IE Insp Repts 50-313/81-16 & 50-368/81-13 on 810421-24.No Noncompliance Noted.Major Areas Inspected:Reactor Cooling Sys Leak Rates
ML20004B242
Person / Time
Site: Arkansas Nuclear  
Issue date: 05/13/1981
From: Hunnicutt D, Yandell L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20004B239 List:
References
50-313-81-16, 50-368-81-13, NUDOCS 8105270437
Download: ML20004B242 (4)


Text

.- o U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION IV

Reports:

50-313/81-16 50-368/81-13 Dockets:

50-313 Licenses:

OPR-51 50-368 NPF-6 Licensee:

Arkansas Power and Light Company P. O. Box 551 Little Rock, Arkansas 72203 Facility Name:

Arkansas Nuclear One (ANO), Units 1 and 2 Inspection At:

ANO Site, Russellville, Arkansas Inspection Conducted: April 21-24, 1981 Inspectors:

h S//,J/8/

0. M. Hunnicutt, Chief

/ Date Project Section 2 l

bl 0 5/S/8/

D L. A. Yandell, Reactor Inspector

' Date

'

Project Section 2 Approved by:

h

[//8/6/

0. M.~Hunnicutt, Chief

' Dat'e Project Seccion 2

.

Inspection Summary Insoection conducted during the period of Acril 21-24, 1981 (Recort 50-313/81-16)

Area Insrected:

Routine, unannounced inspection of the Reactor Cooling System Leak Rates (RCSLR) to independently verify that the RCSLR are within the Limiting Condition for Operation (LCO) and that the licensee's calculational technique for determining RCSLR is adequate.

The inspection involved 14 inspector hours on-site by one NRC inspector.

,

Results:

The RCSLR was dotarmined to be within the Technical Specification limits, met the LC i requirements, and the difference between the licensee's and the inspector' ' alculational techniaues and calculated leak rate values are acceptable. Within the one area inspected, no violations or deviations were l

identified.

D1 8105270

.

-

. - - --

.

-

.

-

-

l l

.

,

Inspection conducted during the period of Aoril 21-24, 1981 Qeport 50-368/81-13)

Area Inspected:

Routine, unannounced inspection of the refueling activities.

The inspection involved 27 inspector hours on-site by two NRC inspectors.

Results: Within the one area inspected, no violations or deviations were identifie *

.

DETAILS 1.

Persons Contacted

  • J. P. O'Hanlon, ANO General Manager
  • G. H. Miller, Engineering & Technical Support Manager
  • E. L. Sanders, Maintenance Manager
  • L. W. Schempp, Quality Control Manager
  • B. A. Terwilliger, Operations Assessment Superintendent
  • L. W. Humphrey, Administration Manager
  • L. A. Taylor, Unit 2 Operations Superintendent W. Mocn, Shift Supervisor, Unit 1
  • Attended exit interview.

The inspectors also contacted other plant personnel, including operators, technicians, and administrative personnel.

2.

Refueling Activities (Unit 2)

The inspectors reviewed the refueling activities being performed during this period as well as the documentation associated with the preparation and verifications required for refueling operations.

The inspectors

'

verified that (1) all surveillance testing required by Technical Speciff-cations had been performed prior to fuel handling, (2) periodic testing of refueling related equipment was being performed, (3) required parameters were being monitored in accordance with Technical Specifications, and (4) staffing for refueling operations was in accordance with Technical Specification requirements.

As part of the review, the inspectors reviewed the following licensee documents:

Procedure 2304.70, " Containment Isolation and Miscellaneous Valves

'

Stroke Test and Positicn Verification," (Revision 1, dated l

March 20, 1981)

Procedure 2503.03, " Operation of Fuel Handling Equipment," (Revision 3, dated April 17, 1981)

l Procedure 2502.03, " Preparation for Refueling (Revision 4, dated April 15, 1981)

l Procedure 2502.01, " Refueling Shuffle (Revision 1 dated April 14, 1981)

The inspector identified four minor administrative discrepancies in the l

!

completed Procedure 2502.03 which the licensee corrected prior to the l

inspector leaving the site.

,

.

.

. -.

.

_.

.

--

.-.

- - _ -. -

. - -.

-

.-

=

.

The inspectors observed refueling operations from the Refueling Machine in containment and at the control station in the Control Room.

In addition, the licensee demonstrated operation of the Spent Fuel Handling Machine for the inspectors since fuel was not being transferred from the containment at that time.

No violations or deviations were identified.

3.

Independent Measurement of Reactor Coolant System Leak Rate (RCSLR) Unit 1 The inspector independently verified that the RCSLR for the Unit 1 RCS was within the Limiting Conditions for Operation (LCO) and that the licensee's calculational technique for determining the RCSLR was adequate.

The licensee's calculational technique and the inspector's independent results were compared.

The licensee's identified and unidentified RCSLR (1) Total Leakage = 0.5098 gallons per minute (gpm); (2) Known were:

Leakage = 0.286 gpm; and (3) Unknown Leakage = 0.224 gpm.

The results of the inspector's independent measurements were:

(1) Total Leakage =

0.594 gpm; (2) Known Leakage = 0.286 gpm; and (3) Unknown Leakage = 0.308 gpm. The RCSLR difference between the licensee's total leakage calcula-tions and the inspector's independent calculations was 0.084 gpm.

The inspector determined that the RCSLR was within the Technical Specificaticn limits and the difference between the licensee's and the inspector's results

'

was acceptable.

No violations or deviations wero identified.

4.

Exit Interview An exit interview was conducted on April 24, 1981, with those ANO personnel denoted in paragraph 1 of this report to summarize the scope of the inspec-tion and the findings.