IR 05000289/1986023
| ML20210V517 | |
| Person / Time | |
|---|---|
| Site: | Crane |
| Issue date: | 01/28/1987 |
| From: | Anderson C, Krasopoulos A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | |
| Shared Package | |
| ML20210V483 | List: |
| References | |
| 50-289-86-23, NUDOCS 8702190040 | |
| Download: ML20210V517 (16) | |
Text
%
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
Report No.
50-289/86-23 Docket No.
50-289
,
License No. DPR-50 Category C Licensee: GPU Nuclear Corporation P. O. Box 480 Middletown, Pennsylvania 17057 Facility Name: Three Mile Island, Unit 1 Inspection At: Middletown, PA Inspection Conducted: December 15-19, 1986 Inspectors:
,
daAr/
/
/ A A fiz A.' Krasopoulos,' Fire Protection Engineer date Also participating and contributing to the report were:
R. Hodor, Mechanical Systems Specialist, BNL K. Parkinson, lectrical Systems Specialist, Sonalyst Inc.
D. Kubicki F rotection Engineer, NRR
/2.P/71 Approved by:
C C. J.V Anderson, Chief date Plant Systems Section, DRS Inspection Summary:
Inspection on December 15-19, 1986 (Report No. 50-289 86-23)
Areas Inspected: Special, announced team inspection of the licensee's efforts to comply with the requirements of 10 CFR 50, Appendix R, Sections III.G, J, and 0, concerning fire protection features to ensure the ability to achieve and maintain safe shutdown in the event of a fire.
Results: One violation was identified [ failure to install emergency lights in the Control Room in accordance with the schedular guidelines of 10 CFR 50.48 (c)(2)]. Three items remained unresolved at the end of the inspection.
8702190040 870211 PDR ADOCK 05000289 O
,
.
-
--.
.
-.
.
.
.
DETAILS 1.0 Persons Contacted 1.1 General Public Utilities Nuclear Cc*poration (GPUN)
- R. Barth, Fire Protection Engineer G. Busch, Licensing Engineer R. Campe11, Control Room Operator
- J. Colitz, Plant Engineering Director
- D. Distel, PWR Licensing
- J. Garrison, MCF
- B. Gan, Projects Engineer T. Goodlavage, Shift Foreman C. Good, Assistant Operator
- G. Gurican, Technical Consultant E. Hammond, NSCC Staff Director
- C. Hartman, Manager, Plant Engineering H. Henry, Quality Assurance
- H.
Hukill, Director, TMI-1 J. Langenbach, Project Engineering Director J. Mancinelli, Manager, EQ/ Fire Protection
- J. Mateychick, Project Engineer
- R. McGeey, Manager, PWR Licensing P. Moor, Projects T. O'Connor, Nuclear Safety Engineer
- S. Otto, Licensing Engineer
,
D. Reese, Control Room Operator M. Ross, Plant Operations Director F. Perry, Support Training Manager C. Shurds, Manager, Technical Functions
- H. Shipman, Operations Engineer
- J. Siegel, Fire Protection Engineer C. Smyth, Licensing Manager
- R. Toole, Operational and Maintenance Director K. Zimmermann, Fire Protection Coordinator 1.2 Gilbert Commonwealth (G.C.)
i
- J. Brenden, Jr., Project Engineering Manager
'
J. Mangeno, Fire Protection Engineer D. Stevens, Project Mechanical Engineer J. Strasser, Fire Protection Engineer
- R. Smith, Project Manager
'
- A. Thaik, Electrical Engineer l
!
!
l
_
_
_ __
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
l
.
.
l 1.3 U.S. Nuclear Regulatory Commission (NRC)
- C. Anderson, Chief, Plant Systems Section
- R. Conte, Senior Resident Inspector
- J. Rogers, Resident Inspector
- F. Young, Resident Inspector
- Denotes those present at the exit meeting.
2.0 Purpose This inspection was to ascertain that the licensee is in conformance with 10 CFR 50, Appendix R, Sections III.G, J, and 0, including exemptions approved by the Office of Nuclear Reactor Regulation (NRR).
3.0 Background 10 CFR 50.48 and 10 CFR 50, Appendix R became effective on February 17, 1981.
Section III.G of Appendix R requires that fire protection be provided to ensure that one train of equipment necessary to achieve and maintain safe shutdown remains available in the event of a fire at any location within a licensed operating facility.
For hot shutdown condi-tions, one train of the systems necessary must be free of fire damage (III.G.I.a).
For cold shutdown conditions, repair is allowed using in place procedures and materials available onsite with the provision that cold shutdown be achievable within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> of the initiating event (III.G.1.b).Section III.G.2 lists specific options as follows to provide adequate protection for redundant trains of equipment located outside of the primary containment:
Separation by a fire barrier having a three hour rating (III.G.2.a).
- Separation by a horizontal distance of at least 20 feet with no intervening combustibles and with fire detection and automatic fire suppression installed in the fire area (III.G.2.b).
- Enclosure of one train in a fire barrier having a one hour rating in addition to having fire detection and automatic suppression installed in the fire area (III.G.2.c).
For non-inerted primary containment,Section III.G.2 specifies one of the above three protection opcions, or any of the following:
Separation by a horizontal distance of at least 20 feet with no intervening combustibles or fire hazards (III.G.2.d).
Fire detection and automatic fire suppression installed in the fire area (III.G.2.e).
- Separation of redundant trains by a non-combustible radiant energy shield (III.G.2.f).
.
.
.
.
If the protection required by Section III.G.2 is not provided or the systems of concern are subject to damage from fire suppression activities,Section III.G.3 of the rule requires that ar. alternate or dedicated shut-down capability be provided which is independent of the area of concern.
Any alternate or dedicated system requires NRC review and approval prior to implementation.
For situations in which fire protection does not meet the requirements of Section III.G, however, such protection is deemed to be adequate by the licensee for the specific situation, the rule allows the licensee to request an exemption on a case-by-case basis.
Such exemption requests are submitted to the NRC for review and approval and must be justified by the licensee on a technical basis.
4.0 Correspondence Correspondence between the licensee and the NRC concerning compliance with Sections III.G, J, and 0 was reviewed by the inspection team in prepara-tion for the site visit. Attachment 1 to this report is a listing of the correspondence reviewed.
5.0 Post Fire Safe Shutdown Capability 5.1 Systems Required For Safe Shutdown In the event of a fire and loss of off site power, the following systems will be used to achieve safe shutdown for the Three Mile Island Unit I reactor.
Shutdown of the reactor and reactivity control will be performed by rod insertion from the control room.
Reactor coolant inventory and long term reactivity control will be maintained by the makeup system.
Primary system pressure control will be maintained by the pressurizer heaters or, if they are unavailable because of fire damage, by let-down flow and the makeup system. The pressurizer spray will be available for primary depressurization during cold shutdown.
For a fire in any plant area, except the motor driven Emergency l
Feedwater (EFW) Pump Room and the " Alligator Pit" (fire zones 1B-FZ-3 and IB-FZ-8), decay heat removal during hot shutdown will be accomp-lished by the emergency feedwater system, main steam safety valves, and atmospheric dump valves.
For a fire in the motor driven Pump Room or the Alligator Pit, the initial decay heat removal will be l
accomplished by the use of the high pressure injection cooling via the makeup system (Feed and bleed method).
Using feed and bleed, the i
licensee can operate in this mode for about 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br />, however, once the fire is extinguished and the operators can gain entry into the j
motor driven EFW Pump Room the EFW steam driven pump can be manually
'
started from this room to provide EFW flow to the steam generators, l
which is the preferred method of decay heat removal.
!
L
-
.
.
Natural circulation of the primary coolant must be relied upon in hot shutdown. Decay heat removal during cold shutdown would be accomp-lished by the decay heat removal system, decay heat closed cooling water system, and decay heat river water systcm.
5.2 Plant Fire Areas / Fire Zones TMI-1 is divided into fire areas and fire zones.
The fire areas are separated from other plant areas by either rated fire barriers or approved alternatives.
The fire zones are subdivisions of fire areas whose boundaries have no fire rating but because of the fire protec-tion provided in the zone, or other mitigating factors such as component separation or lack of intervening combustibles it is logi-cal to postulate that smoke and fire will not propagate through the zone boundary.
On the bases of adequate technical justification, the fire zones described by the licensee are considered fire areas for the purpose of determining compliance with Appendix R.
Attachment 3 provides a listing of the fire areas / fire zones for TMI-1.
5.3 Areas Where Alternate Safe Shutdown Is Required The licensee will provide alternate shutdown capability for the Control Room, Relay Room (cable spreading room), and the Engineered Safeguards Actuation Cabinet (ESAS) Room.
With regard to the latter, the licensee did not provide NRC with adequate information to enable the staff to make a determination on the adequacy of the proposed alternative safe shutdown capability for a fire in this area, therefore since this area is still under review by NRR, the team did not inspect this room for compliance with Appendix R.
The alternative shutdown for a fire in the Control Room or the Relay Room will be accomplished with actions performed at the Remote Shutdown Transfer Switch Panels (RSTSP A, B, and C), Remote Shutdown Panels A & B, Auxiliary Remote Shutdown Panel (Auxiliary RSP), Diesel Generator B Remote Shutdown Panel and the Remote Shutdown Stations listed in Table 5.3-1.
The licensee alternative shutdown capability utilizes the "B" train systems and equipment.
The "B" channel RSTSP is located on elevation 322 feet of the control building in area CB-FA-28.
The redundant "A" channel RSTSP is installed on elevation 338 feet 6 inches of the control building in area CB-FA-3C.
For a fire in the control room, relay room, and ESAS room, the operators will close transfer switches on both of these panels to isolate control circuits and to transfer control of shut-
.-.
.
.
'
down equipment to the Remote Shutdown Panel (RSP). Transfer from the
"A" RSTSP is provided for convenience only since the "A" diesel generator is not electrically protected and can not be electrically isolated.
The Remote Shutdown Panels located at CB-FA-2C provide the capability to monitor the key process variables listed in Table 5.3-2 and to control the atmospheric dump valves and emergency feedwater pump.
Separate panels containing signal conditioning and circuit isolation transfer switches are also provided for the functions at the RSP.
The Auxiliary RSP located at CB-FA-2C contains the control and indi-cation for the secondary plant systems, listed ih Table 5.3-2.
The Diesel Generator B Remote Shutdown Panel is installed near the IE-4160V ES switchgear to house the equipment relocated from the control room for diesel generator IB.
,
l REMOTE SHUTDOWN CONTROL STATIONS TABLE 5.3-1 Equipment Location Elevations 4160 V Swgr IE CB-FA-3b 338 480 V Swgr IS CB-FA-2b 322 6900 V Swgr - 1A2 Turb Bldg Elev 322 IB2
"
"
1A3
"
"
183
"
"
480 V-ESV MCC 1A AB-FZ-6 305 480 V-ESV MCC IB AB-FZ-6a 305 480 V ES MCC 18 CB-FA-2b 322 York Control Panel for Chiller AH-C4B Control Bldg Elev 305 i
l
-
.
..
_
.
..
...
.
REMOTE SHUTDOWN PANEL INSTRUMENTATION TABLE 5.3-2 Source Range Instrumentation Reactor Coolant Inlet Temperature Reactor Coolant Outlet Temperature Reactor Coolant Pressure Pressurization Level EFN Flow to OTSG Steam Generator Level Steam Generator Pressure Makeup Tank Level Borated Water Storage Tank (BWST) Level Decay Heat Removal System Inlet Temperature Decay Heat Removal System Outlet Temperature Decay Heat Removal System Flow Temperature Remote Shutdown Panel Instrumentation REMOTE SHUTDOWN SYSTEM CONTROL AND MONITORING FACILITIES TABLE 5.3-3 Control / Instrumentation Component Facility Facility Location Communication System M/I System (HEAD SET)
Status Indication
"B" Aux. RSP Gray System (Page)
Status Indication
"B" Aux. RSP 480V Feeder to Screen House Control
"B" Aux. RSP l
"B" Aux. RSP i
480V Feeder to IB ES Control
"B" Aux. RSP l
Screen House MCC Status Indication
"B" Aux. RSP
!
Decay Heat Closed Control Aux. RSP "B" Cycle Pump DC-P-1B Status Indication Aux. RSP "B" Intermediate Cooling Control Aux. RSP "B" Pump IC-P-1B Status Indication Aux. RSP "B" l
Nuclear Services Control Aux. RSP "B"
'
Cooling Pump Status Indication Aux. RSP "B" NS-P-1C Nuclear Service Control Aux. RSP "B" River Water Pump Status Indication Aux. RSP "B" NR-P-1C RR-P-1B Discharge Valve Control Aux. RSP "B" l
RR-V-1B Status Indication Aux. RSP "B" l
!
\\
!
'.
.
5.4 Remaining Plant Areas All other areas of the plant not required to have an alternate safe shutdown system must comply with the requirements of Section III.G.2 of Appendix R, unless an exemption request is approved by the staff.
6.0 Inspection Methodology The inspection team examined the licensee's capabilities for separating and protecting equipment, cabling and associated circuits necessary to achieve and maintain hot and cold shutdown conditions.
This inspection sampled selected fire areas which the licensee had identified as being in compliance with Section III.G.
The following functional requirements were reviewed for achieving and maintaining hot and cold shutdown:
Reactivity control
Primary coolant makeup
Support systems
Process monitoring The inspection team examined the licensee's capability to achieve and maintain hot shutdown and the capability to bring the plant to cold shut-down conditions in the event of a fire in various areas of the plant. The examination included a review of selected drawings, safe shutdown proce-dures and other documents. Drawings were reviewed to verify electrical independence from the fire areas of concern. Procedures were reviewed for general content and feasibility.
Also inspected were fire detection and suppression systems and the degree of physical separation between redundant trains of Safe Shutdown Systems (SSSs). The team review included an evaluation of the susceptibility of
'
the SSSs for damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems.
l The inspection team examined the licensee's fire protection features j
provided to maintain one train of equipment needed for safe shutdown free l
of fire damage.
Included in the scope of this effort were fire area boun-l daries, including walls, floors and ceilings, and fire protection of open-ings such as fire doors, fire dampers, and penetration seals.
The inspection team also examined the licensee's compliance with Section l
III.J, Emergency Lighting, and Section III.0, Oil Collection System for i
Reactor Coolant Pump.
I
!
l
l l
l t
.
.
7.0 Inspection of Protection Provided to Safe Shutdown Systems 7.1 Protection in Various Fire Areas The team reviewed the protection provided to safe shutdown components in all plant areas for compliance with Appendix R,Section III.G 1, 2, and 3 with the exception of systems not yet installed and issues awaiting resolution by NRR.
The team did not identify any unacceptable conditions.
7.2 Safe Shutdown Procedures 7.2.1 Procedure Review The team reviewed Procedure 1202-37, revision 26, (draft),
titled "Cooldown From Outside the Control Room."
The scope of this review was to ascertain that the shutdown could be attained in a safe and orderly manner, to deter-mine the level of difficulty involved in operating equip-ment, and to verify that there was no dependence on repairs for achieving hot shutdown.
For review purposes, a repair may include installing electrical or pneumatic jumpers, wires or fuses to perform an action required for hot shut-down.
For cold shutdown, repairs are allowed using in place procedures and materials available onsite with the provision that cold shutdown be achievable within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />.
The team did not identify any unacceptable conditions.
7.2.2 Procedure Walk-Through The team walk-througn selected portions of Procedure 1202-37 "Cooldown from outside the Control Room" to deter-mine by simulation that shutdown from outside the Control Room could be attained in an orderly and timely fashion.
The procedure walk-through involved 5 operators with 3 inspection team members observing.
Because the procedure is still in draft form some of the secondary steps were performed out of sequence so that the entire team could participate and observe the more significant portions of the procedure.
The procedure was followed through from the start until simulated stable hot shutdown conditions were achieved and cooldown was started. The team paid particu-lar attention to the feasibility of each manual action, ease of access, communication and sequence of operation.
The team observed that the procedure in its draft form relies on many manual actions involving the use of many keys, opening and closing breakers and relays and reposi-tioning valve.
.
,
The licensee stated that the procedure will be " stream-lined" especially in the area of using the number of keys required to operate various equipment.
The team indicated to the licensee that the procedure will be reviewed again in its final form when the operators are trained in it.
The licensee also stated that they plan to perform a controlled plant cooldown from outside the Control Loom during restart.
The cooldown will be initiated after normal reactor temper-ature is reached during restart.
The licensee will use the safe shutdown components installed outside the Control Room for compliance with Appendix R to decrease the average Reactor Coolant Temperature by approximately 20 F to 30 F.
The above are collectively categorized as an Unresolved Item pending a review of the finalized procedure and tests, by NRC.
(50-289/86-23-01)
The team did not identify any other deficiencies.
7.3 Protection for Associated Circuits Appendix R,Section III.G, requires that protection be provided for associated circuits that could prevent operation or cause malopera-tion of redundant trains of systems necessary for safe shutdown.
The circuits of concern are generally associated with safe shutdown circuits in one of three ways:
Common bus concern
'
Spurious signals concern Common enclosure concern The associated circuits were evaluated by the team for common bus, spurious signals, and common enclosure concerns. Power, control, and instrumentation circuits were examined for potential problems.
t 7.3.1 Common Bus Concern l
The common bus concern is found in circuits, either safety l
related or non-safety related, where there is a common power source with shutdown equipment and the power source is not electrically protected from the circuit of concern.
The team examined, on a sampling basis, 4160V, 480V, 250V DC and 125V DC bus protective relay coordination. The team also examined, on a sampling basis, the protection for i
i
_.
.
-.
.
specific instrumentation, controls, and power circuits, including the coordination of fuses and circuit breakers.
The licensee has been performing relay settings at approxi-mately 18 and 48 month intervals.
No unacceptable conditions were identified.
7.3.2 Spurious Signals Concern The spurious signals concern is made up of 2 items.
- False motor, control, and instrument indications can occur such as those encountered during 1975 Brown's Ferry fire. These could be caused by fire initiated grounds, short or open circuits.
- Spurious operation of safety related or non-safety related components can occur that would adversely affect shutdown capability (e.g., RHR/RCS isolation valves).
The team examined, on a sampling basis, the following areas to ascertain that no spurious signal concerns exist:
Current transformer secondaries
High/ low pressure interfaces
General fire instigated spurious signals No unacceptable conditions were identified.
7.3.3 Common Enclosure Concern The common enclosure concern is found when redundant circuits are routed together in a raceway or enclosure and they are not electrically protected or when fire can destroy both circuits due to inadequate fire barrier pene-trations.
The common enclosure concern is currently being discussed with NRR and has not been resolved as yet. The team leader emphasized to the licensee the importance of resolving this concern prior to restart.
The licensee indicated that an analysis similar to analyses previously accepted by NRC
'
will be proposed in the discussion with NRR to resolve this-issue.
No other unacceptable conditions were identifie.
7.4 General Fire Protection Features The team examined the general fire protection features in the plant provided to maintain one train of safe shutdown equipment free of fire damage.
Included in the scope of this effort were fire area boundaries, including walls, floors, and ceilings, and fire protec-tion of openings such as fire doors, fire dampers, and penetration seals, fire protection systems, and other lire protection features.
No unacceptable conditi s were identified, however, the team observed that since the cabinet in the Control Room is being upgraded to safety rela
, a detection system within the cabinet is required to satisfy the commitment made by the licensee to provide detection in all safety related cabinets in the Control Room.
The licensee agreed with the team's observation.
The licensee also agreed to maintain the screen house fire door closed, to increase the level of protection in the area. The door was previously held open by a fusible link.
8.0 Emergency Lighting 10 CFR 50, Appendix R, Section III.J, requires that emergency lighting units with at least an 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> battery power supply shall be provided in all areas needed for operation of safe shutdown equipment and in access and egress routes thereto, unless an exemption from this requirement was approved.
The emergency light installation is a modification that usually does not require plant shutdown. However, the installation of emergency lights in some plant areas may depend on NRC approval of the safe shutdown modifica-tions for the particular area.
10 CFR 50.48 (c)(2) requires that those fire protection modifications that do not require prior NRC approval or plant shutdown shall be implemented within nine months after the effective date of 10 CFR 50.48 and Appendix R.
By letters dated May 10, 1982 and March 9,1983, Eisenhut (NRC) to Hukill (GPU), the licensee was informed that the effective date of the rule for TMI-1 was July 1,1982.
The team examined the plant emergency lighting system to ascertain the licensee's compliance with the above requirements.
The team identified the following conditions: The licensee in the Main Control Room area does not have any emergency lights.
Instead of emer-gency lighting in the Control Room, the licensee opted to use the Diesel Generators as a dedicated power source for the Control Room lighting. A recent review of this system by the licensee identified that a fire in either of two areas CB-FA-1 and FH-FZ-5 may render this system inoperable because the power supply to the Control Room lighting from both diesels is run through these two area __
.
The team observed that the licensee does not meet the schedular require-ments of 10 CFR 50.48 (c)(2) because they did not install emergency lights in the Control Room as required by 10 CFR 50, Appendix R, Section III.J and the proposed alternative means of emergency lighting could not be relied upon for a fire in fire areas CB-FA-1 and FH-FZ-5 (control building patio). This is a violation. (86-23-02) Additionally, a number of other areas used for hot shutdown operations were not provided with emergency lights. These areas are the P and S Bus Room, the IE 4160 Switchgear Room, the ESAS Room, the Valve Alley, the Mint Valve Alley and the IB&S Valve MCC area in Auxiliary Building EL.305.
During the inspection it could not be ascertained whether the lighting for these areas is dependent on NRC approval of modifications in the area or was an oversight by the licensee. This is an Unresolved Item pending a review of the licensee's rational for not placing emergency lights in these areas (86-23-03)
9.0 011 Collection System for Reactor Coolant Pump 10 CFR 50, Appendix R, Section III.0, requires that the reactor coolant pump shall be equipped with an oil collection system if the containment is not inerted during normal operation. The oil collection system shall be so designed, engineered, and installed that failure will not lead to fire during normal or design basis accident conditions and that there is reasonable assurance that the system will withstand the Safe Shutdown Earthquake.
Such collection systems shall be capable of collecting lube oil from all potential pressurized and unpressurized leakage sites in the reactor cool-ant pump lube oil systems.
Leakage shall be collected and drained to a vented closed container that can hold the entire lube oil system inven-l tory. A flame arrester is required in the vent if the flash point charac-teristics of the oil present the hazard of fire flashback.
Leakage points to be protected shall include lift pump and piping, overflow lines, lube oil cooler, oil fill and drain lines and plugs, flanged connections on oil lines, and lube oil reservoirs where such features exist on the reactor coolant pumps. The drain line shall be large enough to accommodate the largest potential oil leak.
i The team inspected the Reactor Coolant Pump (RCP-1A) and observed that some copper tubing installed for instrumentation purposes did not appear to be supported seismically. A rupture of this tubing could cause a loss of the entire lube oil inventory contained in the RCP (approximately 120 gallons).
The licensee is reviewing the engineering records for this system to ascertain whether this tubing has been seismically analyzed and will withstand a safe shutdown earthquake. This is an Unresolved Item l
pending a review of the engineering records to be provided by the licensee.
(86-23-04)
<
-.
.
10.0 Quality Assurance During the course of the inspection, the team reviewed several drawings, the fire hazard analysis, fire protection modification packages, proce-dures, and other fire protection documents. The scope of review included verification of their technical adequacy, appropriate reviews, design and procurement controls, and other Quality Assurance requirements for the licensee's fire protection program.
The team did not identify any unacceptable conditions.
11.0 Unresolved Items Unresolved items are matters for which more information is required in order to ascertain whether they are acceptable, violations, or deviations.
Unresolved Items are discussed in Sections 7.2, 8.0, and 9.0 of this report.
12.0 Conclusions The findings of this inspection are summarized in Attachment 2.
One violation was identified and three items remained unresolved.
In addi-tion, the licensee committed to make the changes described in Section 7.4 to be consistent with their commitments.
13.0 Exit Interview The inspection team met with the licensee representatives, denoted in Paragraph 1, at the conclusion of the inspection on December 19, 1986.
The team leader summarized the scope and findings of the inspection at that time.
The team leader and the licensee discussed the contents of this inspection report to ascertain that it did not contain any proprietary information.
The licensee agreed that the inspection report may be placed in the Public Document Room without prior licensee review for proprietary information (10 CFR 2.790).
At no time during this inspection was written material provided to the i
licensee by the team.
.
,
, - - - _ - - -,,,, - - - - - - - - - -, - -
,
- - -
-
-
-.
,
.
ATTACHMENT 1 LIST OF CORRESPONDENCE FROM GPUN TO NRC Date of letter Letter Subject / Description November 20, 1986 10 CFR 50, Appendix R, Clarification of Compliance November 19, 1986 Exemption Request from Appendix R,Section III.J November 19, 1986 10 CFR 50, Appendix R, Emergency Lighting October 22, 1986 Clarification of Compliance Multiple High Impedance Faults August 19, 1986 Exemption Requert from Appendix R,Section III.J July 22, 1986 Clarification of Compliance, Remote Shutdown System, SDD May 17, 1986 Exemption Request to 10 CFR 50, Appendix R.
December 6, 1985 TMI-1 Fire Brigade Training November 7, 1985 Fire Hazard Analysis Report, Safe Shutdown Evaluation, Revision 7 February 11, 1985 Appendix R, Sample Exemption Request, Rockbestos January 7,1984 Fire Protection Program Plan November 30, 1983 Fire Proof Cable Development and Test Program July 1, 1982 Fire Protection FROM NRC TO GPUN June 4, 1984 SE of Exemption Request March 15, 1984 Fire Proof Cable Test Program March 9, 1983 Schedular Exemption Request for 10 CFR 50.48 May 17, 1982 Schedular Exemption Request for 10 CFR 50.48 i
i
,
+
-- - - - -, - _.
,, _ _ _, - - -,
-
_,_
7.._
.. _,_
--
-4
,,
_ _
_
. _. _ _
.
,
.
ATTACHMENT 2 Summary of Inspection Findings For Details Item No.
Description Refer to Section 1.
Violations
'
86-23-02 Failure to install emergency lights 8.0 in the Control Room following the schedular guidelines of 10 CFR 50.48 (c)(2).
2.
Unresolved Items 86-23-01 NRC to review the finalized procedure 7.2.2 to cooldown from outside the Control Room
,
and observe the cooldown from outside the Control Room test during restart.
86-23-03 Licensee to verify that lack of emergency 8.0 lights in the areas described in the report was dependent on NRC approval of modifica-tions for the area.
86-23-04 Licensee to verify that the instrumentation 9.0
'
tubing on the reactor coolant pump will not fail during a seismic event.
-
,
..-m..
-, _
. _.. _. - _ _ _ _. _ _ _ _ _ - _ _, _. _ _. _ _. _ _ _.. _, _ _ _ _ _
.