IR 05000313/1990038
| ML20062G930 | |
| Person / Time | |
|---|---|
| Site: | Arkansas Nuclear |
| Issue date: | 11/23/1990 |
| From: | Collins S Office of Nuclear Reactor Regulation |
| To: | Carns N ENTERGY OPERATIONS, INC. |
| References | |
| EA-88-283, NUDOCS 9012030085 | |
| Download: ML20062G930 (46) | |
Text
q
,
.
I
.
f
=bccito:DM6;(IE14)-
bec distrib by RIV:
,
tin Resident Inspector DkS F ef(DU/A)
gifpi",
Lisa Shea, RM/ALF DRP Project Engineer (DRP/A)
T. Alexion, NRR Project Manager (MS:
13-E-21)
DRS C. Poslusny, NRR Project Manager (MS:
13-D-18)
.
'I
!
'
.w
I
/(
e i
,
9011 E4 QQ1"JO30066 (ADOC K 05 00031._,
pps PDu g
. - -
-
.
. -
_
_.
-
_-
-
,
b
.
NOV 2 31990
,
,
Docket Nos. 50-313/90-38 50-368/90-38 License Nos. DPR-51 HPF-6 EA No.88-283 Entergy Operations Inc.
ATTN: Neil S. Carns Vice President Operations. Arkansas Nuclear One Route 3. Box 137G Russellville Arkansas 72801 Gentlemen:
This refers to the Enforcement Conference conducted at Region IV's request in the Region IV office on October 30, 1990. This meeting related to activities authorized by NRC License Nos. DPR-51 and NPF-6 for Arkansas Nuclear One and was attended by those on the attached Attendance List.
The subjects discussed at this meeting are described in the enclosed Meeting Sunenary.
It is our opinion that this neeting was beneficial and has provided a better understanding of the findings of the NRC inspection conducted October 1-5, 1990 (NRC Inspection Report 50-313/90-38;50-368/90-38), in followup of an issue identified during the operational safety team inspection conducted Septenber 10-21, 1990.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2. Title 10, Code of Federal Regulations, a copy of this letter will'be placed in the NRC's Public Document Room.
Should you have any questions concerning this matter, we will be pleased to discuss them with you.
Sincerely
OdglnalSigned Gy:
L Thomas P.0wynn
'
Samuel J. Collins, Director Division of Reactor Projects Enclosure:
Meeting Surrrnary w/Attachnents cc w/ enclosure:
Entergy Operations Inc.
ATTN: Donald C. Hintz, Executive Vice President & Chief Operating Officer P.O.' Box 31995 Jackson, Mississippi 39286 RIV:C:DRP/M D:DRS E0 RP
,
TFWesterman;df LJCal GF9an orn SJCollins
-
11/g/90 11/g/90 11/t(/90 11/23/90 (
/ \\
/
A
,
b
'
,
.4 Entergy Operations. Inc.
-2 Entergy Operations, Inc.
ATTN:
Gerald W. MuencF. 'iite President Operations S@ port P.O. Box 31995 Jackson, Mississippi 39286 l
Wise, Carter, Child & Caraway ATTN:
Robert B. McGehee, Esq.
P.O. Box 651 Jackson, Mis:;issippi 39205 Arkansas Nuclear One ATTN:
Early Ewing, General Manager Technical Support and Assessment
,
Route 3, Box 137G
Russellville Arkansas 72801 Arkansas Nuclear One ATTN: Jerry Yelverton, Director Nuclear Operations i
Route 3, Box 137G Russellville, Arkansas 72801 Arkansas Nuclear One ATTN: Mr. Tom W. Nickels
Route 3, Box 1370 Russellville, Arkansas 72801
--
Combustion Engineering. Inc.
ATTN: Charles B. Brinkman, Manager Washington Nuclear Operations 12300 Twinbrook Parkway Suite 330
!
Rockville, Maryland 20852 Honorable Joe W. Phillips
County Judge of Pope County Pope County Courthouse Russellville, Arkansas 72801 Winston & Strawn
.
ATTN: Nicholas S. Reynolds. Esq.
1400 L Street, N.W.
Washington, D.C.
20005-3502
<
!
ATTN: Ms. Greta Dieus, Director Division of Environmental Health Protection 4815 West Markam Street Little Rock, Arkansas 72201 d
,
s
,
'
.
Entergy Operations, Inc.
-3-Babcock & Wilcox Nuclear Power Generation Division ATTN: Mr. Robert B. Borsum 1700 Rockville Pike, Suite 525
Rockville Maryland 20852 Admiral Kinnaird R. McKee, USN (Ret)
P.O. Box 41 0xford, Maryland. 21654 bcc to DMB (IE14)
bec distrib. by RIV:
R. D. Martin Resident Inspector DRSS-FRPS SectionChief(DRP/A)
Lisa Shea, RM/ALF RIV File DRP.
Project Engineer (DRP/A)
T.' Alexion, NRR Project Manager (MS:
13-E-21)
DRS C. Poslusny, NRR Project Manager (MS:
13-D-18)
.
i
'
i I
i l,
s
.
.
,
MEETING SUMMARY Licensee:
Entergy Operations, Inc.
Facility:
Arkansas Nuclear One License No.:
50-313; 50-368 Subject:
ESCALATED ENFORCEMENT CONFERENCE CONCERNING NRC FINDINGS (NRCINSPECTIONREPORT 50-313/90-38;CO-368/90-38)
On October 30, 19901, representatives of Arkansas Power & Light Company met with Region IV personnel in Arlington, Texas, to discuss the apparent violation identified during the NRC inspection conducted October 1-5, 1990, in followup to an issue identified during the operational safety team inspection conducted September 10-21, 1990, and corrective actinns taken or planned by the licensee.
Attachments:
!
'
1.
Attendance List 2.
Licensee Presentation (NRC distribution only)
,
l
i
l l
l l
'
I
o i
a ATTENDANCE LIST.
Attendance at the Enforcement Conference between Arkansas Power & Light Company and NRC on October 30, 1990, at the NRC Region !Y office.
Enterqy Operations Inc.
Neil S. Carns, Vice President - Operations
,
J. J. Fisicaro, Manager, Licensing C. H. Turk, Manager, Nuclear Engineering Design D. C. Mims, Manager, Systems Engineering, Unit 2 M. R. Chisum, Assistant Operations Manager, Unit 2 T. G. Mitchell, BOP System Engineering Supervisor R. J. King, Supervisor, Licensing NRC T. P. Gwynn, Acting Director, Division of Reactor Projects (DRP)
L. J. Callan, Director, Division of Reactor Safety (DRS)
R. Wise Allegations Coordinator T. F. Westerman, Acting Deputy Director, DRP P.'H. Harrell, Acting Chief, Project Section A, DRP
, J. E. Gagliardo, Chief Operational Programs Section, DRS
-
J. E. Cunnins, Reactor Inspector, DRS C. C. Warren, Senior Resident Inspector, ANO, DRP T. W. Alexion, Project Manager, Office of Nuclear Re. actor Regulation
-
..
. -
-
A
_.
.-
- _ _
_
. _ - -
-._..
_. -... - _-
-. -. _-._
-
.
l,
-
"
,
l ANO-1
!
CONTROL ROOM ISOLATION SYSTEM I
I q
l
.
'4
.
10/30/90 g
I lq I
I ENFORCEMENT CONFERENCE I
I I
a =r_,
-
=
ll
'
-
-
- - -
. - - -
-
J
. _ _. _. _ _ - _ _ _ _ _. _ _..
_ _ _ _ _ _ _. _ _... _ _ _. _ _ - -. _ - _. - -
_ _ _ _
i
,
,
_.._ - -.-.-
--.7.=-...
_ _ _
- - ::
I$'
AGENDA
'
k ANO 1 10/30/90 ENFORCEN1ENT CONFERENCE ON
'
CONTROL, ROO51 ISOLATION SYSTEN1 l
I I
,
INTRODUCTION N.S. CARNS
.
OPENING REh1 ARKS R.A. FENECil
.
SYSTEh! DESCRIPTION D.C. 51th1S
.
!
l l
PROllLEh! IDENTIFICATION R.A. FENECll
.
CilRONOLOGY
-
OPERAlllLITY I
-
REPORTAHILITY
'
-
g SYSTEh! DESIGN HASIS C.ll. TURK
.
AS FOUND CONDITIONS AND D.C. hiihtS
'
.
lhlhlEDIATE CORRECTIVE ACTIONS TEST PLAN DEVELOPMENT
-
g AS FOUND TESTING
!
-
SIODIFICATIONS/ REWORK I
-
AS LEFT TESTING
-
l SYSTEM RESTORATION
-
ROOT CAUSE R.A. FENECil l
.
!
l l
CORRECTIVE ACTIONS J.J. FISICAR0 I
.
l l
,
SPECIFIC ACTION RELATED TO i
-
i CONTROL ROOM ISOLATION CONCERN k
RELATED CORRECTIVE ACTIONS
!
,
'
-
!
G. L. 8814 INVESTIGATION
-
'
.
i SAFETY SIGNIFICANCE C ll. TUR K
-
.
k CONCLUSIONS R.A. FENECill
.
N.S. CARNS
!
l L.
...
_
h
.
-
- -
- - -
-.
-- - - ---
- - - - - -
-
-
-
)
. _ _
_. _.
-... _
_ _. _
_..
- _. _ _
_ _ _ _ _. _ _ _ _ _. _. _ _ _ _ _ _ _ _ _... _ _ _ _.,
_
'
,
--
u -
--
=
rg
-
,
l, I
.
.
ELEN1ENTS OF SYSTEM CONF.(GUR ATION
'
/k l
NORS1AL VENTILATION
+
,
'
Eh1ERGENCY VENTILATION
.
,
Eh1ERGENCY FILTRATION
-
- l Eh1ERGENCY AIR CONDITIONING
-
-Q INSTRUh1ENT AIR SYSTEh! INTERFACE
Lq
,4
4
i
L4 R
>
e=
__
_
_
,q
.
--
-
.
D
.-
- - - -. _. _ _. ~..
-. - - -. -.
_ - - - _ -. _
__
_ - -. -
_
- - -...... -
.
..
..
- - -,
a 1-
'
NORMAL VENTILATION I
VSF 8A AND VSF 8B
.
i CV 7905 SUPPLY ISOLATION DAMPER j
.
CV 7907 EXHAUST ISOLATION DAh1PER
.
RECIRCULATION WITH FRESH AIR h1AKEUP
.
'
lt UNIT 2 DIFFERENT
.
2UCD 8683 SUPPLY ISOLATION DAh1PER
-
2PCD 8685 EXIIAUST ISOLATION DAh1PER
'
l
-
I
l l
'
,t i
l I
E w
+
l
.
-
-
-
- - -
- - - -
_
.
.
. _ _..
_ _ _ _. _ _. _ _ _ _ _
_ _ _.. _ _ _ _ _.. _ _ _ _ -. _ _ _ _. _ _ _ _ _. _.
.h
'
_.._. _
._
_ _ _ _ _
__
l
!
.
EMERGENCY VENTILATION
'
I
,
(l Eh1ERGENCY FILTRATION
.
'
VSF.9. FAN / FILTER UNIT
'
-
I
'
RECIRCULATION WITH FRESH AIR h1AKE.UP
-
'
ISOLATED DURING NORh1AL OPERATIONS
.
l SEPARATE DUCTWORK
-
'
2VSF.9 SIMILAR REDUNDANT I
-
EMERGENCY AIR CONDITIONING
+
I 2VUC.27A AND 2VUC.27Il REDUNDANT TO
-
EACH OTHER jl SERVE BOTH CONTROL ROOMS
-
!
2VE.l A AND 2VE.1H
-
E
'E
4
,
l l
i Lg l
.
l l
-
-
. -.
l.
,
.
f
!'
' (a I
)
e
- Di -i a
l
@f
_
_
i
^
g
.
o
r
__
Pm E ' < JM l
WW M"O
-
C
= !.
eEl-l
.
l n 2
-,i i
,
.- -
'
I W %_ -
i M,
!
!
g,
.
,
,
l I
g
.
-
<
v h
l b
- ~ -
s
-
- .
i
s
=
- V
,,
- s
<
p (~iq
. l Ra
,l
t a
e
E ll
i li ( il i
R
'
!
,
i
!
g ![
a e
l (b-gg =j
,
,
~
!
1 1 t _ >...>
>
,
-
-
,
=
--
g ([ D 4C D C
ll N
N l
o
.
m
'l
$gg g q
'
O
.
.. -.-
I
'-
~~__i.! 5
$
I
'
D f
D D l i
=
l
-
Q Q
pum D g, F"-- Q l ?"6mV1--l
<
,
,
,
nnn-
'
\\
35E
ll
- D4
- -
= TJ "P,b e!
!
'
.
g=
.w.
- l j
~
(.
_.1 il
-
J
._ -._ -. _
_
_. _ _ _ _
__
. _ _ _ _.. _ _ _ _ _ _ _
._
_ ___
__.
,
,
a.
,
lg.
wr
,
.
-
INSTRUMENT AIR SYSTEM INTERFACE l:
CV 7905 AND CV 7907 ACTUATION
- E REDUNDANT TRAINS
.
j-CIIECK VALVES ISOLATE FROM INSTRUMENT
-
AIR i
CHECK VALVES ISOLATE TRAINS FROM
-
EACil OTIIER k
NORMAL ALIGNMENT / ACTUATION
.
La
'
PRES 3URE CONTROL VALVE
.
1h
.
UNIT 2 INSTRUMENT AIR INTERFACE DIFFERENT Q
-
NOT REQUIRED FOR PLACING OR MAINTAINING
-
lh 2UCD 8683 OR 2PCD 8685 IN SAFETV
'
POSITION e
,%
T
- =
m
-
,
.
_
..
!
?
i
.
'
,
1l
.
M
.
.*.
M-I
-
-
_
_
O
_-
.
_
C C
_
cA A
()
A
_
7 VT 5 V Y
-
0HS 0H L U
9 LP 9 L A
,d O - 6E7 AP
E7 M
A
-
VM H VMU X
CRS CR E cA O
O ()
N W
_
E
_
_.
._
_.
h E
R P
E M
P E
O8 A
T7 E D
-
C V
S LO
d (j
P O
1
_
E
- h W7 I S
V b
L
-
NR
V D C S
EI S
_
N O f.
.
.
W7 O
.
d
.
D T
-
M
- h
.
87
.
N N
-
_
E
-
O V
b V
A I
.. E S
S BT
-
AA T
(j S IC S
EF
VI
L D E
. S T7 VM
- Y O8 AO
-
-
-
DS VS I
U O
R NIO
.
E I
EV LE g
A OR
-
-
-
R
7
-
0 O'
- E
8
3
-
-
P V
V G
C N
. M P
P A
A
-
<
-
A D
R
,
V 3>
-
l 1 N
E
- N IA
3
-
1
4
-
A A
A
.
N
- N
_.
A E
.
4
-
-
A
._
A I
l
-
E
_
~
7 E
IA 5-
_
_
Y E
_
L'
U
.
S M
_
-
_.
'
g k
E i.
ll
!
I l
l
.
- '
%
.
la a nums T m mua sea e.
l-ma :m
. Aus-4;;a -
Aus-aus amu amm aams amm -
man amme ama
.-
-
.
i
.
!
.
.
l fy-. - -. - _ _ _ _ _ _ - -. - - -
-
- - - - - -
--- - - - -
l
\\
'
ACCUMULATOR PRESSURE DECAY SEQUENCE OF EVENTS LOSS OF INSTRUMENT AIR
<
l l
110 -
l 100 -
NORMALINSTRUMENT AIR
!
HEADER PRESSURE
!
g_
i
,
80 -
INSTRUMENT AIR HEADER PRESSURE LOW (ANNUNCIATOR K-12-D3, 70 -
IN CONTROL ROOM)
PRESSUREIN ONE ACCUMULATOR 60 -
FOLLOWING INFLATION OF BOTH DAMPERS
'
ACCtMSULATOR PRESSURE LOW
,
50 -
(ANNUNCIATOR M16-B3,
" TROUBLE - CONTROL ROOM ISOLATION *,
_
IN CONTROL HOOM)
30 -
!
20 -
SYSTEM PRESSURE LOW FOLLOWING ACTUATION (ANNUNCIATOR K16-83, i
" TROUBLE - CONTROL ROOM ISOLATION *.
10 -
IN CONTROL ROOM)
ACTUAL DAMPER DEFLATION BEGINS
-
I O
,
i TIME
/
b I
._
-
u
.
.
--
.. _.
.. _..
_.
-. - - -. - - -.. -
.
.
l.
CHRONOLOGY OF EVENTS
'
- l 99/10/90 09/21/90 NRC OPERATIONAL SAFETY
-
-
TEAM INSPECTION (OSTI)
l 09/12/90 09/15/90 NRC INSPECTOR REQUESTED DATA
-
-
REGARDING CONTROL ROOh1 EMERGENCY VENTILATION g
Jq SYSTEM (CREYS)
09/15/90 RESEARCH CONCI'UDED THAT FOUR
-
--
!g INSTRUMENT AIR ISOLATION
VALVES HAD NOT BEEN i
ADEQUATELY TESTED g
'
CONDITION REPORT C 90 00f'?
-
WRITTEN l-CONDITION CONSIDERED
-
lg SIGNIFICANT - MANAGEMENT
-
INVOLVED
-
PERFORMED CONTROL ROOM ISOLATION g
.
DAMPERS CV 7905/7 CONSIDERED
k:.
OPERABLE EXPEDITIOUS TESTING
-
'l CONSIDERED MANDATORY 09'/21/90 CONTROL ROOM ISOLATION
-
ll.
DAMPER INSTRUMENT AIR L
SYSTEM FAILS INTEGRITY TEST k
CV 7905/7 DECLARED
-
INOPERABLE 1,
'
50.72 REPORT MADE
-
.
09/27/90 CV 7905/7 DECLARED OPERABLE
-
'
10/22/90 50.73 REPORT SUBMITTED
-
f y
a
-
-
- -
-..
-
. - -
-
. - -
.
-.
.
. -. - - - - - -.
.
g:
-
,,*
-
-r
- 8,
,
DESIGN BASIS EVOLUTION l-1968 ORIGINAL DESIGN CONCEPT
.
y 1974 DESIGN AT STARTUP
.
I l
1976 DCR 436 CHANGES
.
k:
,
'
1978 DCR 569 CHANGES
.
g POST 1978 - NO SIGNIFICANT CHANGES
.
.
g:
g In'
I l-L4
- g
.,
,
.
..
-,..
.
-
-- -
-
-- -
. _ __
_
.
..
\\
-ih-g
.
1968 ORIGINAL DESIGN CONCEPT
}
l
" IN TIIE EVENT OF A HYPOTHETICAL LOSS OF COOLANT ACCIDENT, DAMPERS IN THE DUCTS SERVING APF..'aS
'
OTilER THAN THE CONTROL ROOM SHALL BE
[
AUTOMATICALLY CLOSED, SIMULTANEOUSLY WITH THE CLOSING OF THE OUTDOOR AIR INTAKE DAMPER AND THE OUTDOOR EXHAUST AIR DAMPER, THEREHY CAUSING
'
100% RECIRCULATION OF THE CONTROL-ROOM AIR."
,
l
1:
',I
- l l
l, l l-
'I I
y
,
l1
<
.
.
..
.
.
__
_ _ _ _
_
_.__ _ _ -. _.-._ _
. _.. _ _ _.
k
'
-
,,,.
1974 DESIGN AT STARTUP
t
.
j
" LEAK TIGHT" CONTROL ROOh! DESIGN
.
DETAILED ISOLATION SYSTEh1 FEATURES:
HIGH PRESSURE ACCUh1ULATORS
-
(850# DESIGN)
SOLENOID VALVES FOR CONTROLLING
-
_. _
AIR SOURCE BASED ON RADIATION SIGNAL AND INST. AIR PRESSURE
_
'
J STARTUP TESTS CONFIRh1ED ABILITY OF
.
g RESERVE AIR TO HOLD 24 HOURS 1.-; 4.
CLOSURE TIh1E NOT TESTED, THOUGH DESIGNED
-
TO CLOSE IN 3 SECONDS PER FSAR l:k DOSE CALCULATIONS NOT TIED TO SPECIFIC
-
"'
CLOSURE TIh1E, NO TECHNICAL SPECIFICATIONS FOR CL,OSURE TIh1E t
g a
s iq s
,
- $
-- -
- - - -
.--
-
.
.
.
'
,
}
I
,E
!
.l l
_
'
g
.
_
_
.g.
- _
.
_
_.
.
g
-
T R
.
_
SI NA
_
_
I
._
l
.
g
_
7 =
-
_
VS
.
._
c.
_
_
-
_
g
@
.
-
.
09
7-
-
V V
_
C C
_
g
.
_
_
_
-
_
.
_
~
-
.
.
_
_
gr
_
-
.
_
-
-
_
.
.
'
.
g
_
_.
_
_.
_
-
_
8
_
_ N
.
_
-
V
-
G S
I
_
_
S
.
_
_
_
E
_
.
D
_
-
-
N
'3
.
O
-
-
-
-
A g
L
-
O
-
S
.
I g
_
-
/1
/
.
i
.
CA A
_
.
g
_
I b
.
A
o g
.
A
-
-
A 1-R
--
A V
R
.
V R
R
.
RO R O
-
-
I I
AT AT g
_
V U A
A
-
E L E L
_
V U R
R M
M E
.
ES U S U
-
g E C E C R C R C A
A g
.
-
%
g
.-
-
._
.-
.
... -
.
. -. -
. - _.
. - - - - _ _.. _ -
- -
lh
,
+
1978 DCR 569 CHANGES
,
s
.
AS PART OF THE UNIT 2 / UNIT 1 COMMON
.g CONTROL ROOM INTERTIE, SIGNIFICANT CHANGES WERE ACCOMPLISHED (SEE SKETCH)
TIE IN OF NEW " PRESSURIZATION" SCHEME
-
. -
RESERVE AIR BOTTLE SWITCHED TO LOW
-
PRESSURE TO " FLOAT" ON INSTRUMENT AIR
.
(REQUIRING CHECK VALVESh CHANGES MADE TO ENSURE 10 SECOND CLOSURE TIMES ACHIEVED CHLORINE DETECTORS / ISOLATION FEATURE
-
ADDED
.
TECHNICAL SPECIFICATION FOR 10 SECOND
~
.
CLOSURE ADDED (BASED ON CHLORINE RESPONSE
-
CLOSURE REQUIREMENTS FOR ANO 2)
'
p NO ISOLATION HOLD TESTING PERFORMED FOR.
.-
NEW ISOLATION DESIGN
.
. -.
.
.
.
-
_ - -
-.. -_
--
_ _ -. -
- -
.
"
- s.
,.
_,#
~
+
ANO-1 REOUIREMENTS SUMM ARY g
l'
1968 ORIGINAL DESIGN CONCEPT LEAKTIGHT CONTROL ROOM WITH AUTOMATIC
. N.
ISOLATION FOLLOWING LOCA
-
g 1974 STARTUP
'l.
.
LEAKTIGHT CONTROL ROOM (10CFM IN LEAKAGE
-
ASSUMED)
<l
<
NO SPECIFIC CLOSURE TIME REQUIREMENTS
-
AUTOMATIC ISOLATION UPON HIGH RADIATION
-
!
-
BY EITHER INSTRUMENT AIR OR-RESERVE AIR Lg BOTTLES THIRTY (30) DAY POST ACCIDENT TIMES ASSUMED
-
-
24 HOUR ISOLATION HOLD WITHOUT L
-
INTERVENTION
1978 - DCR 569 (ANO 1/ANO-2 INTERTIE)
l.
PRESSURIZED CONTROL ROOM (3 CFM IN LEAKAGE
-
ASSUMED)
AUTOMATIC ISOLATION WITHIN 10 SECONDS
-
,
'._
UPON HIGH RADIATION (TECHNICAL
-
SPECIFICATION REQUIREMENT) BY EITHER
'
INSTRUMENT AIR OR RESERVE AIR l
ISOLATION HOLD CRITERIA NOT ADDRESSED
-
g e
,
.
.. -. _ - - - - _.
.
_ -.
,
'
,
-
..
_,
TEST METHODOLOGY k
Ll CV 7905 AND CV 7907 CURRENT TESTING
.-
- j TEST PLAN
.
-
GENERIC LETTER 8814 REQUIREMENTS
-
'- l-CONSERVATIVE TEST CONFIGURATION
-
TEST CHECK VALVES ALONE
-
TEST SYSTEM IN ACTUATED STATE
-
ORIGINAL TEST - FOUR PARTS 4,
-
COMPENSATORY ACTIONS
-
- I s
I g
'. :.
l
'
i
+
1
.
-
..
.-
.
..
. -_ -.
.-
-_
_
-
.
j
'
g g
>
,
(l; ACCEPTANCE CRITERIA Ll; CONTROL ROOM INTEGRITY. 30 DAYS
.j:
'
.
l -
,
NO FIRM BASIS FOR ACCEPTANCE CRITERIA FOUND
-
I EIGHT HOUR ACCEPTANCE CRITERIA SPECIFIED
- g
.
.
OPERATIONALLY PRUDENT
-
?li
,
CONSISTENT WITH PRECEDENT
-
Ll COMPENSATORY ACTION ACHIEVABLE
-
l..
INTEND.TO MAINTAIN SYSTEM AT 72 HOUR LEVEL
..
Ll Li; a.
s y
,
'g
+
,
- W
-.
..
..
-
__...
_ _ _
__.
_
_. _. _
__
_
__
- _.
.._ _._ _
.
'
,
+
,.
AS FOUND TESTING l
!l TEST 1
-
VRA 2A SIDE CHECK VALVES TO SOLENOID
.g
-
VALVES
- g TEST 2
.
I'
VRA 2B SIDE CHECK VALVES TO SOLENOID
-
-
VALVES
_
g TEST 3
.
j FULL ACTUATION OF SYSTEM WITH IA
-
ISOLATED p
h.
USED WITH TEST 1 AND TEST 2 TO DEFINE
-
l AS FOUND SYSTEM PERFORMANCE
_
N VERIFIED REGULATOR PERFORMANCE
-
BLADDER INFLATION BLADDER INTEGRITY g
=
.
h DATA REDUCTION
.
,
VRA-2A SIDE MAINTAINED ISOLATION 62
.
MINUTES
'
'.
.
VRA-2B SIDE MAINTAINED ISOLATION 212
-
-
MINUTES MOST PROBABLE SCENARIO - MAINTAIN
-
ISOLATION 75 MINUTES
.
_
r-
- -
..
.
-.
,
- 'I
.f
!
'I
,s?
.-
.
.
.
.
.
'
C C
()
A ()
A 7 VT 5 V Y
.
~
0H S H L U
A 9 L
% 5C_ Y LP
~
g~Cn b27 A A AP
-
-
H VM VMU X
C R E CRS O
O ()
()
N N
_
R E
R P
E
M O8 P A T7 E D-V CAM S
'
1 P O d
()
1
8
_
-
NR
8 7 I S U
-
V D
V L
S EIC S
f_
N O
3 O T
1
D
7 N N
)
V A O
-
-V I
S S
BT AA ()
S IC
-
EF
VID n
L t o O8 n
AO so T 7-VM el l Ta V
DS B
S I
U B
ONIO EV LE g
-
7
/
'
-
M
-
3
\\
8
/
V V
C C
P P
A
g
2 p
-
w,-
-
I A
A R
R
V
V
40 -
B
-
h I
A B
1
-
-
-
A
.
'
A
-
I A
l l
-
r TSW E
A A f T "A
4
4
-
t.t j
A
-
-
-
-
-
-
-
-
-
.
r I t, t l ' g,4 4 I
,I
-
-
-
-
Y
- R
-
A A
-
I D
~
H a I3 T U A O y
P B tp T T N S g
-
E E g
V T h
%
/
A I
I j
- l
{'t!
_
_
.
_
.
_
_
m
_
_
e.
_
'
.
-
_m
.-.
a ma
_
_~ m
.
m
_
C C
.
()
A
>
A
_
..a VT
_
5 V Y 70HS 0H L
_
U 9 LP 9 L g=% bb7
@
eC_VMU A A 7 AP
-
-
_ m VM H
-
_
X m
C R E CR S
_
a
_
()
O O
_
)
N N
..ame R
E
R P
E
.
M
P O8 A
.n T7 E D C
-
a V
S LO
d ()
PO
1
NR gd L
7-
I S
s
-
a V
V D C S
S EI m
'
N O
2 O T
}d
1
D 87 g
N N
_
._.
- {b V
A O
.a
-
V I
S S
BT AA
.
Y ()
S C
=
-
I EF
VID
.
m O8 AO
L
,a tsb T7 VM e
-
Ta V
DS
.
B S
I U B
O O NI s
EV e
LE i
OR i
SP A
/
/
.
A
.M
-VC P
A B
S
- !
P
-
..M
-
=
A AR R
-
0,
-
V
V
4
.'M l
Al N l
Al
.
0 -
B B
_
-
1
A
A
-
-
-
B I M I
A A4
4
-
-
A A
-
-
-
-
.R-
_.
-
-
-
-
.
-
.
-r
'sD I l
- I I I I I I
-
.
=
.
-
,_
Y
_
.E
-
R e
t
-
A l
_
i D
.
H N J
_
T U
A O Y
.E P B L
A P
_
T T I P N S U
E E
.
_
V T S
-
_
.D
-
-
,
b
.
-
-
.E
,
<L!
,l l
,
,
f hj
,,
- )
ri l
I
.:
- [
!
,b
~
,
.
-
-
J_
-
s
.
.
C C
(]
A (>
A VT 5 V Y 70HS 0H L U
9 LP 9 LA h cC 7 lgO-bC VM A
H bMU X
C RS C R E r)
O O
N ()
N
.
.
g
. R E
-
R P
E M
P O8 A
T7 E D
-
C V
S LO
8 (J P O 7 S NR u
I S
-
g V
D C S
EI
s N O O T
8 D
S N N
_
'
'
-v g
I S
BT AA Y
(J SC I
EF R
VI
L D e#
A O8 AO ts T7 VM D
T#
V
DS
-
S I
N B
O U NIO
- U EV Y
LE g
O i
TA SP R
OR B
~
8 EN M
03 TU
3
8 g
-
O-V V
B C
C T
P P
S A
B
2 E
A g
-
-
A g
T R
R I
V 3 7 V
B A
lA'-
B
3
-
4
-
-
-
~g l
lA E
E
~
A A
A
~-g I N I
-
A
4 G
G
-
-A A
g-
_.
J 7
7 Y
R
-
.
D I
L F A
A
()
tUO Y
g B
LP A
T I U P
SE S
T g
g Q
,
g...
,ll l'I l
l;l
.
_
. - -
.
_.
-
-
.
-
_ -
. - -.
-.
r
,
.
'-6
,
i SYSTEM MODIFICATION AND REWORK
,
j'
LEAKS REPAIRED ON PIPING g.
.
'g SV.7813 LEAK REPAIRED
.
-
TUBING AND VALVES ABANDONED REMOVED g
.
REPLACED CHECK VALVES WITII SIMILAR
.
VALVES
.
ADDED MANUAL ISOLATION VALVES UPSTREAM l
.
OF CHECK VALVES l
-
,
1 m
.
LE L
I.E M.-
v i
.
__
_.
-...
_
_. _ _ _ _. _ _ _.
.
.
.__
_. _... _ _ _ _ _....
.
%
,
'
AS LEFT TESTING
l TEST 4
.
VRA 2A SIDE CHECK VALVES TO DAMPERS
-
I TEST 5
.
VRA 2B SIDE CHECK VALVES TO DAMPERS
_[
-
I'
.
-TEST 4 AND TEST 5 DID NOT MEET ACCEPTANCE CRITERIA
,
.
TEST 6
=
.
Ll VRA 2A SIDE MANUAL ISOLATION VALVES
'
-
TO DAMPERS k
MET ACCEPTANCE CRITERIA - 200 HOURS OF
-
ISOLATION ll; f.
o
.
l-TEST 7
-
VRA 2B SIDE - MANUAL ISOLATION VALVE ml
-
TO DAMPERS l
l L
MET ACCEPTANCE CRITERIA - 106 HOURS OF
-
ISOLATION l4 Lg-
!+
=r E
.
.
.
_
.-.._..
.
.
..
. _ _ -
-
. _ -
.
.
i
,
- {.
-
.
l v,
W um
~Bsg g
,
a i-100[ f001
-1000 0 01 a
'g B d o 8 g
v, v,
s z
I
@
@
@
@
l laH Zei
"
'
'g
a g7
As s
og a
n n
>
e u
-
i
!
RTl mi Ml S
@
@
- !
IL
l E @::
-C l
@J, k
- ~ ~ i-C i
l s
, _ _
.s I-2[
?
E'
l
'5 S*
-
'
s I
g ge
.6 e v'
,
li.
u _ _ _ _ _ _ _ _ _ _ _.. _ _ _ _ _ _ _ _ _ _ _ _ _ _i
.
g g
hI f
}.
>.
- l y
s A z
m, E8 E
g.
Bm 5e k
.
W n-m
-
+
+
.
l;'
i'
!
i!i f
.;!![L
,i
.
.
.
.
L
.
'
-
C C
()
A (>
A VT 5 V Y 70H S 0H L
-
U 9 LP 9 L A
-
]Cm 697 eC 7 AP
-
A H VM VMU
-
X C R S CRE O
O
[)
(>
N N
-
-
1
]
l x-vS
3'
8v@
f 7-S Y
-
RAD
-
N
-
.
U OB
'
1 O
-
8
0
8
V-V C
C P
T P
B S
A
S
-
b A
- '
E P
A
R T
R 3 I V
>
-
V
-
A 1 N
-
- 5
4
A
4 I
A
-
-
l
_
_.
A l N
-
A A
^
3 4-
A
-
-
I
-
-~.
2 3
6
<
-
>
-
A A!
[
I
'
t
,t s
',s i8
I ' '
'.
-
-
E
-
j7
-
Y
-
R
- gV
.
A A
-
D I
_.
_
_
N (J
_
H U
TA O Y
_
P B LP
_
f T
A f
S I PU rE E S
V T
_.
_
.k f
i
,1
-n+am
,,
--e s---
's.4-a a
,m4 W
1,.
mas
.a-a 6.la.4__,,je
_
,,,4,,\\,ae-Jn-
-_
,
..
e'
L
.
.:
+
p t
$
N e >
lootloci @d
--io o rtool!si
-
Oc Bem usa
@
9 vm um
@
@
@
@
_
!.sH
Ze!
o
.
.
I 5 67 I
n35
.l mJ b
a
>
u i
i y
I-
'
g@
@
e
-
-
i i!@::
{
!
@r-K i
u2, 9:
e 5 L
- d_
- .
- I i.
.
a e
,
,
q
5*
'
.-
.
I I
G lf U
l
\\
E Ak
u___________..______________
,
l 5 l f
>
l-lg 2J L it s
-
n'
s8 b
M Bm 5$
I
'
WW m
-
%
+
l
..
.
.
.
.-.
.
-
'
- !
,5
,.
.I
-!
,
,
-
.
.
.
-
- a
_
.-
.
-
.
_
_
C C
()
A ()
A 7 VT 5 V Y
-
0H S 0H L
_
U 9 LP 9 L Cm 697 AP aCm6= VM A
7 A H VMU CR C R S X
E O
O
.
(2 ()
N N
-
-
-
_
_
I
1
]
I
'
%
N
-
-
V
-
S
-
-
-
d A
1 8 gb A
7-VS Y
E
-
=
.
RADNU O
SP B
g
-
M
-
0
3
y3
8 V
V C
C P
T P
B S-2 S
.
E P
,,
,g
!
A g
R T
r V
-
- N l
g 0 -
B
'
3
g I
A
-
4 A
-
-A I
-
A M
1A A
g
3
4
-
-A
-
m I
}X I
2
6
-
-
-
A A
[
~
r!
sI i', 3 iI
- ,ai g I I
-
j 3
-
6 Y
-
R
- gy A
A
-
D I
H N
()
T U
A O Y
s L
P B
g A P T
T P
I N
S U
E E
S V
T m
,
_
fr Y
M
.
-_
_ _.
.
__
_
_
_
_.
.. _ _ _
_
.. _ _.
. _
_.
3-
,
.
-
-
SYSTEM RESTOR ATION L'g MANUAL ISOLATION VALVES IA 61 AND IA 62
+
NORMALLY CLOSED hf OPENED DAILY TO RECHARGE ACCUMULATORS
-
J$
!
COMPENSATORY ACTIONS PROCEDURALIZED
-
Ll'
~k'
ALTERNATIVE COMPENSATORY MEASURE
-
AVAILABLE
-
g REPETITIVE TEST FREQUENCY
-
\\
..
u
- .
I q
'
I
}
,,
&
.?
.
.
-.
-._-
- -
.-
-..
__ _
l-y
.
,,
t
'
i'
ROOT CAUSE F
INADEQUATE TESTING OF CONTROL ROOM ISOLATION.
SYSTEM TESTING FOCUSED ON VALVE ISOLATION TIME.
DID NOT INCLUDE KEEPING VALVES IN THEIR REQUIRED
!
POSITION.
CONTRIBUTING CAUSES INADEQUATE FUNCTIONAL / SURVEILLANCE TESTING THAT RESULTED IN FAILURE TO RECOGNIZE DEFICIENT EQUIPMENT.-
DEFICIENCIES IN THE PROCESS TO ENSURE THOROUGH RESPONSE TO GENERIC LETTER 8814
,
!
t
,
I k
e
--
,
c
-
-
.
__
-
-
_
.
_
_
.._
. _ _ _ _ _ _ _ _..
..... _...
__
.. ~ _.
'
'
l
.
w
%
l SPECIFIC CORRECTIVE ACTIONS RELATED TO
.
,_
CONTROL ROOM ISOLATION CONCERN COMPLETED ACTIONS SYSTEM MODIFICATION
.-
TESTING OF SYSTEM
.
PREPARE AND SUBMIT LER
.
SYSTEM ENGINEER ASSIGNED
.
DEVELOPED DESIGN BASIS EVOLUTION
.
FOR CONTROL ROOM DAMPERS COMP PROCEDURES DATE L
PROVIDE PERIODIC TESTING
.
12/31/90 OF ACCUMULATORS / CHECK VALVES
,
' FOR NORMAL VENTILATION SYSTEM PERIODIC TESTING OF VSF 9 1.
ACCUMULATORS 04/08/91
,
TESTING ACCUMULATOR / DAMPERS
.
QUARTERLY DESIGN (INITI A L)
'
DETERMINE FEASIBILITY OF
,
.
L UTILI7ING FAIL SAFE DAMPERS 03/01/91 OR _OTHER COMPONENTS RE EVALUATE G.L. 8814
.
RESPONSE ACCUMULATORS REVIEW
-
UNIT-1
=
PRIOR TO-t STARTUP UNIT 2
=
11/30/90-REM AINING G.L. 8814
-
REVIEW 02/I5/91
-TECII SPECS.
!
T.S. CilANGE UNIT 1 SECTION
.
12/31/90 3.9.3' DAMPER CLOSING &
,
SECURING VENTILATION FANS
!
h
!
y
,
-.
.
.
.
-
.
.
-
-
- --
-
--
-
-
...
.
._
-
...
.
'k,
g.
.
ADDITIONAL RELATED ACTIONS j
TAKEN OR UNDERWAY
-
ACTIONS TAKEN SINCE 1978 MAJOR CHANGES IN OUR 10CFR 59.59 PROGRAM
.
g COMPREHENSIVE PROCEDURE
-
TRAINING AND CERTIFICATION
-
BETTER DOCUMENTATION
_
-
SIGNIFICANT CHANGES TO PLANT MODIFICATION
.
_
PROGRAM IMPROVED SAFETY REVIEW OF CHANGE PACKAGES
.
ig~
POST. MODIFICATION TESTING
-
REVIEW BOARD
,
.
ACTIONS UNDERWAY I
SURVEILLANCE TESTING UPGRADE PROGRAM
.
(BUSINESS PLAN C.1)
SYSTEM ENGINEERING PROGRAM
.
(BUSINESS PLAN C.5)
- k UPGRADE ANO CHECK VALVE PROGRAM
.
(IlUSINESS PLAN D.5.m)
DESIGN CONFIGURATION DOCUMENTATION PROGRAM
.
lg (BUSINESS PLAN D.6.a)
ISOMETRIC UPDATE PROGRAM
.
J (BUSINESS PLAN D.6.b)
SAFETY SYSTEM FUNCTIONAL INSPECTION USINESS PLAN D.10)
ll I
+
-
>
--
-
.
. a -.
i
.
$*
\\
a
+
..
.
.I
.
GENERIC LETTER 88-14 j.
INCORRECT STATEMENT REVIEW INVESTIGATION
+
'l.
ROOT CAUSE
+
CORRECTP.'E ALTIONS
+
l
,.
,
g..
l
.
i
.
I d-
,
_,
.
..
...
-
.- - -. _.
....
. -..
. - -
.
.-.
.
...
..
-%%
,
-
...
GENERIC LETTER 8814 INVESTIGATION INTERVIEWS
PROCEDURAL REVIEWS
"G REEN FOLDER" REVIEW
,
!'
I e
,
,
-
-
-
- - -.
- - -
-
-
- - - -. _
.
_=_ ___ _
_
.
_..
. _
h'
-
--
_-
.
-
__ _.-.
_
.
s
_
'
o G.EFERIC LETTER 88-14 l
,.,
, ROOT CAUSE
'l l
FAILURE TO FOLLOW THE APPLICABLE PROCEDURE l
CONCERNING VERIFICATION OF INFORh1ATION CONTAINED IN LIR.
I CONTRIBUTING CAUSES v
LACK OF h1ANAGEhtENT INVOLVEh1ENT AND LEADERSIIIP LACK OF SPECIFIC PROCEDURAL GUIDANCE I
l
i i
!
!
Q-J
>
W.<'
-
z,
,
d.
'
GENERIC LETTER 8814 g
CORRECTIVFmACTIONS l
DATE CONDUCT ADDITIONAL REVIEWS
+
RESPONSES WITH OPERATIONS 03/31/91
-
'd ASSESSMENT GROUP INPUT
(BULLETIN 88 03)
l GENERIC LETTER AND 12/31/90
.
!!ULLETIN RESPONSES h
'
ADDITIONAL NRC SUllMITTALS 01/31/91
-
!.
ENil ANCE PROCEDUR AL GUIDANCE 12/15/90
.
i (l INCREASE AWARENESS OF LIR 11/30/90
.
!
RESPONDENTS
~I I
!
,
I
,q i
l l
q
,
Y__ __._
J Y
Q
>
a.
. - -.. _ _.
__. - -._....... - - -.-.-- - - - -- 7. = -. - -
-.
.
SAFETY SIGNIFICANCE l
'
l FAILURE TO ADEQUATELY TEST Tile REDESIGNED
.
(1978) CONFIGURATION IS CONSIDERED l
g SIGNIFICANT WITH RESPECT TO BOTil Tile I
ORIGINAL POST.h10DIFICATION TESTING AND RECENT G.L. 8814 REQUIREh1ENTS
!
l Tile SPECIFIC CONSEQUENCES IlEING CONSIDERED
+
ARE RELATED TO A POSSillLE EXCEEDANCE OF GDC 19 L1411TS FOR CONTROL ROOh! OPERATOR DOSE.
k Tile ACTUAL SAFETY SIGNIFICANCE IS 511Nih11 ZED i
'
ilY TI'E FOLLOWING FACTORS:
L OSE CALCULATIONS ARE IIASED ON
.
j huh 1EROUS CONSERVATISh1S GDC Llh11TS ARE CONSERVATIVE
-
h I
SEVERAL POTENTIAL RECOVERY ACTIONS
-
WOULD llAVE IIEEN AVAILABLE RADIATION PROTECTION FEATURES ARE i
-
AVAILABLE (ALARh1S, SCBA's, ETC.)
"
'
n I
l
q
'
,!
,=
_
-
.
.
.
.. =......
.. _
_
__.
.
_.
_ _ _ _ _ _.. _ _ _ _ -. _
_____ _ _
i
-
-
.
_... - -.. _ _ -.... -
-
=. -..... - -
- -.
l
- l
'
DOSE CALCULATION ASSUMPTIONS
"
I l
CONSERVATIVE REALISTIC ASSUA1PTION ASSUM PTION l
.
'
l 1.
105% OF FULL POWER 100% POWER GAP j
TID 14844 SOURCE ACTIVITY OR LESS
!
l l
[
2.
INSTANTANEOUS RELEASE DELAYED POST TRIP i
OF CORE INVENTORY TO RELEASE WITil DECAY
!
CONTAINh1ENT ATh10SPilERE l
(NO DECAY llEFORE RELEASE)
,
I l
i l
l 3.
CONTAINhtENT SPRAY HIGiiER IODINE EFFICIENCY LIMITED REMOVAL EFFICIENCY
!
!
PER SRP 6.5.2, REY. O PER SRP 6.5.2, REY. 2 l
l l
4.
NO DECAY OR PLATEOUT DECAY MODELED
'
,
IlETWEEN LEAKAGE FROM I
!
'
l CONTAINMENT AND IN-
!
LEAKAGE TO CONTROL
!
ROOM
'
l'
5.
CONSERVATIVE X/Q: 95 %
-
l, OF DATA INDICATES USE
OF A SMALLER X/Q VALVE
{
i
!
- 6.
10 CFM UNFILTERED IN.
-
i LEAKAGE IS ARIlITRARY j
'
FOR CONSERVATISM
,
i
!
!
I l
l
%
$
,
-.-~v.
,.,. - - - - -,
,
,._,,.,,,_,---,,-----r.-.
.-..
.. -
-
.
.
- -
i l
.
g___.._.__.-.____.
- - - -. _ _
--.--
, _ _
_
,;;
,.
_
l'
..
~
OPERATOR DOSE Ih1 PACT I
CURRENT GDC SRP
,l
-
DESIGN
6.4 CASE CASE (REht)
LIMITS GUIDANCE I
II j
_______________ _________________________________________
______________ ________________ ____..__ _________________
WilOLE I.6
5 3.6
.36 IlODY i
i TilYROID 26.8 (EQUIV)
37 3.7
>
(40)*
j SKIN (IlETA)
32.3 (EQUIV)
64 6.4 i
CASEI:
ESTIMATED DOSE DUE TO DEGRADED ISOLATION SYSTEM ASSUMING (NON.MECilANISTIC)
\\
1)
ISOLATION LOST AT 1 IIOUR i
I 2)
TID SOURCE TERMS I
3)
30 CFM UNFILTERED IN LEAKAGE AFTER I HOUR
'
4)
ISOLATION RESTORED AT 8 liOURS 5)
S R P 6.5.2, REV 2 SPRAY EFFICIENCIES
!
CASE II:
ESTIMATED DOSE REALISTIC ASSUMPTIONS i
(MECIIANISTIC)
1)
GAP ACTIVITY SOURCE TERM 2)
OTI1ER ASSUMPTIONS IIELD CONSTANT
ACCEPTANCE LIMIT FOR ANO PER MEETING WITII NRC b:-
4;
,
,.,. _ _ _
-
. - -
---
-
- - -
,
-
.
-
._..
.
.. _
-.
. _ _ _
-
a
'
'
r
-
-
.. -
,
SAFETY SIGNIFICANCE SUMMARY ESTlh1ATED OPERATOR DOSE IS CONSERVATIVELY
+
CALCULATED TO REh1AIN WITHIN ACCEPTANCE LIh1ITS ASSUh11NG THE CONTROL ROOh! ISOLATION SYSTEh1 IS DEGRADED AFTER ONE HOUR. THEREFORE, THE SAFETY SIGNIFICANCE IS CONSIDERED h11NIh1AL.
i
,
!
i
'
,
t e
o
_