U.S. NUCLEAR REGULATORY COMMISSION O
OFFICE OF INSPECTION AND ENFORCEMENT Region I
Report No. 81-03 Docket No. 50-309 Category C
License No. DPR-36 Priority
--
'
'
Licensee: Maine Yankee Atomic Power Company 20 Turnpike Road Westborough, Massachusetts 01581 Facility Name: Maine Yankee Nuclear Power Station Inspection at: Wiscasset, Maine Inspection conduc
- January 5 - 30, 1981 i
Inspectors:
/ r / Kip %,r w d2 f/
'W.gparusj)eactorInspector Dat'e sitjned
'
OccIJ ak /n P. Swetland, Reactor Inspector Dater sigrfed Date si ned Approved by:
.
4#w 7 // P/'
,
T. Kartin,(gief, Reactpp Projects Date signed
'
j Sec Won No. 3. R0&NS Branch Inspection Summary:
Inspection on January 5 - 30, 1981 (Report No. 50-309/81-03)
Areas Inspected:
Routine, regular and backshift inspection by two resident inspectors.
Areas inspected included the Control Room, Containment, Turbine Building, Primary Auxiliary Building, Spray Building and Auxiliary Feed Pump Room. Activities / Records inspected included physical security, plant operations, maintenance and surveillance testing, followup on previous inspection findings, followup on selected IE Bulletins and Circulars, and shipment of radioactive material. The inspection involved 100 inspection hours.
Results:
No items of non-compliance were identified.
Region I Fom 12 (Rev. April 77)
810 5010 #l
..
.
,
l i
DETAILS 1.
Persor.s Contacted P. Anderson, Administrative Department Head R. Arsenault, Plant Shift Superintendent J. Brinkler, Technical Support Department Head G. Cochrane, Health Physics Supervisor J. Hebert, Director, Plant Engineering W. Paine, Operations Department. Head R. Radasch, I & C Supervisor S. Sadosky, QA and Audit Coordinator D. Sturniolo, Technical Assistant to the Plant Manager E. Wood, Plant Manager R. Wyckoff, Senior Plant Engineer The inspectors also interviewed several plant operators, technicians and members of the engineering and administrative staffs.
2.
Followup on Previous Inspection Findings
.
(0 pen)
Follow-up Item (309/79-06-02).
the inspector reviewed the licensee's progress in this area. During a safeguards valve position verification on January 22, 1981, five valves were found not to have identifying labels. These valves were identified to the Operations Department Head for corrective action (CS-7, CS-8, CS-103, CS-104, SIA-44).
It was noted that all valves outside containment had been properly labeled. The labels on the above valves will be rechecked during a subsequent inspection.
l (Closed) Follow-up Item (309/79-10-01). The NRC Health Physics Appraisal feam evaluated the licensee's Respiratory Protection Pro-gram.
Based on their satisfactory finding the inspector had no further questions in this area.
(Closed) Unresolved Item (309/79-14-06).
Licensee procedures 5-27 Reassembly of a Reactor Coolant Pump; and 5-28, Installation of a Reactor Coolant Pump Motor were reviewed, approved and issued as of 12/1/80.
(Closed) Follow-up Item (309/79-19-02). The NRC Health Physics Appraisal Team evaluated the waste shipping program and identified no significant weaknesses. The 1979 annual audit discrepancies have been corrected. The inspector had no further questions 11 this area.
l
.. _.
-
.-- -
_, - - - -. - - -
. - -
.-
-,
_ - - - -.
s
.
(Closed)
Follow-up Item (309/79-19-03). The inspector determined that the Chemistry / Health Physics Training Program had been initiated in response to the 1979 audit report. The NRC Health Physics Appraisal Team evaluated this training program.
Based on the satisfactory eval-uation of this program, the inspector had no further questions in this area.
(Closed)
Follow-up Item (309/79-19-04). The inspector determined that training sessions have been conducted pertaining to NRC and D0T requirements. The NRC Health Physics Appraisal Team evaluated this area and found it satisfactory. The inspector had no further questions in this area.
(Closed) Unresolved Item (309/80-02-02). The NRC Health Physics Appraisal Team evaluated the air sampling capability of the licensee.
Based on the satisfactory evaluation of this team and the incorpora-tion of new alpha spectroscopic equipment on site, the inspector de-termined that the licensee's air sampling capability is adequate.
The inspector ned no further questions in this area.
(Closed)
Follow-up Item (309/80-10-02). The inspector verified that the locally posted procedures had been incorporated into the controlled document distribution. No further questions were identified.
(Closed) Unresolved Item (309/80-12-03). The inspector reviewed I & C surveillance procedures.
Each calibration procedure has been retyped and reissued. The new data sheets are legible.
No further quastions were identified.
(Closed)
Noncompliance item (309/80-13-ul). The inspector reviewed the licensee's procedure 9-1-15, Snipment of Madioactive Material Rev 7. January 1981.
Precautions and verifications have been added to preclude recurrence of this event. The inspector has observed shipments leaving the site to verify proper marking.
No further instances of improper labels were identified.
(Closed) Follow-up Item (309/80-14-01). The inspector reviewed the corrective action taken with respect to this item. Operator training in this area revealed that cycling of locked valves after this verifi-cation is required procedurally in order to recirculate the sample safeguards system piping. Operators are however still responsible for returning valves to the proper locked position. Subsequent valve line-up verifications were performed by the inspector with no discre-pancies identified. Tne inspector had no further questions in this area.
.
- - - - -
--.
ww,,
y y-yi
.ww-,w-y yni-g-
-,p--
-y-g--
-
r
- - ---
-e----y m,
v-e---
y
_ _ _
.
.
(closed) Noncompliance Item (309/80-16-02). The inspector reviewed revision to the licensee's procedure 9-1-15, Shipment of Radio-aactive Material Rev 7. January 1981. This procedure stipulates the criteria for verific::tica of handling equipment.
Subsequent inspection of waste handling evolutions have identified no further items of non-compliance.
3.
Review of Plant Operations - Plant Inspections The inspector reviewed plant operation through direct observation throughout the reporting period, a.
Instrumentation Control room process instruments were observed for correlation between channels and for conformance with Technical Specification requirements.
No unacceptable conditions were identified.
b.
Annunciator Alarms The inspector observed various alarm conditions which had been received and acknowledged. These conditions were discussed with shift personnel who were knowledgeable of the alarms and actions required.
During plant inspections, the inspector observed the condition of equipment associated with various alarms.
(1) Heat Tracing The inspector noted that the heat tracing malfunction alarm on the main control board is continuously in the alarmed state due to malfunction of non-safety related heat tracing circuits.
Since routine surveillance of local heat tracing e. arm panels is not accomplished, the licensee has no means to verify the operability of safety related heat tracing circuits required
!
by Technical Specification 3.5.
The inspector found no l
required heat tracing out of service. This issue is unresolved pending licensee action on interim measures to monitor safety l
related heat tracing while the annunciator is invalid.
(309/81-03-01).
c.
Shift Manning The operating shifts were observed to be staffed to meet the operating requirements of Technical Specifications, Section 5, both to the number and type of licenses. Control room and shift manning were observed to be in conformance with 10 CFR 50.54.
l
- - -. - -
- ~..
- _ _ _
_ _ _, _.
__
_
___
.
.
d.
Plant Housekeeping Controls Storage of material and components was observed with respect to prevention of fire and safety hazards.
Plant housekeeping was evaluated with respect to controlling the spread of surface and airborne contamination. There were no unacceptable conditions identified.
e.
Fire Protection / Prevention The inspector examined the condition of selected pieces of fire fighting equipment. Combustible materials were being controlled and were not found near vital areas. Selected cable penetrations were examined and fire barriers were found intact. Cable trays were clear of debris.
f.
Control of Equipment During plant inspections, selected equipment under safety tag control was examined.
Equipment conditions were consistent with information in plant control logs, g.
Equipment Lineups The inspector verified that the major valve and switch positions were correct to insure Operability of the Safety Injection System, Auxiliary Feedwater System, Containment Spray, and Emergency Diesel Generators, by observation of the Main Control Board and inspections in the Diesel Generator Rooms, Spray Building, Primary Auxiliary Building and Containment. System walkdowns were per-formed on those systems; no unacceptable conditions were identi-fied.
h.
Containment Inspection The inspector toured the containment 'fi'. ding on January 22, 1981 during normal operations. System lineup verification of inaccessible components and general leakage and housekeeping inspections were performed.
No abnormal conditions were identified.
4.
Review of Plant Operations - Logs and Records During the inspection period, the inspector reviewed operating logs and records covering the inspection time period against Technical Specifications and Administrative Procedure Requirements.
Included in the review were:
.-
.
.
.
Control Room Log
- daily during control room surveillance Jumper and Lifted Leads Log
- all active entries Maintenance Requests and Job Orders - all active entries Safety Tag Log
- all active entries Plant Recorder Traces
- daily during centrol room surveillance Plant Process Computer Printed Output
- daily during control room surveillance Night Orders
- daily during control room surveillance The logs and records were reviewed to verify that entries are properly made and communicate equipment status / deficiencies; records are beir.g reviewed by management; operating orders do not conflict with the Technical Specifications; logs detail no violations of Technical Specification or reporting requirements; logs and records are main-tained in accordance with Technical Specification and Administrative Control Procedure requirements.
Several entries in these logs were the subject of additional review and discussion with licensee personnel.
No unacceptable conditions were identified.
S.
Observation of Physical Security The resident inspector made observations, witnessed and/or verified,
,
during regular and off-shift hours, that the selected aspects of the security plan were in accordance with regulatory requirements, physical security plans and approved procedures, a.
Physical Protection Security Organization
Observations and personnel interviews indicated that a
--
full time PL./uer of the security organization with authority to direc physical security actions was present, as required.
Manning of all three shifts on various days was observed to
--
be as required.
b.
Physical Barriers Selected barriers in the protected area, access controlled area, and the vital areas were observed and random monitoring of iso-lation zones was performed. Observations of truck and car searches were made.
l
.
+
,-
e
. -. _.,. - - -
- - - -,
,p
-.,__,,-_,,,,_
-_.-e.--.,
,.,----,.r---,
,
,w..-,
,
-w
--
,v-y,,-m-,, - '
-t
=--
y e-4p--
- - - * -
w---1--
.
.
'
c.
Access Control Observations of the following items were made:
Identification, authorization and badging
--
l Access control searches
--
Escorting
--
Communications
--
Compensatory measures when required
--
No items of non-compliance were identified.
6.
Followup on IE Bulletins and Circulars Licensee action concerning the following IE Bulletins and Circulars was reviewed to verify that:
The Bulletin or Circular was forwarded to appropriate onsite
--
management.
A review for applicability was performed.
--
When applicable, appropriate corrective actions have been taken
--
or are scheduled to be taken.
And in the case of the IE Bulletins:
Written response (when required) was within the stated time
--
period and contains the required information.
Written response contains adequate corrective action commitments.
--
Information on the licensee's written response was accurate.
--
Corrective action taken by the licensee is as described in the
--
written response.
IEC 80-03, Protection from Toxic Gases The licensee has reviewed this item and will formulate action in his response to the TMI Task Action Plan (TAP) Item III.D.3.4.
The inspector will follow this concern during review of implenien-tation of TAP items.
.
.---
- - -
-
-
-.
.-
-_
.
'
,'
.
i
.
IEC 80-21, Regulation of Refueling Crews
.
The inspector reviewed the licensee's meno dated 10/30/80 and
'
verified that Technical Specifications require a Senior Reactor Operator to supervise core alteration from the refueling deck.
The inspector had no further questions in this area.
t IEC 80-22, Confirmation of Employee Qualification The inspector verified that the licensee's present employment procedures require a contracted background investigation of new
employees, the depth of which is sufficient to confirm the qualification of licensee personnel. The inspector had no
'
further questions in this area.
l IEB 80-05, Vacuum Conditions Resulting in Damage to Holdup Tanks The inspector reviewed the licensee's response (WMY letter 80-91, i
.
June 6, 1980). Followup in this area was conducted by review of system drawings and actual installation. The inspector verified
'
that the specified tanks were constantly vented and that fluid
>
removal rates versus vent capacity was evaluated in terms of tank negative pressure design specifications. The inspector h:d no further questions in this area.
,
The licansee's evaluation / corrective actions for the above listed Bulletins and Circulars were appropriate.
7.
Observation of Maintenance and Surveillance Testing t
a.
The inspector observed various maintenance and problem investi-
gation activities. The inspector reviewed these activities to verify compliance with regulatory requirements, including those stated in the Technical Specifications; compliance with applicable l
codes and standards; required QA/QC involvement; proper use of safety tags; proper equipment alignment and use of jumpers; appropriate personnel qualifications; proper radiological controls for worker protection; adequate fire protection; and appropriate i
retest requirements. The inspector also ascertained reportability
,
i as required by Technical Specifications.
The following maintenance items were reviewed:
Diesel Fire Pump Cooling System repair (MR 0028 & 0038)
'
--
Primary Component Cooling Pump repair (MR-0168)
l
--
!
i
.
e,*.a
--
-w.-
,,,, - -, - -----r--
,s,e,ese
,,__-m..,w,-.
--,-e,,,-
-wn-m m e,,m,vw wo, r
,-o,,m,
,,__gg--w
__ m - m y w p -m w w ww - w v o w
---~<~-r
,--v&
-_
-
--
. -_
-
..
-
.
.-
, -.
.
s
'
Primary Component Cooling Pumps P9A and P9B were placed out of service one at a time on January 23, 1981 for preventive mainten-ance. Each pump remained out of service for more than two hours.
i Pump P9A was placed out of service for corrective maintenance on January 26, 1981 and remained out of service for 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. Tech-nical Specification 3.6 requires two redundant safeguards trains
to be operable during power operation and specifies "one component i
cooling pump" per train. This specification allows unlimited operation with one of the two pumps available in each train out of service. The secondary component cooling (SCC) system is especially sensitive as it supplies cooling for both emergency diesel generators. Operation (as permitted by Technical Specifi-cations) with only one SCC pump in service places the plant in i
the situation that a single failure of either the remaining SCC pump or its associated diesel generator would disable both safe-guards trains.
In response to the inspectors' concerns, the licen-
,
l see is proposing several changes in the component cooling systems, including supplying cooling water for one diesel generator from the primary component cooling (PCC) system and rearranging pump
-
power supplies. The licensee intends to accomplish these modifi-cations during the next refueling outage. The licensee proposed to take interim measures to verify operability of the diesel generators daily while any component cooling pump is out of service.
The adequacy of the design of the component cooling system and the current Technical Specifications has been referred to IE Headquarters for evaluation (AITS F01004861 ).
This issue is
>
unresolved pending IE/NRR review of the recomended action.
(309/81-03-02).
b.
The inspector witnessed the performance of surveillance testing of selected components to verify that the surveillance te-1 pro-
,
i cedure was properly approved and in use; test instrumentation required by the procedure was calibrated and in use; technical specifications were satisfied prior to removal of the system l
from service; test was performed by qualified personnel; the procedure was adequately detailed to assure performance of a satisfactory surveillance; and, test results satisfied the pro-cedural acceptance criteria, or were properly dispositioned.
The inspector witnessed the performance of:
l Auxiliary Feedwater Pump Testing (SP 3.1.5)
--
Engineered Safeguards Monthly Surveillance (SP 3.1.2)
j
--
l
m.
t
Control Element Assembly Exercisir.g (SP 3.1.8)
--
ReactorCoolantChemistryTest(TS4.2.1)
--
No abnormal conditions were identified.
8.
Shipment of Radioactive Materials The inspector observed the preparation, loading and survey of solidi-fied liquid radioactive waste for transportation to Barnwell, S.C.
The following documentation was reviewed:
Shipment records:
Serial #0181-146A, January 6, 1981 Serial #0181-147A, January 6, 1981 Serial #0181-148A, January 13, 1981 Serial #0181-416A, January 13, 1981 Maine Yankee Procedure 9.1.15 Rev 6. Shipment of Radioactive Material The inspector verified that the shipment met Department of Transpor-tation requirements for placerding and external dose limits. Records show that proper notifications were made in accordance with procedure 9.1.15.
No items of non-compliance were identified.
9.
Unresolved Items Unresolved items are matters about which more information is required in order to determine whether they are acceptable items or items of non-compliance. Unresolved items identified during this inspection j
are discussed in paragraphs 3b and 7.
10.
Exit Interviews At periodic intervals during the course of the inspection, meetings were held with senior facility management to discuss the inspection scope and findings.