IR 05000275/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000275/2024004 & 05000323/2024004
ML25015A030
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 01/15/2025
From: Patricia Vossmar
NRC/RGN-IV/DORS/PBA
To: Gerfen P
Pacific Gas & Electric Co
References
IR 2024004
Download: ML25015A030 (1)


Text

January 15, 2025

SUBJECT:

DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000275/2024004 AND 05000323/2024004

Dear Paula A. Gerfen:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Diablo Canyon Power Plant, Units 1 and 2. On January 13, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety Docket Nos. 05000275 and 05000323 License Nos. DPR-80 and DPR-82

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000275 and 05000323

License Numbers:

DPR-80 and DPR-82

Report Numbers:

05000275/2024004 and 05000323/2024004

Enterprise Identifier:

I-2024-004-0008

Licensee:

Pacific Gas and Electric Company

Facility:

Diablo Canyon Power Plant, Units 1 and 2

Location:

Avila Beach, CA

Inspection Dates:

October 1, 2024, to December 31, 2024

Inspectors:

E. Garcia, Resident Inspector

M. Hayes, Senior Resident Inspector

D. You, Operations Engineer

Approved By:

Patricia J. Vossmar, Chief

Reactor Projects Branch A

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Diablo Canyon Power Plant, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000323/2024001-07 Auxiliary Building Ventilation Inoperable Coincident with Redundant Train Diesel Generator Maintenance Outage 71153 Closed LER 05000323/2024-001-00 LCO 3.0.3 Completion Time Limits 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On October 5, 2024, the unit reduced power to 50 percent to support condenser cleaning. The unit returned to full power on October 7, 2024. The unit remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 auxiliary saltwater pump 1-1 on October 2, 2024
(2) Units 1 and 2 auxiliary feedwater cross tie to firewater on November 15, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 2 radiological control area, 115-foot elevation, on October 2, 2024
(2) Unit 1 emergency diesel generator rooms 1-1, 1-2, and 1-3 on October 30, 2024
(3) Unit 2 emergency diesel generator rooms 2-1 and 2-2 on November 15, 2024
(4) Unit 2 vital 480 V switchgear rooms on December 11, 2024

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from September 17, 2024, to October 25, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a crew of licensed operators during simulator training on October 1, 2024.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Yellow risk due to emergency diesel generator 1-3 planned maintenance on October 14, 2024 (2)inadvertent VANS notification made to emergency response organization on November 19, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 1 reliability of support systems necessary for emergency diesel generators 1-1 and 1-2 during the maintenance on emergency diesel generator 1-3 on October 16, 2024
(2) Unit 1 update to the probability risk assessment model and how it effects risk informed completion time on October 21, 2024
(3) Unit 1 dual indication on emergency diesel generator 1-3 fuel transfer start circuit on October 29, 2024
(4) Unit 2 main feedwater pump 2-2 lube oil pump 1 thermal anomaly on November 25, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)reducing number of protected emergency diesel generators from three to two during an offsite power radial feed on December 9, 2024

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1) Unit 1 auxiliary saltwater pump 1-2 and component cooling water heat exchanger 1-2 return to service following testing on October 1, 2024
(2) Unit 1 emergency diesel generator 1-3 following overhaul and extended on-line maintenance on October 21, 2024
(3) Unit 1 and 2 diesel fuel oil transfer pump 0-1 following filter and fuse replacements on October 23, 2024
(4) Unit 2 centrifugal charging pump 2-1 following maintenance on December 3, 2024
(5) Unit 2 auxiliary building ventilation supply and exhaust fans following sensor modification on December 11, 2024
(6) Unit 2 component cooling water pump 2-3 following breaker maintenance on December 18, 2024

Surveillance Testing (IP Section 03.01) (3 Samples)

(1) Unit 1 Surveillance Test Procedure P-SIP-11, "Routine Surveillance Test of Safety Injection Pump 1-1," on October 8, 2024
(2) Unit 2 Surveillance Test Procedure P-AFW-23, "Routine Surveillance Test of Motor-Driven Auxiliary Feedwater Pump 2-3," on November 5, 2024
(3) Unit 1 Surveillance Test Procedure P-CCW-A11, "Comprehensive Pump Test of Component Cooling Water Pump 1-1," on November 6, 2024

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) The inspectors evaluated a tabletop emergency preparedness drill on November 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)review of oil misting onto safety-related cables in inverter rooms on December 17, 2024

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in auxiliary building ventilation fans failing to start on demand during periods of high rain that might be indicative of a more significant safety issue. The inspectors reviewed the design change package which modified flow switches associated with the starting circuit of the auxiliary building ventilation fans. The inspectors also reviewed the failures to ensure they were properly documented in the maintenance rule program. Overall, the inspectors determined the licensee properly documented the failures of auxiliary building ventilation fans to start and took appropriate corrective actions.

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) LER 05000323/2024-001-00, "LCO 3.0.3 Completion Time Limits" (ADAMS Accession No. ML24141A032). The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensee's ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is Closed.

INSPECTION RESULTS

Unresolved Item (Closed)

Auxiliary Building Ventilation Inoperable Coincident with Redundant Train Diesel Generator Maintenance Outage URI 05000323/2024001-07 71153

Description:

On March 18, 2024, during a planned maintenance outage of Unit 2 emergency diesel generator (DG) 2-2, auxiliary building ventilation system (ABVS) fan E-1 tripped off on thermal overload and was declared inoperable. The redundant ABVS fan E-2 started automatically and was supported by DG 2-2, which was inoperable due to the planned maintenance outage. Technical specification (TS) limiting condition for operation (LCO) 3.8.1, condition B, required action B.2 requires declaring equipment supported by the inoperable DG inoperable when the redundant equipment on the other train is inoperable, within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of discovery of the condition. After condition B, required action B.2 was applied, operators declared ABVS fan E-2 inoperable in accordance with TS LCO 3.7.12 (the TS for ABVS).

TS LCO 3.7.12 does not describe a required action for two inoperable ABVS trains.

Therefore, TS LCO 3.0.3 was entered, and the licensee was required to be in Mode 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> of applying TS 3.8.1.B.2.

The licensee stated that after ABVS fan E-1 failed, their troubleshooting investigation identified slight discoloration of the C phase contactor between the breaker and the contactor on the load side downstream of the breaker. Voltage, current, and thermography measurements indicated the cause of the condition was most likely local to the connections between the breaker and the contactor. The licensees immediate corrective actions were to refurbish the copper bus bar between the breaker and the contactor and to replace the fasteners for the bus bar. Additional movable contacts internal to the breaker were replaced with a new contact kit. The equipment was post-maintenance tested, declared operable, and returned to service within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The licensee performed a causal evaluation for the ABVS fan E-1 trip and the circumstances surrounding the request for a Notice of Enforcement Discretion (NOED). It was determined that the cause of the thermal overload condition was due to oxidation buildup in the 480 V breaker cubicle for the E-1 fan. This oxidation buildup occurs over a long period of time through normal breaker operation. The breaker cubicle was last opened and inspected on October 24, 2022, during a Unit 2 refueling outage. The system engineer determined the cubicle to be in acceptable condition after all bolted connections were checked and tightened, loose stab and termination connections were checked SAT, and no signs of overheating or excessive contact wear was discovered. The licensee determined that a NOED was necessary because there was no TS action statement for having two inoperable ABVS trains and it was unlikely that troubleshooting, repair plan development and execution, and returning affected equipment to service could be completed within the 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> prior to declaring redundant equipment inoperable per TS 3.8.1 action B.2.

The inspectors evaluated the licensees immediate corrective actions and causal evaluation of the event, and did not identify any findings or violations of more than minor significance. It was not reasonably within the licensees ability to foresee and correct a thermal overload condition on an ABVS exhaust fan breaker during the coincident redundant train DG maintenance outage prior to the requirements of TS 3.0.3 to be in Mode 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />. The licensee took the necessary steps to request and receive a NOED, conducted maintenance on the affected equipment, and returned the required TS equipment to operable status within the 24-hour period of discretion granted by the NOED. The licensee plans to conduct thermography prior to major DG maintenance windows in the future and are updating their procedures to incorporate this action. Enhanced monitoring and thermography of 480 V breakers will be conducted going forward to preemptively identify issues. Training and procedure updates for breaker cubicle inspections will be performed due to this event. This URI is closed.

Corrective Action References: Notification 51229398, 51229466, and

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 13, 2025, the inspectors presented the integrated inspection results to Paula Gerfen, Senior Vice President, Generation and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

106717-7

Intake Structure for Unit 1

216

106717-7A

Intake Structure for Unit 2

216

Drawings

106717-8

Unit 1 Intake Discharge to Condenser Outlet Flow Diagram

2

EOP FR-C.1

Unit 1 Response to Inadequate Core Cooling

26C

71111.04

Procedures

EOP FR-C.1

Unit 2 Response to Inadequate Core Cooling

19D

Corrective Action

Documents

Notifications

256348

111805-12

Unit 1 & 2 Radiological Control Area (RCA) Elev. 100

111805-22

Unit 2 Radiological Control Area (RCA) Elev. 115'

111805-49

Unit 1 Turbine Building Elev. 85'

111805-60

Unit 2 Turbine Building Elev. 85'

111805-61

Unit 2 Turbine Building Elev. 85'

111906-11

Unit 2 Turbine Building Elev. 85'

111906-12

Unit 2 Turbine Building Elev. 104'

Drawings

111906-6

Unit 1 Turbine Building Elev. 85'

71111.05

Miscellaneous

M-824

Controlled Combustion Loading Tracking Calculation

71111.11A

Miscellaneous

71111.11

71111.11A Table 03.03-1 Examination Results

TQ2.DC3

Licensed Operator Continuing Training Program

TQ2.DC15

Licensed Operator Annual/Biennial Exam Development and

Administration

71111.11Q

Procedures

TQ2.ID4

Training Program Implementation

Corrective Action

Documents

Notifications

226912, 51251460, 51262272

OP J-6B:IX

Diesel Generator Extended On-Line Maintenance

STP M-21-ENG.1

Diesel Engine Generator Inspection (Every Refueling

Outage)

STP M-21-ENG.2

Diesel Engine Generator Inspection (Every Second

Refueling Outage)

Procedures

STP M-9B

Overspeed Trip Test of Diesel Generators

71111.13

Work Orders

WO 279698

71111.15

Corrective Action

Documents

Notifications

256523, 51258615, 51258637, 51262776

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawing

437657

Diesel Fuel Transfer Pumps

AD7.DC6

On-Line Maintenance Risk Management

Procedures

OP1.DC44

Risk Informed Completion Time Program

Work Orders

WO 296541

Corrective Action

Documents

Notifications

51192270, 51212195

OP J-2:VIII

Guidelines for Reliable Transmission Service for DCPP

40, 41

71111.18

Procedures

OP O-36

Protected Equipment Postings

Corrective Action

Documents

Notifications

235081, 51258835

Miscellaneous

DCN 2000002061

Design Change Package for Fan S-45 Flow Switch

Relocation

OP D-1:I

Auxiliary Feedwater System - Make Available

OP E-5:II

Auxiliary Saltwater System Two CCW Heat Exchanger

Operation

STP M-21-RTS.1

Return Diesel Engine to Service Following Outage

Maintenance

STP M-26

ASW System Flow Monitoring

STP M-9A3

Diesel Engine Generator 1-3 Routine Surveillance Test

STP P-AFW-23

Routine Surveillance Test of Motor-Driven Auxiliary

Feedwater Pump 2-3

STP P-ASW-12

Routine Surveillance Test of Auxiliary Saltwater Pump 1-2

STP P-CCP-21

Routine Surveillance Test of Centrifugal Charging Pump 2-1

STP P-CCW-23

Routine Surveillance Test of Component Cooling Water

Pump 2-3

STP P-CCW-A11

Comprehensive Pump Test of Component Cooling Water

Pump 1-1

STP P-DFO-01

Routine Surveillance Test of Diesel Fuel Oil Transfer

Pump 0-1

14A

Procedures

STP P-SIP-11

Routine Surveillance Test of Safety Injection Pump 1-1

71111.24

Work Orders

WO 60167055, 64099427, 64175161, 64211275, 64285874,

286806, 64286807, 64287981, 64295489, 64309105

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

ESOMS Logs

DCPP Form 69-

11506

Dose Equivalent I-131 and Corrected I-131 Calculation Data

Sheet

2/26/2017

71151

Miscellaneous

DCPP Form 69-

297

RCS Dose Equivalent Iodine Performance Indicator

2/08/2022

71152A

Corrective Action

Documents

Notifications

50077678, 50307520, 50539359, 50541988, 51161487,

51162301, 51205737

Corrective Action

Documents

Notifications

225585, 51226017, 51226892

107723-12

Auxiliary Building: Condenser Unit Room, Cable Spreading

Room, 480V Switchgear Room Supply & Exhaust

114

107723-13

Auxiliary Building: 480V AC Switchgear, Battery, Inverter,

and Reactor Rod Drive Control Rooms

71152S

Drawings

494432-1

Auxiliary Building Switchgear Room Supply Fans S-43 & 44

Corrective Action

Documents

Notifications

223636, 51229398, 51229452, 51229453, 51229466,

229578, 51230229, 51247028, 51260708, 51260860

OM7.ID1

Problem Identification and Resolution

OM7.ID3

Root Cause Evaluation

71153

Procedures

OM7.ID4

Cause Evaluations

44