MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20243012024-08-26026 August 2024 NRC Examination Report 05000275/2024301; 05000323/2024301 IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 ML24190A0812024-07-10010 July 2024 NRC Initial Operator Licensing Examination Approval 05000275/2024301; 05000323/2024301 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 05000323/LER-2024-001, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage ML24127A2042024-05-0202 May 2024 02May2024 Ltr - California Coastal Commission to Pg&E, Coastal Development Permit Needed for Pg&E’S Proposed Relicensing of Diablo Canyon Nuclear Power Plant DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report L-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report 2024-09-09
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000323/LER-2024-001, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits 05000323/LER-2017-0012017-10-0303 October 2017 Relief Valve Leakage Resulting in Inoperable Pressurizer Power Operated Relief Valve, LER 17-001-00 for Diablo Canyon, Unit 2, Regarding Relief Valve Leakage Resulting in Inoperable Pressurizer Power Operated Relief Valve 05000323/LER-2016-0012016-07-28028 July 2016 Reactor Trip Breakers Manually Opened During Shutdown Due to a Control Rod Movable Gripper Fuse Failure, LER 16-001-00 for Diablo Canyon, Unit 2, Regarding Reactor Trip Breakers Manually Opened During Shutdown Due to a Control Rod Movable Gripper Fuse Failure 05000275/LER-2015-0012016-02-11011 February 2016 Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld, LER 15-001-01 for Diablo Canyon, Unit 1, Regarding Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld DCL-15-042, Supplemental Licensee Event Report 1-2014-004-01 for Diablo Canyon, Units 1 and 2 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power2015-03-30030 March 2015 Supplemental Licensee Event Report 1-2014-004-01 for Diablo Canyon, Units 1 and 2 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power DCL-15-041, Supplemental LER 2-13-004-01 for Diablo Canyon, Unit 2 Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-32015-03-30030 March 2015 Supplemental LER 2-13-004-01 for Diablo Canyon, Unit 2 Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-3 DCL-13-034, Licensee Event Report 12-005-00 for Diablo Canyon Regarding Expected Submittal Date2013-04-0101 April 2013 Licensee Event Report 12-005-00 for Diablo Canyon Regarding Expected Submittal Date DCL-11-118, LER 11-05-001 for Diablo Canyon Unit 1, Emergency Diesel Generator Actuations Upon Loss of 230 Kv Startup Due to Electrical Maintenance Testing Activities2011-11-0808 November 2011 LER 11-05-001 for Diablo Canyon Unit 1, Emergency Diesel Generator Actuations Upon Loss of 230 Kv Startup Due to Electrical Maintenance Testing Activities DCL-11-119, LER 11-04-001 for Diablo, Unit 1, Regarding Emergency Diesel Generator Actuated Upon 230 Kv Isolation Due to Maintenance Activities on Relay Panel2011-11-0808 November 2011 LER 11-04-001 for Diablo, Unit 1, Regarding Emergency Diesel Generator Actuated Upon 230 Kv Isolation Due to Maintenance Activities on Relay Panel 2024-05-17
[Table view] |
LER-2024-001, LCO 3.0.3 Completion Time Limits |
Event date: |
|
---|
Report date: |
|
---|
3232024001R00 - NRC Website |
|
text
Pac ific Gas and Electric Company ""
Justin E. Rogers Diablo Ca nyon Powor Plant Sta tion Direc tor Mail code 104151502 P.O. Bo x 56 Avila Bea c h, CA 93424
805.545.3088 Ju stin.Rogers@ pge.c o m
PG&E Letter DCL-24-054
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Docket No. 50-323, OL-DPR-82 Diablo Canyon Power Plant, Unit 2 Unit 2 Licensee Event Report 2024-001-00, Unit 2 LCO 3.0.3 Completion Time Limits
Dear Commissioners and Staff,
In accordance with the requirements of 10 CFR 50. 73(a)(2)(i)(B), Pacific Gas and Electric Company (PG&E) hereby submits the enclosed Diablo Canyon Power Plant (DCPP) Unit 2 Licensee Event Report.
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this report. Corrective actions identified in this letter will be implemented in accordance with the DCPP Corrective Action Program.
This event did not adversely affect the health and safety of the public.
If you have any questions or require additional information, please contact Mr. James Morris, Regulatory Services Manager, at (805) 545-4609.
Sincerely,
Justin E. Rogers r -z-'1 Date
dqmg/ 51229466-7 Enclosure Diablo Distribution Mahdi 0. Hayes, NRC Sen ior Resident Inspector INPO Samson S. Lee, NRC Senior Project Manager John D. Monninger, NRC Region IV Administrator
A m e mber of th e STAR S Allia n ce Callaway
Abstract
On March 19, 2024, Pacific Gas and Electric Company requested, and the Nuclear Regulatory Commission (NRC) verbally granted, additional time to resolve a maintenance issue affecting an exhaust fan associated with the Auxiliary Building Ventilation System (ABVS) due to its redundant exhaust fan being concurrently inoperable. The cause of the inoperable redundant ABVS fan was elevated temperature on the "C" Phase between the contactor and the breaker.
The additional time granted by the NRC allowed Diablo Canyon Power Plant ma intenance personnel to perform needed maintenance and restore the exhaust fan to operable on March 19, 2024. As required by NUREG - 1022, exceedance of Technical Specification completion times are still required to be reported per 50.73(a)(2)(i)(B), even though be ing granted enforcement discretion. There was no impact to the health and safety of the public or plant personnel.
I. Reporting Requ irements
This event is being reported in accordance with 10 CFR 50. 73(a)(2)(i)(B) and the associated guidance of NUREG-1022, Rev ision 3, as a condition prohibited by Technical Specifications (TS). The total time that Auxi liary Bu ilding Ventilation System (ABVS) was inoperable exceeded the tota l time allowed per Diablo Canyon Power Plant (DCPP) TS 3.0.3.
II. Plant Cond itions
At the time of the event, DCPP Unit 2 was in Mode 1 at 100 percent power.
Ill. Problem Description
A. Background
The ons ite power systems cons ist of all sources of electric power and their associated distribution systems within the DCPP. Included are the main generators, emergency diesel generators (EOG), and the Class 1 E and non-Class 1 E station batteries.
!The ABVS provides all outside air supply for the auxiliary building under all operating conditions. It also serves its primary purpose of providing cooling air for the engineered safety features pump motors. The fans for the system receive power
~rom the Class 1 E 480-V buses. The supply system consists of two full capacity fans (each powered _ from a separate Class 1 E bus). The exhaust system consists of two full capacity fans (each powered from a separate Class 1 E bus).
~BVS exhaust fans' functions are to limit the maximum ambient temperature in rooms containing safety related equipment, and during accident conditions to provide for conta inment excess pressure relief and min imize radioactivity released via the plant vent.
B. Event Description
On March 19, 2024, Pacific Gas and Electric Company (PG&E) requested, and the Nuclear Regulatory Commission (NRC) verbally granted, additional time to resolve a maintenance issue affecting an exhaust fan associated with the ABVS due to its redundant exhaust fan being concurrently inoperable.
The additional time allowed DCPP maintenance personnel to perform needed maintenance and restore an exhaust fan to operable (note that an exhaust fan remained in service and available), thereby preventing an otherwise unnecessary down-power or the shutdown of Unit 2 without a corresponding health and safety benefit. As requ ired by NUREG-1022, the exceedance of TS completion times are still required to be reported per 50.73(a)(2)( i)(B),even though being granted enforcement discretion. A discussion of this occurence is provided below:
NR C FOR M 366A (04-02-2024 ) Page 2 of 4
On March 18, 2024, during planned maintenance of EDG 2-2, ABVS exhaust fan E-1 tripped on thermal overload (TOL).
Following reset and investigation of the TOL condition, fan E-1 was declared inoperable at 19:43 Pacific Daylight Time (PDT). Fan E-1 was not restored within four hours, and therefore in accordance w ith the provisions of TS 3.8.1 Required
~ction 8.2, ABVS exhaust fan E-2 (which was supported by EDG 2-2) was declared inoperable at 23:43 on the same day.
TS 3. 7.12 for ABVS does not describe a Required Action for two inoperable ABVS trains, and TS 3.0.3 was entered.
DCPP personnel determined that the add itional repairs necessary to restore ABVS fan E-1 would exceed the TS 3.0.3 LCO completion times and requested enforcement discretion. Verbal enforcement discretion was granted by the NRC on March 19, 2024, at 05:36 PDT, which allowed an add itional period of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to restore an ABVS fan to operab le condition. Fan E-1 was restored to operab ility at 17:30 on March 19, 2024, and the applicable TS Conditions were exited.
There was no impact to the health and safety of the public or plant personnel.
C. Status of Inoperable Structures, Systems, or Components that Contributed to the Event
EDG 2-2, ABVS Fan E-1, and ABVS Fan E-2 are discussed above.
rrhere were no other structure, system, or component failures associated with this event.
D. Method of Discovery
Self-Revealing.
E. Operator Actions
Operations pe rsonnel responded to the trip of ABVS exhaust fan E-1 in accordance with plant procedures. Although declared inoperable in accordance with TS, exhaust fan E-2 rema ined available and in service.
NR C FOR M 366A (0 4-02-2 024 ) Page 3 of 4
F. Safety System Responses
There were no safety system responses related to this event.
IV. Cause o f the Problem
The cause of the ABVS fan failure E-1 was a degraded "C" phase contactor in the breaker cubicle providing power to the
~an.
V. Assessment of Safety Consequences
There were no safety consequences as a result of this event.
VI. Corrective Actions
The immediate corrective action was to implement repairs in the breaker cubicle providing power to ABVS Fan E-1.
Operations declared E-1 operable at 1730 PDT on March 19, 2024. Additional follow-up corrective actions will be managed in accordance with the DCPP Corrective Action Program.
IVII. Additional Information
rrhere have been no similar events at DCPP in the previous three years.
NR G FOR M 366A (04-02 -2024) Page 4 of 4