MONTHYEARML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 ML20015A5832020-01-15015 January 2020 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000271/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Vermont Yankee Nuclear Power Station (Report 05000271-14-006) IR 05000271/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Vermont Yankee Nuclear Power Station (Report 05000271/2013001)(w/Inspection Plan) IR 05000271/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Vermont Yankee Nuclear Power Station (Report 05000271-13-006) IR 05000271/20120012013-03-0404 March 2013 Annual Assessment Letter for Vermont Yankee Nuclear Power Station (Report 05000271/2012001) ML12244A4052012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Vermont Yankee Nuclear Power Station IR 05000271/20110012012-03-0505 March 2012 Annual Assessment Letter for Vermont Yankee Nuclear Power Station (Report 05000271-11-001) ML1124305292011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Vermont Yankee Nuclear Power Station IR 05000271/20100012011-03-0404 March 2011 Annual Assessment Letter for Vermont Yankee Nuclear Power Station (Report 05000271/2010001) ML1024405672010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Vermont Yankee Nuclear Power Station IR 05000271/20010012010-03-0303 March 2010 Annual Assessment Letter Vermont Yankee Nuclear Power Station (05000271-01-001) ML0924400442009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Vermont Yankee Nuclear Power Station, Dated 09/01/09 IR 05000271/20090012009-03-0404 March 2009 Annual Assessment Letter, Vermont Yankee (IR 05000271-09-001) ML0824700052008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan Vermont Yankee IR 05000271/20080012008-03-0505 March 2008 Annual Assessment Letter EOC 2007 ROP8 - Vermont Yankee Station (05000271-08-001) ML0734709582007-12-13013 December 2007 ROP8 - Vermont Yankee - Change to Inspection Plan, 12/13/07 IR 05000271/20070012007-03-0202 March 2007 Annual Assessment Letter - Vermont Yankee Nuclear Power Station (Report 05000271-07-001) IR 05000271/20060012006-03-0202 March 2006 Annual Assessment Letter - Vermont Yankee Nuclear Power Station (Report 05000271/2006001) ML0524207102005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - Vermont Yankee Nuclear Power Station ML0506101212005-03-0202 March 2005 Annual Assessment Letter 2005001 Vermont Yankee ML0423607082004-08-23023 August 2004 Vermont Yankee - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML0406301922004-03-0202 March 2004 2003-04 Annual Assessment Letter - Vermont Yankee IR 05000271/20030012003-03-0303 March 2003 2003 Annual Assessment Letter - Vermont Yankee (Report 50-271/03-001) IR 05000271/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Vermont Yankee (Report 50-271/02-001) 2022-12-21
[Table view] Category:Letter
MONTHYEARBVY 24-028, Pre-Notice of Disbursement from Decommissioning Trust2024-10-31031 October 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-10-30030 October 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-026, Pre-Notice of Disbursement from Decommissioning Trust2024-10-0202 October 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status BVY 24-024, Pre-Notice of Disbursement from Decommissioning Trust2024-07-30030 July 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-023, Pre-Notice of Disbursement from Decommissioning Trust2024-07-0202 July 2024 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20240012024-06-28028 June 2024 NRC Inspection Report No. 05000271/2024001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities BVY 24-022, Pre-Notice of Disbursement from Decommissioning Trust2024-05-30030 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-020, Biennial Update of Quality Assurance Program Manual2024-05-22022 May 2024 Biennial Update of Quality Assurance Program Manual BVY 24-019, 2023 Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Radiological Environmental Operating Report BVY 24-017, Pre-Notice of Disbursement from Decommissioning Trust2024-05-0606 May 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-018, 2023 Radiological Effluent Release Report2024-05-0505 May 2024 2023 Radiological Effluent Release Report BVY 24-016, 2023 Individual Monitoring NRC Form 5 Report2024-04-18018 April 2024 2023 Individual Monitoring NRC Form 5 Report BVY 24-015, Pre-Notice of Disbursement from Decommissioning Trust2024-04-0101 April 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-014, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-04-0101 April 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-013, Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 20232024-03-27027 March 2024 Status of Decommissioning and Spent Fuel Management Fund for the Year Ending 2023 BVY 24-012, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-14014 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-011, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-03-0606 March 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-010, Pre-Notice of Disbursement from Decommissioning Trust2024-03-0505 March 2024 Pre-Notice of Disbursement from Decommissioning Trust ML24053A2572024-03-0101 March 2024 Withdrawal of Requested Licensing Action for a License Amendment Submitted for Approval of the License Termination Plan BVY 24-009, Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 3172024-02-27027 February 2024 Withdrawal of License Amendment Request to Add License Condition 3.K, License Termination Plan; Proposed Change No. 317 BVY 24-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-02-26026 February 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-008, ISFSI, Annual Radioactive Effluent Release Report2024-02-26026 February 2024 ISFSI, Annual Radioactive Effluent Release Report IR 05000271/20230022024-02-20020 February 2024 NRC Inspection Report Nos. 05000271/2023002 and 07200059/2023001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 24-006, Pre-Notice of Disbursement from Decommissioning Trust2024-02-0606 February 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request – Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION I
rch 4, 2009
SUBJECT:
ANNUAL ASSESSMENT LETTER - VERMONT YANKEE NUCLEAR POWER STATION (Report 05000271/2009001)
Dear Mr. Colomb:
On February 11, 2009, the NRC staff completed its performance review of the Vermont Yankee Nuclear Power Station (Vermont Yankee). Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as AOfficial Use Only - Security Related Information will include the security cornerstone review and resultant inspection plan.
Overall, Vermont Yankee operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter, as well as for the first three quarters of the assessment cycle, was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The staff identified six inspection findings for the current twelve month assessment period with a documented cross-cutting theme in the aspect of procedure and document adequacy (H.2(c)) 1 .
The NRC first identified this theme in our mid-cycle assessment letter dated September 2, 2008
[ML082470005] 2 , and concluded that a substantive cross-cutting issue did not exist because you had recognized the theme and had taken or scheduled to take appropriate corrective actions. During this assessment period, we reviewed your corrective action plan and identified no concerns with your implementation. Furthermore, in the last six months of this assessment period, the staff identified only one inspection finding with this aspect, which reflects an improving trend. Therefore, the NRC determined that a substantive cross-cutting issue in the
This is a descriptor which correlates to the cross cutting aspect in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.
Designation in parentheses refers to an ADAMS ascension number. Documents referenced in this letter are publicly available using the ascension number in ADAMS. area of Human Performance does not exist at this time. We will monitor your progress in the area of procedure and document adequacy through the baseline inspection program, including a focused review of your procedure upgrade action plan execution. In addition, we will review your progress and completed actions during the biennial problem identification and resolution inspection scheduled for April 2009.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through June 30, 2010. In addition to the baseline inspections, an independent spent fuel storage installation inspection will be performed. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10CFR2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5306 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/ Original Signed By:
Donald E. Jackson, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-271 License No. DPR-28 Enclosure: Vermont Yankee Inspection/Activity Plan