IR 05000275/1987009

From kanterella
Jump to navigation Jump to search
Insp Repts 50-275/87-09 & 50-323/87-08 on 870223-27.No Noncompliance Noted.Major Areas Inspected:Followup of IE Bulletins,Vital Areas & Equipment
ML20205D848
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/11/1987
From: Burdoin J, Mendonca M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML20205D716 List:
References
50-275-87-09, 50-275-87-9, 50-323-87-08, 50-323-87-8, IEB-86-003, IEB-86-3, NUDOCS 8703300498
Download: ML20205D848 (7)


Text

er

-,m -

'

l

.

P

~

U. S. NUCLEAR REGULATORY C0MMISSION

REGION V

Report Nos.

50-275/87-09,50-323/87-08 Docket Nos.

50-275, 50-323 License Nos.

DPR-80, DPR-82 Licensee: Pacific Gas and Electric Company 77 Beale Street, Room 1451 '

San Francisco, California 94106 Facility Name: Diablo Canyon Units 1 and 2 Inspection at: Diablo Canyon Site, San Luis Obispo County, CA Inspection Conduihe :S Februpr 23-7, 1987 Inspector:

o!

.

J # ff J

F. B0rd6in, Re5ctor Inspector D4te Signed Approved by:

NN M"/#7 M. M. Mendonca, Chief Date Signed ReactorProjectSectionI Summary:

Inspection During Period of February 23-27, 1987 (Report Nos. 50-275/87-09 and 50-323/87-08 Areas Inspected:

An unannounced inspection by one regional inspector of design, design changes and modifications; followup of IE Bulletin (s) and an independent inspection of different vital areas and equipment in the plant.

Inspection Procedures Nos. 30703, 37700, 71707, and 92703 were used as guidance for the inspection.

Results:

No items of noncompliance or deviations were identified.

<

h G

i

.

.r

--

,

-

...

-

i;?

3;

\\

., ;

4',

<

,

,

.,

//

',

. =,

,

.

-

-.

,

.

,

.A

~

DETAILS

,

<

c

^

1.

Individuals Contacted Pacific Gas and Electric Company (PG&E)

R.:C. Thornberry,. Plant Manager-

  • J. A. Sexton, Plant Superintendent
  • T. L. Grebel, Regulatory Compliance Supervisor
  • D.=A. Taggart, Director, Quality Support QA c-

.

  • L. F. Womack, Operations Manager J. E. Nolan, Nuclear Engineer, Design Control

'

S. R. ' Fridley, Senior Operations Supervisor J.'E. Skaggs, Shift Technical Advisor R.' D. Cramins, Verification Section Supervisor J. R. Harris, Audit Administrator R. P. Flohaug, Quality Assurance D. R. Geske, Verification Planning Group Supervisor

.

E. E. Pierce, QC Engineer, General Construction

,

'

'C. L. Meyers, Document Control Analyst

  • M. J. Angus, Work Planning Department Manager S. W. Hamilton, Power Production Engineer, Design Control L. R. Collins, Work Planning Center Supervisor l

J. S. Pequignot, Senior Construction Coordinator

>

Various other engineering and QC personnel s

.

,

  • - Denotes attendees at exit management meeting on February 27, 1987.

In addition, NRC Resident Inspectors attended the exit management meeting.

2.

Area Inspection L

An independent inspection was conducted in the Turbine and Auxiliary

,

Buildings, Units 1 and 2..The equipment and areas inspected included:

'

A '.

Five Emergency Diesel Generator Rooms.

B.

Six 4160. Volt Switchgear Rooms.

i-C.

Combined Two-Unit Control Room.

D.

Four Containment Spray Pumps.

E.

Three Charging. Pumps, Unit 1.'

F.

Four Safe Injection Pump Areas.

G.

Four RMR Pump Areas.

.H.

Six Component Cooling Water Pumps.

I.

Six Auxiliary Feedwater Pumps

!

J.

Six 480 Volt Vital Bus Rooms.

K.

Two Cable Spreading Rooms.

i L.

Two Hot Shutdown Panel Areas.

!

M.

Two 480 Volt Load Center Areas.

N.

Turbine Building at Elevations 85' and 140' Areas.

!

.

BYE;i af

~ -5 A-

,

. ;. [

>

f,

.

-

.

'

4 -,

'

'

.

~

'

_

..

.

_

Housekeeping and equipment status appeared to be acceptable.

,.,

i.

y,yjolations'or.deviationswereidentified.

'

3.

'(Closed) Followup Item 50-275/323/87-05-01, Design, Design Changes and

~

Modification The purpose of this inspection was'to evaluate the effectiveness of.the-licensee's program for implementing plant modifications and for effecting a

changes in the design of Diablo Canyon Units 1 and 2,'and to determine

,

that such plant modifications and changes in design are in conformance

'with the requirement of the technical specification (TS) and 10 CFR-50.59. To this end the processes for initiating,-approving, processing and documenting design change and new design; and the mechanics of-

.

installing / constructing,- inspecting, accepting, testing and placing in service of modifications and new systems were-examined in detail-and were verified by sampling.

The following licensee's procedures _ describes the licensee's program for implementing design, design changes and modifications:

A.

Engineering ProcedureLNo. 3.60N, Revision TR-59,~ dated August 4, 1986, " Operating Nuclear Power Plant Design Changes."

B.

Procedure NPAP C-1,- "Nuc1' ear Power. Plant Modification Program "

C.

Administrative Procedure (AP) C-1S1, "Onsite Plant Modification -

,

-

Administration."

-

D.

Procedure NPAP C-4, " Bypass bf Safety Functions and Control of

. Jumpers."

.

-

^

.The above procedures were revi.ewed to verify the following:'

,

~

I a.

That the design changes were reviewed and approved in accordance with TS and established QA/QC controls.

~ b.

That design changes were controlled by established procedures.

.

c.

That'the licensee conducted a review and evaluation of test results.

d.

That operating and' surveillance procedure modifications were made and approved in-accordance with TS for the design changes.

e.

That operator training programs were revised in a reasonable time frame to reflect the design change or modification that was implemented.

For significant design changes to safety-related systems, operator training should occur prior to system startup.

,

f.

That as-built drawings were changed to reflect the modifications, and that control room drawings were revised prior to system startup.

g.

That design changes are planned to be on or were listed on the required 10 CFR 50.59(b) annual report to the NR %

_.

-3

.

.

"

~

-That design change activities are conducted in accordance with the h.

appropriate specifications,-drawings, and other requirements.

i.

That acceptance and;startup t'esting of modifications is conducted in accordance with technically' adequate and approved procedures.

,

j.

That appropriate controls (i.e., fire watch, portable fire fighting

-

equipment, welding and cutting permit)zare implemented.

_

k.

Thatthere~isnotanexcessivebackfogofDesignChangeRequests.

n.

The licens'ee's procedures for! implementing'the program for design, design changes and modifications address the above listed topics.

Modifications as described.in Design Change Packages (DCP's) are

- accomplished either by Plant Maintenance personnel or, by General ~

Construction personnel.

The-Design Change Packages for modifications performed by Plant Maintenance personnel.are processed in the Work Planning Center:(WPC)~while'those packages for modifications performed by General Construction are processed by General Construction Document Control. The completed DCPs with all of the paperwork such as work orders, field followers, approval sheets,^QC inspection sheets,: post modification testing sheets, etc., are assembled in General. Construction Quality Control and the Work, Planning Center.

In order to verify that the plant modifications are being performed.in accordance with the above procedures, the following completed Design Change Packages were reviewed at General Construction Quality Control Vault:

DCP-J-25792

-

Auxiliary Feedwater System, Temperature Sensing and Alarms (Instrumentation)

DCP-J-31783 RHR Pressure Transmitter, Replacement

-

(Instrumentation)

Emergency D-G, Air Receiver Pressure Switch DCP-M-35057

-

(Instrumentation)

DCP-J-31956 RCP Seal Leakoff Flowmeters (Instrumentation)

-

Frame and Detail FuH Cask. Lateral Restraint (Spent DCP-C-35204

-

Fuel Pool)

Spent Fuel Pump 1-2, Suction Line 10" Manual Gate DCP-P-35790

-

Valve (Spent Fuel Pool)

480 Volt System, Cabling (Plant Electrical Power DCP-E-35763

-

System)

Auxiliary Feedwater Pump Turbine (Other)

DCP-M-27427

-

- - -

-

-

--

~4

.

.

af

,

,+

-

The above Design Change Packages and the associated documentation appeared to conform to the requirements of the procedures NPAP C-1 and AP C-151.

.

.

The'following completed Design Change Packages were reviewed at the Work

-

Planning Center:

'

~

DC1-EE-31853

'

Solid State Protection System (Instrumentation)-

- -

DCl-SM-35935

-

Steam Generator Primary Manway Bolts (Reactor

-

Coolant System)

DC1-SM-35936

. Steam Generator Primary / Secondary Manways and

-

Handhole,Co~ers (Reactor Coolant System)

v

'

- -

Containment Fan Cooler 1-2 (Containment Systems)

DCP-M-37147

' Diesel Generator' Mounting Bolts (Plant Electrical DCl-0M-31235

-

s

-

Power System)

.

,

DCP-M-35746

-;

Feedwater Nozzle "J" - Tubes (Other)

MSIVs and Reverse Flow Check Valves (Other)

DCP-M-37286

-

The above Design Change Packages and the associated documentation appeared to conform to the requirements of the procedures NPAP C-1 and AP C-151.

The following completed Design Change Packages were' reviewed with NPG document control.to verify that as-built drawings and manufacturers instructions were distributed and were on file as required by procedures NPAP C-1 and AP C-151.

DCP-J-25792

-

Auxiliary Feedwater System, Temperature Sensing and Alarms RHR Pressurizer Transmitter, Replacement DCP-J-31783

-

Solid State Protection System DCl-EE-31853

-

Emergency 0-G, Air Receiver Pressurizer Switch DCP-M-35057

-

DCl-EM-35172

-

RC Pump Shaft Vibration Monitoring System Feedwater Solenoid Valves DCl-EM-35205

-

Turbine Steam Supply System Solenoid Valves DCl-EM-35764

-

The processing / distribution of as-built drawings and manufacturers component instructions appeared to conform to'the requirements of procedures NPAP C-1 and AP C-151.

No violations or deviations were identified.

-Temporary Modifications, Lifted Leads and Jumpers The licensee's program for the control temporary modifications, lifted leads and the installation of jumpers is described in the following procedures:

NPAP C-4, " Bypass of Safety Functions and Control of Jumpers"

y

,

l

'

.

,

.

,

._.

.

-1-APC-4,S1,." Mechanical Bypass, Jumper and Lifted Circuit Log Accountability System" The procedures were reviewed to verify that controls are established to

.

satisfy the following requirements:

a.

Review and approval _of temporary modifications in accordance with section 6 of the T.S. and 10 CFR 50.59.

-

b.

The'use of detailed approved procedures when performing temporary modifications.

c.

Assign responsibility for approving procedures.

d.

That a formal record be maintained of the status.of temporary modifications, lifted leads and jumpers, temporary strainers, temporary trip set points of control equipment, etc.

e.

Evaluation of the need for independent verification, where appropriate, of installation and removal of temporary modifications, liftedleadsandjumpers.

f.

Functional testing of equipment following installation or re:noval of temporary modifications.

g.

- Periodic. reviews of lifted lead and jumper records, including a check of outstanding entries.

The inspector exam'ined the-licensee's jumper. log books for units 1 and 2, with speci'al attention to the jumpers past the ninety day review cycle (pastduejumpers).

Inconjunctionwithpastduejumperstheinspector examined the following licensee nonconformance report (NCR) issued in December-1986:

-NCR DCO-86-TN-N145, " Jumper Log Three Month Review", which contained t

the following action re_ quest and quality evaluations:

Action Request, A/R, A-0032357

-

Quality Evaluation, Q0003420'

-

.A/R, A0033498

-.

Quality Evaluation, Q0003556

-

A/R, A0050289

-

Quality Evaluation, Q0003815

-

The concerns with the number of past due jumpers are described in the above NCR.

Actions developed by the licensee to correct the NCR findings include reducing the backlog of past due jumpers and taking steps to assure control of jumpers.

It is concluded that the licensee's design, design changes and modifications program is planned and documented, and has been acceptably implemented.

No violations or deviations were identified.

,

-

.

.

4.

(Closed) 50-275/50-323 IE Bulletin 86-03, " Potential Failure of Multiple ECCS Pumps Due to Single Failure of Air Operated Valve in Minimum Flow Recirculation Line".

This bulletin alerted licensees of a potential single failure of minimum flow recirculation lines containing air-operated isolation valves which could result in a common-cause failure of all Emergency Core Cooling

'

System (ECCS) pumps in a system.

The licensee's submittal DCL-8L-334 of November 14, 1986 reports the review performed as action required by item 1 of the bulletin.

The licensee concluded that the potential problem as described in the bulletin does not exit at Diablo Canyon because:

1)

The two motor operated isolation valves in the common minimum flow recirculation line share by the safety injection pumps are required (by T.S.) to be open with the power to the valve operators removed.

2)

The two motor operated valves in the common minimum flow header for the centrifugal charging pumps (CCPs) are maintained in the open position with power available and fail as is. Also since the CCPs have a shutoff pressure of 2511 psig plant conditions resulting in dead heading conditions is highly unlikely.

Emergency operating procedures provide operator guidance for closure and reopening of the valve (s) based on RCS pressure.

3)

Each RHR train contains its own minimum flow / recirculation line with a motor-operated isolation valve powered from a separate vital bus.

The inspector reviewed the bulletin and examined the licensee's FSAR and evaluation (DCL-86-334) of the three systems of the ECCS and concludes that the plant configuration and procedures acceptably address the bulletins concern.

This bulletin is closed for Units 1 and 2.

No violations or deviations were identified.

5.

Exit Meeting The inspector conducted an exit meeting on February 27, 1987, with the Plant Superintendent and other members of the plant staff.

During this meeting, the inspector summarized the scope of the inspection activities and reviewed the inspection findings as described in this report.

The licensee acknowledged the concerns identified in the report.