| | Title | Significance | Cross cutting aspect |
|---|
| 05000285/FIN-2013013-01 | Failure to Complete all Testing for a Condition Adverse to Quality | Green | H.1 |
| 05000285/FIN-2013013-02 | Failure to Furnish Evidence of an Activity Affecting Quality | Green | H.7 |
| 05000285/FIN-2013013-03 | Failure to Evaluate Changes to Ensure They Did Not Require Prior Approval | Green | |
| 05000285/FIN-2013013-04 | Failure to Submit Licensee Event Report | Severity level IV | |
| 05000285/FIN-2013013-05 | Inadequate Corrective Actions to Prevent Repetition of a Significant Condition Adverse to Quality, a White MSPI SSFF Degrading Trend | Green | P.2 |
| 05000285/FIN-2013013-06 | Failure to Control Deviations From the Design Basis Requirements for Structural Calculations Related to the Reactor Coolant System | Green | |
| 05000285/FIN-2013013-07 | Programmatic Failure to Evaluate Safety Impact of Degraded Conditions During Use of Interim Operability Criteria | Green | H.8 |
| 05000285/FIN-2013013-08 | Failure to Correct Overstressed Components | Green | P.1 |
| 05000285/FIN-2013013-09 | Non-conservative Criteria in Operability Procedure | Green | |
| 05000285/FIN-2013013-10 | Failure to Follow Operability Procedure | Green | H.14 |
| 05000285/FIN-2013013-11 | Failure to Evaluate the Effects of Modifying the Turbine Driven Auxiliary Feedwater Pump | Green | H.14 |
| 05000285/FIN-2013013-12 | Failure to Perform Adequate Operating Experience Reviews | Green | P.5 |
| 05000285/FIN-2013013-13 | Failure to Incorporate Design Requirements for Switchgear Room Cooling | Green | P.2 |
| 05000285/FIN-2013013-14 | Inadequate Corrective Action for Non-Seismic Category 1 Piping | Green | H.14 |
| 05000285/FIN-2013013-15 | Lack of an Adequate Operability Evaluation for Class 1 Raw Water Piping in Non-Class 1 Service Building | Green | P.2 |
| 05000285/FIN-2013013-16 | Inadequate Operability Determination Due to Failure to Consider an Unavailable Raw Water Pu | Green | H.5 |
| 05000285/FIN-2013013-17 | Failure to Translate Design Sluice Gate Leakage Into Operating Procedure | Green | P.2 |
| 05000285/FIN-2013013-18 | Inadequate Procedure for Intake Cell Level Control During a Flooding Event | Green | P.2 |
| 05000285/FIN-2013013-19 | Failure to Translate Appendix R license Exemptions into the Plants Fire Protection Program Design | Green | |
| 05000285/FIN-2013013-20 | Failure to Provide Complete and Accurate Information to the NRC | Green | |
| 05000285/FIN-2013013-21 | Failure to Perform Adequate Extent of Condition Reviews | Green | P.2 |
| 05000285/FIN-2013013-22 | Shutdown Cooling Piping and Pipe Supports Calculation Has Incorrect Acceptance Criteria for Anchor Displacement | | |