IR 05000275/1997015
| ML16342D819 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 10/07/1997 |
| From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML16342D818 | List: |
| References | |
| 50-275-97-15, 50-323-97-15, NUDOCS 9710080324 | |
| Download: ML16342D819 (6) | |
Text
DOCUIVlENTCONTAINS ENCLOSURE U.S. NUCLEAR REGULATORY COMM(SS(ON
REGION IV
Docket Nos.:
50-275; 50-323 License Nos.:
Report No.:
Licensee:
Facility:
Location:
DPR-80; DPR-82 50-275/97-1 5; 50-323/97-1 5 Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant, Units 1 and 2 7 1/2 miles NW of Avila Beach Avila Beach, California Dates:
Inspector:
Approved By:
September 15-19, 1997 D. W. Schaefer, Security Specialist, Plant Support Branch Blaine Murray, Chief, Plant Support Branch Division of Reactor Safety ATTACHMENT:
Supplemental Information DOCUMENT CONTAINS 97'LO080324'7%007 PDR ADGCK'5000275
PDR ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
-2-DOCUMENT CONTAINS EXECUTIVE SUMMARY Diablo Canyon Nuclear Power Plant, Units 1 and 2 NRC Inspection Report 50-275/97-15; 50-323/97-15 This was a special, announced, inspection of the licensee's implementation of the land vehicle control measures implemented in accordance with 10 CFR Part 73, "Physical Protection of Plants and Materials," utilizing Temporary Instruction 2515/132, "Malevolent Use of Vehicles at Nuclear Power Plants,"'dated January 18, 1996.
Plant Su ort The installed vehicle barrier system was generally consistent with the summary description previously submitted to the NRC. A noncited violation was identified involving the failure to establish adequate vehicle control measures at Gate 1. An inspection followup item was identified involving the lack of a current description of the vehicle barrier system in the security plan (Section S1.1).
The installed vehicle barrier system was capable of protecting required plant vital equipment from a vehicle bomb blast.
The bomb blast analysis was generally consistent with the summary description previously submitted to the NRC.
Distances between the vehicle barrier system and vital equipment equalled the minimum standoff distance (Section S1.2).
The licensee's procedures addressed the operation, inspection, testing and
'implementation of compensatory security measures of the vehicle barrier system.
An inspection followup item was identified involving the lack of detail in portions of the vehicle barrier system security procedure (Section 1.3).
DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED
Pacific Gas and Electric Company-4-DOCUMENT CONTAINS bcc distrib. by RIV:
bcc copy of letter, and inspection summary only:
E-mail report to T. Frye (TJF)
E-mail report to T. Hiltz (TGH)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
DCD (IE04)
Regional Administrator DRP Director Branch Chief (DRP/E, WCFO)
Senior Project Inspector (DRP/E, WCFO)
MIS System M. Hammond (PAO, WCDO)
WCFO File Lean Tremper (OC:LFDCB, MS: TWFN 9E10)
bcc w/copy of entire report:
Senior Resident Inspector RIV Docket File Elaine Koup (NRR/DRPM/SGB, MS: 011E-22)
DRS/PSB Security File (Goines)
"DOCUMENT NAME: 6CE1 6RP.D To receive copy of document, indicate in hex:
C" - Copy vnt out enctosures
"E - Copy vvithenctosures N - Ro copy RIV:PSS:PSB E
C:DRP:E E
C:PSB E
DWSchaefer/
10/ /97 HWong
97 BMurray
/97 OFFICIAL ECORDCOPY DOCUMENT CONTAINS ENCLOSURE CONTAINS UPON SEPARATION THIS PAGE IS DECONTROLLED