 2-GN-TK-1A, show a leak in the system,

which challenges the opereability of 2-RC-PCV-2456,

Pressurizer Power Operated Relief Valve (PORV)

8/1/2019

Procedures

1-OP-24.2

Operation of the PORV Nitrogen Back-up Fill System,

3, 2-GN-TK-1A Nitrogen Leakage Determination

9/4/2019

1-OP-24.2

Operation of the PROV Nitrogen Back-up Fill System,

3, 2-GN-TK-1A Nitrogen Leakage Determination

8/30/2019

1-OP-24.2

Operation of the PORV Nitrogen Back-up Fill System, 2-

8/18/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

GN-TK-1A Nitrogen Leakage Determination

1-OP-24.2

Operation of the PORV Nitrogen Back-up Fill System

1-PT-212.14

Valve Inservice Inspection (Backup Air Supply for Aux

Feedwater Valves)

2-AR-C-E7

RCS PORV TK A N2 Sup Lo Press

AD-AA-100,

Technical Procedure Approval

7/21/2019

ER-NA-ISI-SN-615 Safety Related Snubbers

Work Orders

WO59102848049

Small Bore Hydraulic Snubber Functional Testing

10/2/2016

71111.18

Corrective Action

Documents

CR1129258

1-FH-CRN-13 hoist #2 stopped moving and smoke was

seen coming out at hoist

8/20/2019

Engineering

Changes

STI-N12-2017-003

Surveillance Test Interval Evaluation and approval change

EDG SR from 31 day to 92 day frequency

2/26/2019

Engineering

Evaluations

ETE-NA-2019-

0005

North Anna Unit 1 and Unit 2 Reactor Containment Polar

Crane Safety Classification Downgrade

6/4/2019

Miscellaneous

MR Function

MH002

Polar Crane is scoped in Maintenance Rule as Function

MH002

4/15/2019

NAPS-UCR-2014-

28

SAR Change Request: Update based on new Regulatory

Guide 1.9 in place

9/2/2014

Regulatory Guide 1.29

Seismic Design Classification

Regulatory Guide 1.63

Electrical Penetrations Assemblies in Containment

Structures for Nuclear Power Plants

Regulatory Guide 1.9

Selection, Design, Qualification, and Testing of Emergency

Diesel Generator Units as Class 1E Onsite Electrical Power

Systems at Nuclear Power Plants

Procedures

0-OP-4.10

Fuel Building Bridge and Trolley Crane 1-FH-CRN-13

2-OTO1

CM-AA-STI-101

Risk Informed Technical Specification Surveillance

Frequency Control Program

NAPS1-EVAL-

2019-0004

50.59/72.48 Evaluation to perform a hook-to-hook transfer

of a fuel assembly from 1-FH-CRN-13 to a 3 ton chain fall

and lower the remaining exposed portion of the assembly

into the rack.

WM-AA-301

B5B Fuel Pit Shuffle evolution hoist stopped moving, task to

8/21/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

14:

Medium Risk Plan

Actions

Lower Fuel Assembly 51N to seated position in SFP

location F46 using Temporary rigging IAW 0-OP-4.10 OTO1

71111.19

Corrective Action

Documents

CR1131036

U1 CC to RHR supply check valves 1-CC-193 and 1-CC-

198 failed 1-PT-210.14

9/16/2019

CR1131106

1-CC-193 and 1-CC-198 failed to pressurize during type C

testing IAW 1-PT-61.3

9/17/2019

CR1131139

Work performed on 1-CC-193 using work order 1-CC-198

9/17/2019

Drawings

1175-CBM-078A-4 ISI Classification Boundary DWG Interval - 4

Engineering

Changes

NA-19-00108

1-SW-MOV-105C Valve Replacement

Procedures

0-ECM-1509-03

MOV Testing - Quarter Turn Valves

0-MCM-0305-01

Inspection and Repair of Limitorque Valve Control Units,

Type SMB-0, with HBC Acutuators for Butterfly Valves

0-MCM-0307-01

NOV Stem Cuts and Spline Adapter Machining to Permit

Installation of Strain Gauges

0-MCM-0404-02

Removal and Installation of Allis-Chalmers / Rodney Hunt

Butterfly Valves

Work Orders

WO59102494733

01-QS-PI-105A (Pressure Indicator Calibration)

1/10/2017

WO59102941198

01-QS-PI-104A (Pressure Indicator Calibration)

7/6/2018

WO59103134512

01-QS-FI-104 (Flow Indicator Calibration)

10/18/2018

WO59103134519

01-QS-FI-103 (Flow Indicator Calibration)

10/18/2018

WO59203271357

1-PT-63.1A: Quench Spray System - "A" Subsystem

7/10/2019

WO59203279199

CC supply check valves to RHR HX open and inspect

9/18/2019

WO59203294982

Valve Replacement DC 19-00108

WO592032997861 HBC3 Valve Adapter Plate

71111.20

Corrective Action

Documents

Resulting from

Inspection

CR1132024

Containment Coating Damage Identified during NRC Final

Walkdown

9/28/2019

CR1132047

NRC identified items during containment walkdown

9/29/2019

Miscellaneous

2019 Outage Plan Safety Review North Anna Unit 1

8/8/2019

ER-AA-RXE-1004

Reactivity Plan for North Anna 1, N1C27

8/23/2019

71111.22

Calculations

59-02-PT-75.2A

Service Water Pump Test

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

Resulting from

Inspection

CR112384

CR1124166

CR1124170

Engineering

Changes

ETE-NA-2019-

0013

1-SW-P-1B & 2-SW-P-1A Performance Evaluation

Miscellaneous

Nuclear Qualifications for Visual Testing - 2 Level - 2

Examiner

7/17/2019

Procedures

1-PT-138

Valve Inservice Inspection -- LHSI System Functional

Verification

1-PT-210.19

Inservice Inspection SI Accumulator Discharge Check

Valves Full Open Test

2-PT-75.2A

Service Water Pump Quarterly Test

ER-AA-NDE-VT-

2

VT-2 Visual Examination Procedure

Work Orders

WO59102993539

Quench Spray Pump 1-QS-P-1A System Pressure Test

7/10/2019

71124.06

Corrective Action

Documents

Condition Reports (CRs) 1094202, 1107476, 1118898, and

20814

Various

Work Orders

Work Order

Number

59102939905

Perform Surveillance, 0-PT-77.4B, Emergency Core Cooling

Eystem (ECCS) Pump Room Exhaust Air Cleanup System

(PREACS) Filter 1-HV-FL-3B Charcoal Laboratory Test

2/14/2017

Work Order

Number

59103005349

Perform Surveillance 0-PT-77.14A, ECCS PREACS

(Emergency Core Cooling System Pump Room Exhaust Air

Cleanup System ) Filter Train A In-Place Test (1-HV-FL-3A)

2/15/2018

Work Order

Number

59103062602

Perform Surveillance 0-PT-77.14B, ECCS PREACS

(Emergency Core Cooling System Pump Room Exhaust Air

Cleanup System ) Filter Train B In-Place Test (1-HV-FL-3B)

11/08/2018

Work Order

Number

203269622

Perform Surveillance, 0-PT-77.4A, Emergency Core Cooling

Eystem (ECCS) Pump Room Exhaust Air Cleanup System

(PREACS) Filter 1-HV-FL-3A Charcoal Laboratory Test

10/17/2018

71124.07

Calculations

0-HSP-MET-001

X/Q and D/Q

Calculation

North Anna Power Station - 2018 Meteorological Data

Summary (5 Year Summary)

Corrective Action

CR1103691

Aquatic sediment samples from Station 9A collected at the

08/16/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

wrong location

Miscellaneous

2017 AREOR

2017 Annual Radiological Environmental Operating Report

2017

2018 AREOR

2018 Annual Radiological Environmental Operating Report

2018

VPAP-2103N

Offsite Dose Calculation Manual (North Anna)

Revision 28

Procedures

0-HSP-MET-001

X/Q AND GROUND LEVEL D/Q

Revision 0

0-HSP-REMP-001

Radiological Environmental Monitoring Program, Land Use

Census

Revision 1

C-HP-1033.620

Portable Air Samplers Calibration and Operation

Revision 9

HP-3051.010

Radiological Environmental Monitoring Program

Revision 31

RP-AA-502

Groundwater Protection Program

Revision 8

Radiation

Surveys

59-04-2017

Ground Water Protection Plan Implementation Campaign

Analysis 4th Quarter 2017

01/22/2018

GWPP 59004-

2018

Ground Water Protection Plan Campaign Analysis Results

4th Quarter 2018

03/29/2018

Self-Assessments SAR PIR1082665

NEI 07-07 App B Ground Water Protection Initiative

Implementation Assessment

10/31/2017

71124.08

Corrective Action

Documents

CR 1113595, CR

23792, CR

1117959, and CR

23476

71151

Calculations

HP-3010.022

Liquid Effluents Dose Summary July 2019

08/06/2019

HP-3010.032,

10

Gaseous Liquid Effluents Cumulative Dose Summary

08/07/2019

Engineering

Evaluations

Technical Report

No. SE-0007

NRC Mitigating System Performance Index (MSPI) Basis

Document, North Anna Power Station Unit 1 and Unit 2

71153

Corrective Action

Documents

CA7525215