IR 05000338/1987007

From kanterella
Jump to navigation Jump to search
Insp Repts 50-338/87-07 & 50-339/87-07 on 870330 & 0402-03. No Violations or Deviations Noted.Major Areas Inspected: Licensee Action on Previous Open Items,Svc Water Reservoir Improvements,Weld Insp & Review of Personnel Qualifications
ML20210C150
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 04/20/1987
From: Blake J, Economos N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20210B050 List:
References
50-338-87-07, 50-339-87-07, NUDOCS 8705060094
Download: ML20210C150 (5)


Text

UNITED STATES

  • /y Hru,o NUCLEAR REGULATORY COMMISSION 4

+-

_[ p REGION 11

. ;r j 101 MARIETTA STREET * t ATLANTA. GEORGI A 30323

\,*..../

Report Nos.: 50-338/87-07 and 50-339/87-07 Licensee: Virginia Electric and Power Company Richmond, VA 23261 Docket Nos.: 50-338 and 50-339 License Nos.: NPF-4 and NPF-7 Facility Name: North Anna 1 and 2 - -

Inspectio Con ted: h 30 and April 2-3, 1987 -

Inspect r: - . 0 7 p Date 5~gned Approv/db _

- -r /

f. // ake, Section Chief -

Date Signed

/En[n ' ring Branch Di i on of Reactor Safety SUMMAR Scope: Routine, unannounced inspection in' the areas of licensee action on previous open items, service water reservoir improvements - inspection of welds, review of personnel qualifications and quality records of materials use Results: No violations or deviations were identifie g5060094870427 G ADOCK 05000338 PDR

-

.

REPORT DETAILS Persons Contacted Licensee Employees E. W. Harrell, Station Manager E. R. Smith, Jr. , Assistant Station Manager

  • A. Stall, Superintendent Technical Services L. N. Hartz, ISI Supervisor, North Anna Power Station J. H. Liberstien, Site Licensing Engineer
  • T. Johnson, Quality Assurance Supervisor J. E. Wroniewicz, Supervisors Site Engineering T. Sweeney, Site Engineering Office Engineer
  • G. Harkness, Station Licensing Coordinator Other licensee employees contacted included QC/QA inspector, technicians, and office personne NRC Resident Inspector
  • J. Caldwell, Senior Resident Inspector
  • Attended exit interview Exit Interview The inspection scope and findings were summarized on April 3,1987, with those persons indicated in paragraph 1 above. The inspector followup item (IFI), listed below was discussed in detai (0 pen) IFI 338, 339/87-07-01, Field Changes & Revisions to DC84-31 paragraph The licensee did not identify as proprietary any of the materials provided to or reviewed by the inspector during this inspection.

l Licensee Action on Previous Enforcement Matters Thissubjectwasnotaddressedintheinspection.

, Unresolved Items

'

Unresolved items were not identified during this inspection.

Part 21 Report Followup (927168)

i l (Closed) Item P21/86-04, New Service Water Spray Array Support System.

,

-

.

On November 7, 1986, the licensee notified Region II of a potential defect involving a substantial safety hazard at North Anna Power Station Units 1 and 2. The potential defect was described as laminar indications or

" pipe," located in the webbing of the structural steel material used as support columns for the spray array system in the service water pond. The condition was first observed by qC during inspection of completed weld The licensee's followup volumetric, " ultrasonic" examination disclosed that a total of 21 columns exhibited this condition. The material in question was produced by Inland Steel Company (Inland) and purchased through Rockwell Engineering of Blue Island, Illinois. The licensee, with assistance from Inland, has determined that the defective columns were produced from material produced from heat number 17802. The defective columns have been removed and their replacement installed via Design Change (DC), Number 84-31-13, Revision 70, December 15, 1986 and Field Changes 350, 353 and 358. The inspector reviewed the aforementioned Part 21 report and determined it to be acceptabl Also, the inspector reviewed the aforementioned DC, and n elated QA/QC nonconformance report 86-81 " Column Replacement", records to verify that the corrective actions have been implemented as stated. This item is close . Service Water Reservoir Spray and Bypass System Welding (55050)

This work effort was performed as a followup to that documented in Report 50-338,339/86-26. At the time of this inspection, work activity was focussed on welding the tie-in, 36" pressure balanced expansion joints, on service water line WS-4-151-Q3. The licensee's submittal entitled

. . . Proposed Technical Specification Changes, S/N 86-102, dated September 12, 1986, states in part that, design, materials, fabrication, inspection and testing, of the buried piping, expansion joints and access hatches etc. , are governed by Class III requirements of USAS/ ANSI B31.7, 1969 Edition with 1970 Addenda. The aforementioned system has been designated as a QA Category I, structur Weld selected for inspection at this time were as follow Weld Type Status FW-61 36" pipe to Flange completed FW-62H Trunnion to Pipe hot passes in progress H501 Support Plate to trunnion completed These joints were examined to determine whether the following characteristics / attributes conformed to the requirements of the aforementioned code Weld surface finish and appearanc Weld reinforcemen Joint configurations of permanent attachments and structural supports, Removal of temporary attachments, arc strikes and welds spatte .

3 Finish grinding; verify absence of wall thinning, Absence of surface defects including cracks, laps, lack of penetration, lack of fusion, porosity, slag, oxide film and undercut exceeding prescribed limit ,

In addition, the inspector reviewed the performance qualification records of welders to verify that they had been, and were currently qualified to weld these components / piping in accordance with ASME Section IX code requirements. These welders were identified by stencil number: N-263,

-283, -288 and -31 Quality records of the filler metal material used at the time of this inspection were re /iewed to serify compliance with applicable code / standards requirements. The material was identified as follows:

Lot / Heat Size E7018 32604F/402J8331 1/8" 0 ER705-2 702907-12-5/F8902 1/8" 0 Other quality records of related components which were reviewed for content completeness and comoliance with applicable specification NAS-2045, May 31, 1985 were as follows:

Component Purchase Order Mark N Pressure Balanced ET-16195 2-MEJ-20A Elbow Expansion Joint, 1-MEJ-208 36" diameter OUTLET "T", IP-73276 Ht/ Lot KPWS-1B 36" x 36" x 4'5" Quality records reviewed included certificate of compliance, material certifications, vendor fabrication records including NDE reports and receipt inspection report Discussions with cognizant personnel disclosed that the tie-in would be hydroed and flow tested weld within the allotted time permitted under the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Technical Specifications Action Item Statement. Following completion of this inspection, discussion with the licensee's supervisor of Technical Services disclosed that the above mentioned tests were performed on April 4, 1987, as planne Within these areas, the inspector noted that the original Design Change Package No. 84-31-3 and Field Drawings had undergone numerous revisions and field changes or FCRs during constructio Included were field changes necessitated by the replacement of the defective columns and other hardware discussed earlier in this repor Although all these changes / revisions appear to be fully documented and controlled, a final l

-

,

drawing and design change package reflecting as built conditions has not been issued. The inspector discussed the need/ requirement for such documentation with site management and was informed that site engineering is assigned with the resnonsibility for issuing the subject documents within a specified time i.e. , within 90 days after project completio an IFI, to allow for review The inspector stated and evaluation that hedocuments of the subject was generating / drawings when issue IFI-338,339/87-07-01, Field Changes and Revision to DC 84-3 Within the areas inspected, no violations or deviations were identifie . Inspector Followup Items (Closed) 339/86-12-01, Reactor Coolant Pump (RCP) Flywheel Assembly -

Procedur This item was identified when a review of subject procedure disclosed that it lacked specific instructions for the disassembly and reassembly of the RCP flywhee By Revision 11, dated August 7, 1986, the licensee has rewritten and reissued the procedure which includes the instruction under discussio !