Integrated Inspection Report 05000275/2019003 and 05000323/2019003
ML19303D548
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/30/2019
From: Jeffrey Josey
NRC/RGN-IV/DRP/RPB-A
To: Welsch J
Pacific Gas & Electric Co
References
IR 2019003
Download: ML19303D548 (23)


Text

ber 30, 2019

SUBJECT:

DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000275/2019003 AND 05000323/2019003

Dear Mr. Welsch:

On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Diablo Canyon Power Plant, Units 1 and 2. On October 7, 2019, the NRC inspectors discussed the results of this inspection with Ms. Paula Gerfen, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Diablo Canyon Power Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Diablo Canyon Power Plant, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Jeffrey E. Josey, Chief Project Branch A Division of Reactor Projects Docket Nos. 05000275 and 05000323 License Nos. DPR-80 and DPR-82

Enclosure:

As stated

Inspection Report

Docket Numbers: 05000275 and 05000323 License Numbers: DPR-80 and DPR-82 Report Numbers: 05000275/2019003 and 05000323/2019003 Enterprise Identifier: I-2019-003-0001 Licensee: Pacific Gas & Electric Company Facility: Diablo Canyon Power Plant, Units 1 and 2 Location: Avila Beach, CA 93424 Inspection Dates: July 1, 2019 to September 30, 2019 Inspectors: A. Athar, Resident Inspector (Acting)

L. Carson, Senior Health Physicist S. Hedger, Emergency Preparedness Inspector G. Kolcum, Senior Resident Inspector C. Newport, Senior Resident Inspector J. Reynoso, Senior Resident Inspector (Acting)

Approved By: Jeffrey E. Josey, Chief Project Branch A Division of Reactor Projects Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Diablo Canyon Power Plant, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations Failure to Maintain Structural Fire Barrier in an Approved Design Configuration Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.7] - 71111.05Q Systems NCV 05000323/2019003-01 Documentation Open/Closed The inspectors identified a Green, non-cited violation of Operating License DPR-82, License Condition 2. C. (4), Fire Protection, for the failure to control structural gap seal fire barrier configuration in accordance with the stations NRC-approved fire protection program.

Additional Tracking Items Type Issue Number Title Report Section Status URI 05000275,05000323/2018 Emergency Diesel Generator 71152 Closed 008-01 Mission Time for Operability Evaluations

PLANT STATUS

Units 1 and 2 began the inspection period at full power. Unit 1 operated at or near full power for the remainder of the inspection period.

On September 22, 2019, Unit 2 was shut down for a planned refueling outage and remained in the refueling status for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection Seasonal Extreme Weather Sample (IP Section 03.02)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot and extreme drought due to dry weather for the following systems:
  • Units 1 and 2, intake and cooling systems on July 31, 2019
  • Units 1 and 2, auxiliary saltwater systems on July 31, 2019

External Flooding Sample (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated readiness to cope with external flooding for the following areas:
  • Units 1 and 2, intake structure on August 2, 2019
  • Units 1 and 2, turbine building external doors on August 2, 2019

71111.04Q - Equipment Alignment Partial Walkdown Sample (IP Section 03.01)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1, emergency diesel generator fuel oil and starting air system on July 2, 2019
(2) Unit 1, motor-driven auxiliary feedwater pump 1-3 on September 19, 2019
(3) Unit 2, reactor vessel refueling level indication system alignment on September 27, 2019

71111.05Q - Fire Protection Quarterly Inspection (IP Section 03.01)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Unit 1, H block 115 foot elevation on July 11, 2019
(2) Unit 2, H block 115 foot elevation on July 12, 2019
(3) Units 1 and 2, intake structure on August 29, 2019
(4) Units 1 and 2, vital 4 kV switchgear rooms on September 6, 2019
(5) Unit 1, motor-driven auxiliary feedwater pump room on September 19, 2019

71111.06 - Flood Protection Measures Inspection Activities - Underground Cables (IP Section 02.02c.)

The inspectors evaluated internal flooding mitigation protections in:

(1) the diesel fuel oil underground vault 0-1 on August 14, 2019

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during the following activities:
  • Units 1 and 2, turnover and an operability challenge board in the control room on July 11, 2019
  • Unit 2, plant shutdown and planned reactor trip for refueling outage 2R21 on September 21, 2019 Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
(1) The inspectors observed and evaluated the Unit 2 crew of control room licensed operators during simulator training on September 10, 2019.

71111.12 - Maintenance Effectiveness Routine Maintenance Effectiveness Inspection (IP Section 02.01)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Units 1 and 2, fire water system on July 17, 2019
(2) Units 1 and 2, vital batteries on September 3, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control Risk Assessment and Management Sample (IP Section 03.01)

The inspectors evaluated the risk assessments for the following emergent work activities:

(1) Unit 1, turbine-driven auxiliary feedwater pump 1-1 out of service for maintenance on July 2, 2019
(2) Units 1 and 2, delayed surveillance test of cable spreading room fire suppression system on July 18, 2019
(3) Unit 1, startup transformer 1-1 insulator cleaning and maintenance on July 24-25, 2019
(4) Unit 2, emergency diesel generator 2-2 turbo air receiver leak on July 29, 2019
(5) Unit 1, elevated outage risk during drain down for reactor head removal on September 25, 2019

71111.15 - Operability Determinations and Functionality Assessments Operability Determination or Functionality Assessment (IP Section 02.02)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Unit 2, safety-related atmosphere dump valve PCV 22 backup air leak on July 1, 2019
(2) Units 1 and 2, offsite power and transmission operability determination during threat of wild fire on July 29, 2019
(3) Unit 2, emergency diesel generator turbo air receiver leak on July 29, 2019
(4) Units 1 and 2, loss of Emergency Response Data System on August 7, 2019
(5) Units 1 and 2, diesel fuel oil transfer pump vault fuel oil leak on August 12, 2019
(6) Unit 2, residual heat removal pump 2-1 recirculation valve Agastat relay failure on September 4, 2019

71111.18 - Plant Modifications Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03)

The inspectors evaluated the following temporary or permanent modifications:

(1) Validation of severe accident mitigation guidelines integration into emergency response program on August 15, 2019

71111.19 - Post-Maintenance Testing Post Maintenance Test Sample (IP Section 03.01)

The inspectors evaluated the following post maintenance tests:

(1) Unit 1, residual heat removal pump 1-1 preventative maintenance on July 1, 2019
(2) Unit 2, containment air radiation monitors RM-11 and 12, preventative maintenance and pump replacement on July 16, 2019
(3) Units 1 and 2, diesel fuel oil transfer pump 0-1, differential pressure switch PS-595 replacement on August 15, 2019
(4) Unit 2, auxiliary building exhaust fan E-1 on August 19, 2019
(5) Unit 2, auxiliary building ventilation system after emergent replacement of charcoal beds on September 18, 2019

==71111.20 - Refueling and Other Outage Activities Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)

(1) (Partial)

The inspectors evaluated the Unit 2 refueling outage 2R21 activities beginning September 21, 2019, through the end of the quarter. Specifically, the inspectors completed Inspection Procedure 71111.20, Sections 03.01.a through b, and will continue to inspect the remaining elements of the procedure as the outage continues in the subsequent quarter.

71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)==

(1) Unit 1, 12 kV bus F underfrequency and undervoltage time response test, per Procedure STP I-9, on July 9, 2019
(2) Unit 2, 4 kV bus F vital bus auto-transfer test, per STP M-13F, on September 23, 2019
(3) Unit 2, integrated safeguard testing, per STP M-15, on September 25, 2019

Inservice Testing (IP Section 03.01) (1 Sample)

(1) Unit 1, train B residual heat removal recirculation valve FCV-641B in-service test, per Procedure STP V-3M1B, on September 5, 2019

FLEX Testing (IP Section 03.02) (1 Sample)

(1) Units 1 and 2, annual FLEX equipment surveillance testing on August 13, 2019

71114.04 - Emergency Action Level and Emergency Plan Changes Inspection Review (IP Section 02.01-02.03)

(1) The licensee submitted a summary of emergency plan changes on April 4, 2019. Changes involved the emergency plans table of contents and Appendix F (Revision 4.07). The inspectors conducted an in-office review of the changes from July 23 to July 25, 2019. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01)

(1) The inspectors evaluated an emergency preparedness drill on July 24, 2019.

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) The inspectors evaluated a simulator-based drill of a loss of AC vital buses following a seismic event on August 20,

RADIATION SAFETY

71124.02 - Occupational ALARA Planning and Controls Radiological Work Planning (IP Section 02.01)

The inspectors evaluated the licensees radiological work planning.

(1) The inspectors reviewed the following activities:
  • RWP 2019-1020: 1RF21 Reactor Disassembly & Reassembly
  • RWP 2019-1023: 1RF21 Fuel Movement/Underwater Work
  • RWP 2019-1026: 1RF21 Lower Cavity & Transfer Canal Verification of Dose Estimates and Exposure Tracking Systems (IP Section 02.02) (1 Sample)

The inspectors evaluated dose estimates and exposure tracking.

(1) The inspectors reviewed the following as low as reasonably achievable planning documents:
  • RWP 2019-1020: 1RF21 Reactor Disassembly & Reassembly
  • RWP 2019-1023: 1RF21 Fuel Movement/Underwater Work
  • RWP 2019-1026: 1RF21 Lower Cavity & Transfer Canal Additionally, the inspectors reviewed the following radiological outcome evaluations:
  • RWP 2019-1020: 1RF21 Reactor Disassembly & Reassembly
  • RWP 2019-1023: 1RF21 Fuel Movement/Underwater Work
  • RWP 2019-1026: 1RF21 Lower Cavity & Transfer Canal

71124.04 - Occupational Dose Assessment Source Term Categorization (IP Section 02.01)

(1) The inspectors evaluated the licensees characterization of the source term and use of scaling factors for the use of hard-to-detect radionuclide activity.

External Dosimetry (IP Section 02.02) (1 Sample)

(1) The inspectors evaluated the external dosimetry program implementation.

Internal Dosimetry (IP Section 02.03) (1 Sample)

The inspectors evaluated the internal dosimetry program implementation.

(1) The inspectors reviewed the following:

Whole Body Counts

  • 12/7/17, 29.8 nCi Xe-133
  • 12/7/17, 7109 nCi Tc-99M
  • 4/10/18, 34.51 nCi Co-60 In-Vitro Internal Monitoring
  • There were no in-vitro dose assessments available during this inspection period.

Dose Assessments Performed Using Air Sampling and Derived Air Concentration-Hour Monitoring

  • No dose assessments were performed or available using air sampling and derived air concentration-hour monitoring during this inspection period.

Special Dosimetric Situations (IP Section 02.04) (1 Sample)

The inspectors evaluated the following special dosimetric situation:

(1) The inspector evaluated five declared pregnant workers' records for this inspection period from March 2017 to February 2019.

Licensees implementation of requirements to manage radiation protection of declared pregnant workers, application of NRC-approved external dosimetry methods (i.e., EDEX), shallow dose equivalent and neutron dose assessments were also evaluated by the inspector.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07) ===

(1) Unit 1 (07/01/2018-06/30/2019)
(2) Unit 2 (07/01/2018-06/30/2019)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (07/01/2018-06/30/2019)
(2) Unit 2 (07/01/2018-06/30/2019)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (07/01/2018-06/30/2019)
(2) Unit 2 (07/01/2018-06/30/2019)

71152 - Problem Identification and Resolution Annual Follow-up of Selected Issues (IP Section 02.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) evaluation and corrective actions related to Unit 2, emergency diesel generator scaffolding in support of governor replacement on August 30, 2019
(2) evaluation of battery sizing calculations for station blackout on September 10, 2019
(3) evaluation and corrective actions related to Units 1 and 2, high energy line break program compliance with equipment control guidelines (ECG) and surveillance requirements on September 30,

OTHER ACTIVITIES

- TEMPORARY INSTRUCTION, INFREQUENT, AND ABNORMAL Evaluation of Diablo Canyon Power Plant Safety Condition in Light of Financial Conditions Because Pacific Gas & Electric Corporation, and its subsidiary, Pacific Gas & Electric Company (the licensee) was under bankruptcy protection/reorganization during the inspection period, NRC Region IV conducted special reviews of processes at Diablo Canyon Power Plant (DCPP).

Using the flexibilities in the baseline inspection program, the inspectors evaluated several aspects of the licensees operations to determine whether the financial condition of the licensee impacted plant safety. The factors reviewed during this period included:

(1) impact on staffing,
(2) corrective maintenance backlog,
(3) changes to the planned maintenance schedule,
(4) corrective action program implementation, and
(5) any reduction in outage scope, including risk-significant modifications. Considering the licensees financial difficulties, the inspectors verified that licensee personnel continued to identify problems at an appropriate threshold and enter these problems into the corrective action program for resolution. The inspectors also verified that the licensee continued to develop and implement corrective actions commensurate with the significance of the problems identified.

The special review of processes at DCPP included continuous reviews by the resident inspectors, as well as the specialist-led baseline inspections completed during the inspection period - emergency preparedness and radiation protection - which are documented in this report. During this period, the inspectors did not identify any indications that the licensees financial circumstances were adversely affecting plant performance and safety.

INSPECTION RESULTS

Failure to Maintain Structural Fire Barrier in an Approved Design Configuration Cornerstone Significance Cross-Cutting Report Aspect Section Mitigating Green [H.7] - 71111.05Q Systems NCV 05000323/2019003-01 Documentation Open/Closed The inspectors identified a Green, non-cited violation of Operating License DPR-82, License Condition 2. C. (4), Fire Protection, for the failure to control structural gap seal fire barrier configuration in accordance with the stations NRC-approved fire protection program.

Description:

On September 6, 2019, during a fire protection walk-down of the Unit 2, vital 4 kV switch-gear rooms, the inspectors identified that the fire boundary gap seal 23E-24A-4004-15 in the vital bus F switch-gear room had not been properly sealed or documented on fire barrier drawings. The licensee evaluated the as-found condition of the fire barrier gap seal and determined that it was not functional per Equipment Control Guidelines ECG 18.7, Fire Rated Assemblies. The licensee entered the required 1-hour action ECG 18.7 A.1 and established a continuous fire watch in the Unit 2, vital 4 kV bus F switch-gear room.

The condition was associated with a 3-hour fire barrier which has an approved design configuration in accordance with the approved fire protection program. This type of fire barrier is normally a continuous vertical or horizontal construction assembly designed and constructed to limit the spread of heat and fire and to restrict the movement of smoke. The 4 kV vital bus switch-gear fire barriers protect against external hazard such as the 500 kV main transformer on the other side of the wall from the switch-gear room. The functionality of the fire barrier was questioned when the inspectors found a vertical section with a gap which had not been sealed in accordance with the requirements of the fire protection program. The licensee immediately established a continuous fire watch in the area and initiated repairs to properly seal the gap with pyrocrete.

The inspectors reviewed the licensee surveillance program and determined the ECG fire barriers required visual inspections on an 18-month frequency. The most recent surveillance was completed on February 7, 2019, using Procedure STP M-70D, Inspection of Rated Fire Assemblies, except Penetration Seals, Dampers, & Doors," Revision 23A. Fire barriers are visually inspected for gaps and defects and noted on barrier drawings. Procedures rely on fire barrier drawings to document design penetrations with known deficiencies or gaps. A design configuration, which existed since plant construction, was not on the fire barrier drawings. As a result, Unit 2, vital 4 kV switch-gear room fire barriers drawings, used in visual inspections, were incomplete and inaccurate.

Diablo Canyon Power Plant is required by operating license condition 2.C.(4), Fire Protection, to meet the requirements found in the National Fire Protection Association (NFPA) Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Passive fire barriers are credited as defense-in-depth measures and were evaluated and approved using Engineering Equivalency Evaluations as required by the licensee's approved fire protection program. Diablo Canyon Power Plant demonstrates compliance with NFPA 805 requirements through assessments called fire protection engineering evaluations (FPEE). These FPEEs focus on key fire protection systems and features to ensure they are capable of limiting fire damage and are adequate for the hazard with the appropriate fire safety capabilities.

The inspectors also reviewed FPEE 134, "Non-rated Structural Gap in Fire Barrier, dated December 5, 2017, which stated that gap seal 23E-24A-4004-15 covers both sides of the gap with a pyrocrete enclosure. Contrary to this requirement, the gap was not covered with pyrocrete and therefore not in the evaluated and approved configuration. Failure to properly implement the required criteria for this fire penetration resulted in the 3-hour fire barrier not meeting requirements in the approved fire program.

The licensee evaluated the as-found gap in the fire barrier and concluded that even with the gap, a fire was not expected to propagate across the fire barrier because of the low fire hazard in the area, separation of the explosion or fire hazard by distance, and existing construction of gypsum and steel separating the 4 kV switch-gear room from the outside main transformer.

Corrective Action References: Notification 51044746

Performance Assessment:

Performance Deficiency: The license failed to control structural gap seal fire barrier configuration in accordance with the stations NRC -approved fire protection program.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure of licensee personnel to implement proper configuration control of fire barriers decreased the external event mitigation for fire confinement and may have allowed hot gases or smoke into the vital switch-gear room Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. The inspectors determined that the finding was of very low safety significance (Green) because the identified degraded fire confinement element (i.e., fire barrier) was evaluated and found to provide adequate fire endurance to prevent fire propagation through the fire confinement element (i.e., fire barrier), given the combustible loading and location of equipment important to safe shutdown in the fire area of concern.

Cross-Cutting Aspect: H.7 - Documentation - The organization creates and maintains complete, accurate and up-to-date documentation. The finding has a cross-cutting aspect in human performance, Documentation, because the routine surveillance and inspection drawings did not have complete or accurate documentation.

Enforcement:

Violation: Diablo Canyon Power Plant is required by operating license condition 2.C.(4), Fire Protection, to meet the requirements found in National Fire Protection Association (NFPA)

Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants, 2001 Edition. Passive fire barriers are credited as defense-in-depth measures and were evaluated and approved using Engineering Equivalency Evaluations as required by the licensee's approved fire protection program. The licensee demonstrates compliance with NFPA 805 requirements through assessments called fire protection engineering evaluations (FPEE). These FPEEs focus on key fire protection systems and features to ensure they are capable of limiting fire damage and are adequate for the hazard with the appropriate fire safety capabilities. As such, DCPP's fire protection program required evaluation of non-rated structural gap in fire barriers to meet National Fire Protection Association Standard NFPA 805.

Further, DCPPs Facility Operating License condition 2.C.(4). c.

(1) states, in part, that PG&E may use an engineering evaluation to demonstrate that changes to certain NFPA 805, Chapter 3, elements are acceptable because the alternative is adequate for the hazard. The licensees required evaluation of non-rated penetration seals in rated fire barriers is part of the licensing commitments associated with 10 CFR 50.48(c) (NFPA 805)validation, and updating of engineering evaluations, which form the basis of acceptability are found in Fire Protection Engineering Evaluations, (FPEE) and are credited part of the DCPP fire protection license condition and design basis. In addition, the DCPP-approved fire protection program includes Equipment Control Guidelines ECG 18.7, Fire Rated Assemblies, which is implemented in part by Procedure STP M-70D, Inspections of Rated Fire Assemblies," to ensure structural fire barriers are routinely inspected against the appropriate criteria and ensure it meets the as-design criteria.

Contrary to the above, prior to September 6, 2019, the licensee failed to implement and maintain in effect all provisions of the approved fire protection program as described in the Fire Prevention Program and required by the Operating License Condition 2.C.(4).

Specifically, the licensee failed to ensure the as-found configuration of the fire barrier gap of fire penetration DC-2-98-F-FP-23E-24A-4004A-15 met the required criteria for proper configuration and was appropriately evaluated.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Unresolved Item Emergency Diesel Generator Mission Time for Operability 71152 (Closed) Evaluations URI 05000275,05000323/2018008-01

Description:

The inspectors identified an unresolved item in Inspection Report 2018-008 (ADAMS Accession No. ML18159A483) related to emergency diesel generator (EDG)mission time for operability evaluations. On December 3, 2016, a plant operator discovered that the air inlet boot seal on EDG 1-2 had degraded. A subsequent inspection of the other EDGs across both units revealed that the EDG 2-2 boot seal was also degraded. The licensee performed an operability evaluation and concluded that the EDGs were operable based on a mission time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The licensee then performed a past operability evaluation, concluding that the EDGs had remained able to perform their safety function for this stated 24-hour mission time despite the deficiency; therefore, the licensee determined that no licensee event report was required by 10 CFR 50.73.

Minor Violation 71152 Minor Violation: Title 10 of the Code of Federal Regulations, Part 50, Appendix B, Criterion V, Procedures, requires, in part, that activities affecting quality shall be prescribed by documented procedures and shall be accomplished in accordance with those procedures. Procedure OM7.ID12, Operability Determination, defines mission time as the duration of SSC operation that is credited in the current licensing bases for the SSC to perform its specified safety function. The inspectors determined that PG&E operations personnel failed to follow the requirements of OM7.ID12 when they used 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> as the duration of EDG operation required for it to perform its specified safety function in a justification for operability (i.e., mission time).

Screening: The inspectors determined the performance deficiency was minor. The inspectors requested information related to the basis of the use of a 24-hour mission time for EDG operability determinations. The licensee provided a non-controlled reference document, Engineered Safety Feature (ESF) Equipment Mission Time, and the PG&E Procedure OM7.ID12, Operability Determination. Procedure OM7.ID12 defines mission time as the duration of SSC operation that is credited in the current licensing bases for the SSC to perform its specified safety function. Additionally, the non-controlled Engineered Safety Feature (ESF) Mission Time document lists the mission time for the EDGs as 7 days (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />). The 6- and 24-hour values were specified based on the particular accident sequence and electrical power recovery time and originated from a letter sent to the NRC-related to the licensees Individual Plant Examination of External Events (IPEEE)circa 1994, which is a plant-specific probabilistic risk assessment (PRA). The 7-day value is related to DCPP license bases requirements including the required diesel fuel oil storage volume as discussed in Technical Specification Bases 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air and Turbocharger Air Assist. The inspectors determined that the use of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> as a mission time for EDG operability determinations at DCPP could not be justified based on information contained in the plant licensing basis. Based on a thorough review of DCPP licensing basis documentation, the inspectors did not identify a reason to challenge the use of 7 days as a mission time for EDG operability at DCPP.

The issue was evaluated in accordance with Inspection Manual Chapter 0612, Issue Screening, and determined to be minor since an engineering evaluation performed as a result of the inspectors inquiries determined that the EDG would have remained operable in excess of the 7-day mission time subsequently determined by the licensee to be appropriate.

As a result of the violation, PG&E personnel discontinued the use of timeframes of less than 7 days as an EDG mission time in operability determinations, performed an evaluation to determine EDG past operability, and re-evaluated 10 CFR 50.73 reportability requirements using EDG operability with a 7-day mission time.

Enforcement:

This failure to comply with 10 CFR Part 50, Appendix B, Criterion V, Procedures, constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs enforcement policy. Specifically, this violation was similar to examples of issues having minor safety significance as described in Inspection Manual Chapter 0612, Appendix E, (examples 3.j, 3.k).

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 25, 2019, the inspectors presented the Emergency Plan Revision In-Office Review inspection results to Mr. M. Ginn, Manager, Emergency Preparedness, and other members of the licensee staff.
  • On July 26, 2019, the inspectors presented the Radiation Cornerstone Inspection, ALARA IP 71124.02 & Dose Assessment IP 71124.04 inspection results to Mr. J. Welsch, Senior Vice President, Generation and Chief Nuclear Officer, and other members of the licensee staff.
  • On October 7, 2019, the resident inspectors presented the integrated inspection results to Ms. P. Gerfen, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.01 Drawings 515222 Architectural Door Schedule, Sheet 1 82

71111.01 Drawings 59565 Architectural Plan Area K, Sheet 1 29

71111.01 Miscellaneous DCM No. S-61B 500 kV and 230 kV Systems 18

71111.01 Miscellaneous ML17328A249 NRC Staff Assessment of Flooding Focused Evaluation 12/18/2017

71111.01 Procedures CP M-16 Severe Weather 17

71111.01 Procedures DCM T-45 Diverse and Flexible Coping Strategies 0

71111.01 Procedures EOP ECA-0.0 Loss of Vital AC Power 33

71111.01 Procedures OP J-2:VIII Guidelines for Reliable Transmission Service for DCPP 32

71111.01 Procedures STP M-70.SWG Inspection of ECG Swing Type Doors 10

71111.04Q Corrective Action Notifications 51035933, 51047355

Documents

71111.04Q Procedures MP I-2.28 Activation of RVRLIS 29

71111.04Q Procedures OP A-2:II Reactor Vessel- Draining the RCS to the Vessel Flange 51

71111.04Q Procedures OP D-1:II Auxiliary Feedwater System - Alignment Verification for Plant 35B

Startup

71111.04Q Procedures OP Z-2:X RVRLIS Alignment for Head Removal 8B

71111.05Q Corrective Action Notifications 51044746, 51046372, 51045097,51044746

Documents

71111.05Q Drawings PA-1 Intake Structure 2

71111.05Q Drawings RA-9 H Block Elev. 115' 3

71111.05Q Procedures STP M-70D Inspection of Rated Fire Assemblies 23A

71111.05Q Work Orders 64214038, 64214039, 64169950

71111.06 Corrective Action Notifications 51040590, 51040642

Documents

71111.06 Procedures AR PK15-01 Annunciator Response Diesel Fuel Sump 22

71111.06 Procedures OP J-6C:VI Diesel Fuel Oil Transfer System - Pipe leak Detection 8

Equipment

71111.06 Work Orders 64224911

71111.11Q Procedures AP-27 Loss of Vital 4 kV Bus 9

71111.11Q Procedures EOP EO Reactor Trip / Safety Injection 45

71111.11Q Procedures O B-2:V Residual Heat Removal in Service 37

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.11Q Procedures OP AP-12B Control Rod Misalignment 19

71111.11Q Procedures OP AP-12C Dropped Control Rod 17

71111.11Q Procedures OP L-5 Plant Cooldown from Minimum Load 88B

71111.11Q Procedures PEP R-10 Control Rod Exercising for CRDM Crud Mitigation 5

71111.11Q Procedures STP M-91 Emergency Diesel Generator Start and Loading 29A

71111.11Q Procedures STP M-9A1 Emergency Diesel Generator Routine Surveillance 13A

71111.11Q Procedures STP R-7D Determination of Moderator Temperature Coefficient at Power 7A

with Temperature Coastdown

71111.11Q Work Orders 64174355

71111.12 Corrective Action Notifications 50987717, 50989078, 50989402, 51009184, 51017602,

Documents 51032964, 51033302, 51041907, 51042007, 51042028,

51042050, 51042051

71111.12 Miscellaneous System Health Report - Vital Battery

71111.12 Miscellaneous DCM S-67/ 37 125V/250V Direct Current System

71111.12 Miscellaneous PC-09-01 Maintenance Rule Summary - Fire Water system 5

71111.12 Miscellaneous PC-67A-01 Maintenance Rule Summary - Vital Battery

71111.12 Procedures MP E-67.3C Maintenance of Solid State Controls 400A Vital Station Battery 11

Chargers

71111.12 Procedures STP M-16D Operation of Train B Slave Relay K608 (Safety Injection) 43

71111.12 Work Orders 60112506, 64193715, 64207195, 64208170, 64209249,

211081

71111.13 Corrective Action Notifications 50970602, 51019330, 51028007, 51036525, 51037072,

Documents 51037549, 51038399, 51038997

71111.13 Procedures AD7.DC6 On-Line Maintenance Risk Management 27

71111.13 Procedures AD8.DC50 Outage Safety Management 5

71111.13 Procedures OP O-36 Protected Equipment Postings 21

71111.13 Procedures OP O-36 Protected Equipment Postings 20

71111.13 Procedures STP M-39B Routine Test of Cable Spreading Room CO2 system 38

71111.13 Work Orders 60121068, 64162178

71111.15 Corrective Action Notifications 50974282, 51001419, 51014603, 51015347, 51034564,

Documents 51034572, 51038997, 51039785, 51039971, 51040557,

51040590, 51041134, 51043265, 51045111, 51045112

71111.15 Procedures AD7.DC6 On-Line Maintenance Risk Management 27

Inspection Type Designation Description or Title Revision or

Procedure Date

71111.15 Procedures OM7.ID1 Emerging Issue and Event Investigations 54

71111.15 Procedures OM7.ID12 Operability Determinations 39

71111.15 Procedures OM7.ID12 Operability Determinations 40

71111.15 Procedures OP J-2:VIII Guidelines for Reliable Transmission Service for DCPP 32

71111.15 Procedures Ops Policy B-40 Operations Response to Wildfires 0

71111.15 Work Orders 60120285, 60121068, 60121341, 60122003

71111.18 Corrective Action Notifications 50812660, 51041151

Documents

71111.18 Miscellaneous 90-42456 SAMG Setpoint Development Calculation 0

71111.19 Corrective Action Notifications 51035295, 51036524, 51036803, 51040557, 51040590,

Documents 51040642, 51041134, 51045953

71111.19 Drawings 102021 Diesel Engine Generator Associated Systems, Sheet 2 67

71111.19 Drawings 106721 Diesel Fuel Oil System, Sheet 2 68

71111.19 Drawings 6008437 Diesel Fuel Oil Leak Detection, Sheet 10 3

71111.19 Procedures AR PK15-01 CONTMT/TB SUMP/DSL FO VAULT LVL/DSL FO FLTER DP 22

71111.19 Procedures MP I-2.24-1 Installation of Metallic Compression Fittings on Instrument 9

Tubing

71111.19 Procedures STP I-100A Functional Test of Containment Air Radio-gas Monitor RM-12 16

71111.19 Procedures STP M-3A Auxiliary Building Ventilation System - DOP and Halide 14

Penetration Test

71111.19 Procedures STP P-RHR-11 Routine Surveillance Testing of RHR Pump 1-1 26

71111.19 Work Orders 51035795, 60120663, 60120740, 60121441, 60121465,

64155747, 64184972, 64213964

71111.22 Corrective Action Notifications 50813278, 50952156, 50954161, 50970812, 51040847,

Documents 51041022, 51047875

71111.22 Drawings 441297 Logic Diagram 4160 Volt Bus Section G 14

71111.22 Procedures OP J-6A:II Transferring 4 kV Busses 18

71111.22 Procedures STP I-9 12 kV Bus RCP U/F and U/V Channels Calibration and Time 10

Response Test

71111.22 Procedures STP M-13F 4 kV Bus F Non-SI Auto Transfer Test 65

71111.22 Procedures STP M-15 Integrated Test of Engineering Safeguard 72

71111.22 Procedures STP V-2D RHR Pump Recirculation Valves 7

71111.22 Procedures STP V-3M1B Exercising Valve RHR-FCV-641B, RHR Pump 2 Recirculation 5

Inspection Type Designation Description or Title Revision or

Procedure Date

Valve

71111.22 Work Orders 64175687, 64186351

71114.04 Miscellaneous DCL-19-025 Docket No. 50-275, OL-DPR-80; Docket No. 50-323, OL-DPR- 4/4/2019

2; Diablo Canyon Units 1 and 2; Docket No. 72-26, Materials

License No. SNM-2511; Diablo Canyon Independent Spent

Fuel Storage Installation; Emergency Plan Update

71114.04 Miscellaneous Tracking Number Revise DCPP Severe Accident Management Guidelines 2/15/2019

2018-97 (SAMGs) Based on the Latest Pressurized Water Reactor

Owners' Group (PWROG) Generic Severe Accident Technical

Guidelines

71114.06 Corrective Action Notification 51038507, 51041749, 51041801

Documents

71114.06 Procedures AR PK15-24 Seismic Instrument Alarm 13

71114.06 Procedures EOP ECA 0.3 Restore 4 kV Buses 20

71114.06 Procedures EOP ECA-1.1 Loss of Emergency Coolant Recirculation 27

71114.06 Procedures EP G-1 Emergency Classification / Emergency Plan 46

71114.06 Procedures FSG 0.5 FLEX Support Guidelines- Assessment / FLEX Equipment 4

Strategy

71114.06 Procedures FSG 58 FLEX Support Guidelines - Placing 4 kV in Service 1

71114.06 Procedures OP AP-27 Loss of Vital 4 kV and 480 VAC bus 9

71114.06 Procedures OP1.DC10 Conduct of Operations 56

71124.02 Corrective Action SAPN 50943780, 50975426, 50981002, 5098399, 51016203,

Documents 51017812, 51019489, 51023740

71124.02 Miscellaneous Unit-1 1R21 Post Outage ALARA Report 3/18/19

71124.02 Miscellaneous Unit-2 2R20 Post Outage ALARA Report 3/22/18

71124.02 Procedures RCP D-200 Writing RWPs and ALARA Processes 58A

71124.02 Procedures RCP NISP-RP.04 Radiological Posting and Labeling 1

71124.02 Procedures RCP NISP-RP.05 Access Controls for High Radiation Areas 1

71124.02 Procedures RP1.DC8 Radiation Protection Code and Conduct 5

71124.02 Procedures RP1.ID1 ALARA Program 10

71124.02 Self-Assessments ASMP SAQH Quick hit self-assessment (QHSA) is to perform a pre- 5/13/19

51025561 inspection assessment using NRC Inspection Procedure 71124.02

71124.04 Corrective Action SAPN 50975426, 50981002, 51016203, 51023740

Inspection Type Designation Description or Title Revision or

Procedure Date

Documents

71124.04 Procedures RCD D-330 Personnel Dosimetry Evaluations 13

71124.04 Procedures RCP D-370 Evaluations of Internal Deposition of Radioactive Material 13

71124.04 Procedures RP1 Radiation Protection 9

71124.04 Procedures RP1.ID10 Embryo/Fetus Protection Program 9

71124.04 Procedures RP1.ID6 Personnel Dose Limits and Monitoring 16

71124.04 Self-Assessments 2016 Mirion Audit 2016 Mirion Audit and follow up by PGE 8/26/16

2019 follow-up

audit.

71124.04 Self-Assessments ASMP SAQH Quick hit self-assessment (QHSA) for pre-inspection 5/13/19

51025562 assessment using NRC Inspection Procedure 71124.04

71124.04 Self-Assessments No. 173180001 2018 Radiation Protection Programs Audit 2/1/18

71124.04 Self-Assessments SAPN DN Mirion Dosimetry Laboratory Audit 6/30/19

50985673

71151 Miscellaneous DCPP MSPI Mitigating System Performance Index Basis Document 10

Basis

71151 Miscellaneous MSPI Derivation Unit 1 and 2 Diablo Canyon (MSPI MS 08,09,10) 8/2019

Reports

71151 Miscellaneous NEI 99-02 Regulatory Assessment Performance Indicator Guideline 7

71151 Miscellaneous Technical Diablo Canyon Power Plant 7/1/2018-

Specification Logs 6/30/2019

71151 Procedures XI1.ID5 Collection and Submittal of NRC Performance Indicators 1

71152 Corrective Action Notifications 51040307, 51041907, 51042050, 51042730, 51045163,

Documents 51045164, 51045238, 51045239

71152 Drawings 515220 Door Schedule; Sheet 1 and 2, Unit 1 67

71152 Drawings 515225 Door Schedule; Important to Safety Doors, Unit 2 69

71152 Drawings 515939 HELB Compartment Pressurization Study; 85-foot elevation 4

Turbine Building

71152 Drawings 515940 HELB Compartment Pressurization Study; 104-foot elevation 5

Turbine Building

71152 Drawings 515945 HELB Compartment Pressurization Study; 85-foot elevation 4

Auxiliary and Containment Building

71152 Miscellaneous Calculation No. Class 1E, Battery Capability Calculation During Battery 0

235T-DC Discharge Test

Inspection Type Designation Description or Title Revision or

Procedure Date

71152 Miscellaneous Calculation No. 125 VDC System Analysis Methodology & Scenario 3

360-DC Development

71152 Miscellaneous EOP ECA-0.0 Loss of Vital AC Power 33

71152 Procedures AD7.ID5 Scaffold Material Structure 13

71152 Procedures MIP C-14.0 Temporary Scaffolding 1

71152 Procedures OM4.ID14 Notification Review Team (NRT) 32

71152 Procedures OM7.ID1 Problem Identification and Resolution 54