IR 05000269/2024003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000269/2024003 and 05000270/2024003 and 05000287/2024003 (2)
ML24310A040
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 10/31/2024
From: Robert Williams
NRC/RGN-II/DORS
To: Snider S
Duke Energy Carolinas
References
IR 2024003
Download: ML24310A040 (1)


Text

SUBJECT:

OCONEE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000269/2024003 AND 05000270/2024003 AND 05000287/2024003

Dear Steven Snider:

On September 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Oconee Nuclear Station. On October 29, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Oconee Nuclear Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; and the NRC Resident Inspector at Oconee Nuclear Station.

October 31, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert E. Williams, Jr., Chief Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000269 and 05000270 and 05000287 License Nos. DPR-38 and DPR-47 and DPR-55

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000269, 05000270 and 05000287 License Numbers:

DPR-38, DPR-47 and DPR-55 Report Numbers:

05000269/2024003, 05000270/2024003 and 05000287/2024003 Enterprise Identifier:

I-2024-003-0025 Licensee:

Duke Energy Carolinas, LLC Facility:

Oconee Nuclear Station Location:

Seneca, South Carolina Inspection Dates:

July 1, 2024, to September 30, 2024 Inspectors:

N. Smalley, Senior Resident Inspector D. Dang, Resident Inspector E. Robinson, Resident Inspector S. Battenfield, Operations Engineer M. Bradfield, Senior Reactor Technology Instructor K. Schaaf, Operations Engineer J. Tornow, Physical Security Inspector J. Walker, Senior Emergency Preparedness Inspector Approved By:

Robert E. Williams, Jr., Chief Projects Branch 1 Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Oconee Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Follow Shutdown Procedure Resulted in Inadvertent Automatic Feedwater Isolation System Actuation Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000287/2024003-01 Open/Closed

[H.12] - Avoid Complacency 71153 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 5.4, Procedures, was identified when the licensee failed to properly implement procedure OP/3/A/1102/010, Controlling Procedure for Unit Shutdown, during a planned shutdown on Unit 3 which resulted in the inadvertent actuation of the automatic feedwater isolation system (AFIS). The subsequent level transient in the once-through steam generators (SG) caused an emergency feedwater (EFW) system actuation.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000287/2024-001-00 LER 2024-001-00 for Oconee Nuclear Station,

Unit 3, Procedure Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation 71153 Closed

PLANT STATUS

Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period, with the exception of a temporary power reduction to 98.2 percent on August 3, 2024, as required to implement a measurement uncertainty recapture power uprate from 2568 megawatts to 2608 megawatts core thermal power.

Unit 2 operated at or near 100 percent RTP for the entire inspection period.

Unit 3 operated at or near 100 percent RTP for the entire inspection period, with the exception of a temporary power reduction to 98.2 percent on September 16, 2024, as required to implement a measurement uncertainty recapture power uprate from 2568 megawatts to 2608 megawatts core thermal power.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending Hurricane Helene expected on September 26, 2024, to include heavy rain, wind gusts up to 69 mph, and widespread power outages.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 3 A train of the essential siphon vacuum system concurrent with maintenance on the B train on July 16, 2024
(2) Unit 3 turbine driven emergency feedwater on August 14, 2024
(3) Underground emergency power path while 230kV red bus out of service on September 18, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire zone 106: Unit 1 cable room on July 10, 2024
(2) Fire zone 81: Unit 2 auxiliary building 200 level hallway on July 29, 2024
(3) Fire zone 110: Units 1/2 control room on July 29, 2024
(4) Fire zone 6: Unit 3 main feed pump area on August 27, 2024
(5) Fire zone 29: Unit 3 4160V switchgear on August 28, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated external flooding mitigation protection provided in the:
  • Unit 3 auxiliary building work area, Vaqua room roof drains, and exterior subsurface walls and penetrations

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed power ascension and measurement uncertainty recapture activities on August 5, 2024

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the training staff while performing training in the simulator (ASE3) on July 23, 2024

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components remain capable of performing their intended function:

(1) Nuclear condition report (NCR) 2523154, leakage in Unit 3 core flood tank sample line relief valve, and associated sample line blockage maintenance on July 23, 2024
(2) NCR 2526449, 1C low pressure injection (LPI) pump difficult to rotate by hand on August 22, 2024
(3) NCR 2494408, Unit 2 low pressure service water supply valve 2LPSW-1054 failed leak rate test on September 18, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 1, 2, and 3 green risk due to transformer CT5 maintenance, on July 8, 2024
(2) Unit 1, 2, and 3 yellow risk due to planned maintenance on the standby shutdown facility, on July 29, 2024
(3) Unit 1, 2, and 3 elevated green risk due to maintenance on the backup instrument air compressor, on August 4, 2024
(4) Unit 2 green risk due to 2C LPI pump motor replacement, on August 8, 2024
(5) Unit 1 high green and yellow risk due to C LPI pump testing, nuclear instrumentation calibration, and concentrated boric acid storage tank water movements, on August 22-23, 2024
(6) Unit 2 green risk due to emergent nuclear instrument calibration, on September 11, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) NCR 2521743, reactor building emergency sump detectors past environmental qualification end of life
(2) NCR 2530135, voids detected in Unit 3 B train of reactor building spray (RBS) piping
(3) NCR 2450961, 1B motor driven emergency feedwater pump following postponed replacement of leaking motor air cooler gaskets
(4) NCR 2522001, response to notification of deviation in welding of incore detector assemblies by Framatome
(5) NCR 2494408, Unit 2 reactor building auxiliary cooling system supply control valve 2LPSW-1054 failed leak rate test
(6) NCR 2525104, 2B motor driven emergency feedwater pump test block valve degradation and missing parts

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) NCR 2524513, replacement of test flow throttling valve 2FDW-354 due to issues achieving required flow
(2) NCR 2512808, compensatory action for isolation of Unit 2 low pressure injection cross-train suction relief valves 2LP-195/196

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1) PT/0/A/0750/025, "Fuel Assembly Inspection by Canned Sipping," following indications of fuel leakage during Unit 3 maintenance outage, on July 24, 2024
(2) PT/0/A/0400/005, "[Standby Shutdown Facility (SSF)] Auxiliary Service Water Pump Test," following preventative maintenance on electrical relays and service water components, on July 31, 2024
(3) OP/0/A/1600/010, "Operation of the SSF Diesel-Generator," following annual maintenance on the diesel engines, on August 1, 2024
(4) IP/1/A/0315/014 A, "Unit 1 CRD Breaker Test," following breaker replacement due to initial timing test failure, on August 8, 2024
(5) PT/2/A/0202/011, "Unit 2 B High Pressure Injection Pump Test," following preventative maintenance and lubrication, on September 17, 2024
(6) PT/1/A/0600/012, "Retest of Turbine Driven Emergency Feedwater Pump," following leakage repair of Unit 1 turbine driven emergency feedwater pump seal pressure regulator valve, on September 18, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) PT/1/A/0251/001, "1-2 C Low Pressure Service Water Comprehensive Test," on July 12, 2024
(2) PT/2/A/2200/003, KHU-2 operability checks following outage for semi-annual inspection and electrical preventative maintenance, on August 6, 2024

Inservice Testing (IST) (IP Section 03.01) (2 Samples)

(1) PT/0/A/0400/004, SSF Diesel Engine Service Water Pump Test, on July 31, 2024
(2) PT/0/A/0400/005, SSF Auxiliary Service Water Pump Test, on September 12, 2024

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency preparedness exercise during the week of August 19, 2024. The simulated scenario began with a reactor coolant pump shaft shear and subsequent trip. Shortly after, lightning strikes in the switchyard resulted in the inability to power essential transformers with a combination of lockouts and failed open breakers, which also impacted the alternate underground power source. This resulted in the loss of all offsite and all emergency AC power capability and a Site Area Emergency was declared. As the scenario progressed, the 1B steam generator experienced a tube leak. When a chemistry sample indicating dose equivalent iodine sample results were greater than threshold values, a General Emergency was declared which allowed the offsite response organizations to demonstrate the ability to implement emergency actions.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated submitted emergency action level, emergency plan, and emergency plan implementing procedure changes during the week of August 19, 2024. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Simulator drill exercise and performance (DEP) training session using lesson plan ASE-3 on July 23, 2024

71114.08 - Exercise Evaluation - Scenario Review

Inspection Review (IP Section 02.01 - 02.04) (1 Sample)

(1) The inspectors reviewed and evaluated in-office, the proposed scenario for the biennial emergency plan exercise at least 30 days prior to the day of the exercise.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (July 1, 2023, through June 30, 2024)
(2) Unit 2 (July 1, 2023, through June 30, 2024)
(3) Unit 3 (July 1, 2023, through June 30, 2024)

MS09: Residual Heat Removal Systems (IP Section 02.08) (3 Samples)

(1) Unit 1 (July 1, 2023, through June 30, 2024)
(2) Unit 2 (July 1, 2023, through June 30, 2024)
(3) Unit 3 (July 1, 2023, through June 30, 2024)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (3 Samples)

(1) Unit 1 (July 1, 2023, through June 30, 2024)
(2) Unit 2 (July 1, 2023, through June 30, 2024)
(3) Unit 3 (July 1, 2023, through June 30, 2024)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) January 1, 2023, through June 30, 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) January 1, 2023, through June 30, 2024 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) January 1, 2023, through June 30, 2024

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) NCR 2508058, incorrect bellows assembly identified for LPI system relief valves
(2) NCR 2495187, magnesium Limitorque motor replacement with motor operated valves 2MS-79 and 2MS-76

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) Licensee Event Report (LER) 05000287/2024-001-00, Procedural Deficiency Results in Inadvertent Automatic Feedwater Isolation and Automatic Emergency Feedwater Actuation (ADAMs Accession No. ML24215A408). The inspection conclusions associated with this LER are documented in this report under Inspection Results Section

INSPECTION RESULTS

Failure to Follow Shutdown Procedure Resulted in Inadvertent Automatic Feedwater Isolation System Actuation Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000287/2024003-01 Open/Closed

[H.12] - Avoid Complacency 71153 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 5.4, Procedures, was identified when the licensee failed to properly implement procedure OP/3/A/1102/010, Controlling Procedure for Unit Shutdown, during a planned shutdown on Unit 3 which resulted in the inadvertent actuation of the automatic feedwater isolation system (AFIS). The subsequent level transient in the once-through steam generators (SG) caused an emergency feedwater (EFW) system actuation.

Description:

AFIS is an accident mitigating system designed to provide protection to the plant by monitoring main steam (MS) pressure and sending a signal to automatically secure feedwater flow following a drop in MS pressure below the setpoint of 550 psig. Securing feedwater prevents containment over pressurization following a main steam line break (MSLB) inside containment, and limits SG tube-to-shell differential temperature increase in a faulted SG. AFIS is required to be in operation in Modes 1 and 2 to provide this accident mitigating function. However, during the performance of a unit shutdown, it is necessary to cooldown and depressurize the reactor coolant system (RCS), which necessitates that MS pressure is decreased in a controlled manner. Since this decrease in MS pressure is due to a planned operator action and not a MSLB, disabling AFIS is required to prevent unnecessary loss of main feedwater.

On June 3, 2024, Oconee Nuclear Station Unit 3 was in Mode 3 conducting a shutdown and cooldown for a maintenance outage (O3F32A). At approximately 0047, an AFIS actuation occurred which resulted in a trip of the operating main feedwater (MFW) pump. The resulting SG water level transient caused an EFW actuation due to low SG water level at 0051. Prior to the AFIS actuation, the licensee acknowledged but did not perform procedure OP/3/A/1102/010, step 2.7.4, for disabling AFIS at MS pressure of 625-675 psig. Instead, the licensee prioritized subsequent steps to continue the depressurization of the RCS, and MS pressure decreased, unmonitored, until it passed below the AFIS actuation pressure setpoint of 550 psig. Following the EFW actuation, motor driven EFW pumps 3A and 3B started and supplied feedwater which controlled SG level in band as designed until operators could properly exit emergency response procedures. Operators restored MFW flow at 0411, and continued the shutdown as planned.

Corrective Actions: OP/3/A/1102/010, Controlling Procedure for Unit Shutdown, was revised (07/03/2024, revision 257) to restructure steps and add an additional note for emphasis to ensure AFIS is bypassed in a timely manner.

Corrective Action References: PRR 02520442, NCR 02518069

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensees failure to perform step 2.7.4 of procedure OP/3/A/1102/010 to disable AFIS was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the performance deficiency caused a SG level transient substantial enough to initiate EFW actuation. This is similar to example 4.b in IMC 0612, Appendix E, Examples of Minor Issues.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 1, Initiating Events Screening Questions, inspectors determined this finding was of very low safety significance (Green). Specifically, this event did not cause a reactor trip, did not prevent safety systems such as emergency feedwater from operating as designed, and did not prevent main feedwater from being returned to service by the operators.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, operators and supervisors present in the control room failed to recognize the risk presented by delaying the deactivation of AFIS and failed to adequately prioritize actions to avoid the AFIS actuation or establish a critical parameter to monitor the lowering MS pressure.

Enforcement:

Violation: Oconee Unit 3 Technical Specification 5.4, Procedures, states, in part, that written procedures shall be implemented covering the applicable procedures recommended in Appendix A of Regulatory Guide (RG) 1.33, Quality Assurance Program Requirements (Operation), February 1978. RG 1.33, Appendix A, Paragraph 2, General Plant Operating Procedures, Section i, includes procedures for Plant Shutdown to Hot Standby. The licensee established procedure OP/3/A/1102/010, Controlling Procedure for Unit Shutdown,"

to implement the requirements for commencing plant shutdown to hot standby. Contrary to the above, on June 3, 2024, the licensee failed to implement procedure OP/3/A/1102/010, step 2.7.4, to disable the AFIS system prior to its actuation.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 29, 2024, the inspectors presented the integrated inspection results to Steven Snider and other members of the licensee staff.
  • On August 22, 2024, the inspectors presented the emergency preparedness exercise inspection results to Steven Snider and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Risk profile for the week of September 23rd for Units 1, 2

and 3

AD-OP-ONS-0120

Severe Weather Preparations

AP/0/A/1700/006

Natural Disaster

035

71111.01

Procedures

AP/0/A/2000/001

Keowee Hydro Station - Natural Disaster

009

Drawings

OFD-121D-3.1

Flow Diagram of Emergency Feedwater System

Miscellaneous

OSS_0254.00-00-

1049

(Mech) Design Basis Spec for the Essential Siphon

Vacuum System

015

71111.04

Work Orders

20563290

Corrective Action

Documents

2517405

CSD-ONS-PFP-

1AB-0809

Pre-Fire Plan for U1 Auxiliary Building Elevation 809

000

CSD-ONS-PFP-

1AB-0822

Pre-Fire Plan for U1 Auxiliary Building Elevation 822

000

CSD-ONS-PFP-

2AB-0783

Pre-Fire Plan for U2 Auxiliary Building Elevation 783

2

CSD-ONS-PFP-

3TB-0775

Pre-Fire Plan for U3 Turbine Building Elevation 775

001

Fire Plans

CSD-ONS-PFP-

3TB-0796

Pre-Fire Plan for U3 Turbine Building Elevation 796

000

O-0310-FZ-012

Auxiliary Building - Unit 1 Fire Protection Plan Fire Area

and Fire Zone Boundaries Plan at EL 809+3

003

O-0310-K-005

Auxiliary Building Unit 2 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 783+9

O-0310-K-010

Auxiliary Building Unit 1 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 809+3

O-0310-K-013

Auxiliary Building Unit 1 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 822+0 & EL

25+0

71111.05

Miscellaneous

O-0310-K-014

Auxiliary Building Unit 2 Fire Protection Plan & Fire Barrier,

Flood & Pressure Boundaries Plan at EL 822+0 & EL

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

25+0

O-0310-L-003

Turbine Building Unit 3 Fire Protection Plan & Fire Barrier,

Flood, & Pressure Boundaries Plan at EL 775+0

OFD-124C-1.2

Flow Diagram of High Pressure Service Water System

Turbine Building

AD-FP-ALL-1520

Transient Combustible Control

Procedures

OP/0/A/1106/029 C

Alternate Chilled Water System

23

Work Orders

20668484

OSC -0070

Auxiliary Building Design of Slabs/Beams @elevations

771'+0, 783'+9, 809'+3, 858'+0

Calculations

OSC -10856

PMP Hydraulic Analysis - Local Drainage Basin Surface,

Yard and Roof Drainage

Corrective Action

Documents

NCR 02519428

24 ARD Return U3 AB roof drains to their as-designed

condition

06/17/2024

O-1030-07-07

Auxiliary Building Architectural Wall Section & Details

O-2412-C

Piping Layout Auxiliary Building Roof Drains Plan

Drawings

O-2412B

Piping Layout Roof Drains Details & Sections

Engineering

Changes

408447

OSS-0254.00-00-

3007

(Civil) Auxiliary Building DBD

OSS-0254.00-00-

4005

Design Basis Specification for Design Basis Events

Miscellaneous

OSS-0254.00-00-

4016

(Civil) Design Basis Specification for Flooding from

External Sources

71111.06

Procedures

S.D. 3.2.16

Control of Passive Design Features

Miscellaneous

Simulator Exam Guide 2404 (ASE3)

AD-OP-ALL-0106

Conduct of Infrequently Performed Tests or Evolutions

004

AD-OP-ALL-0203

Reactivity Management

016

71111.11Q

Procedures

AD-OP-ALL-1000

Conduct of Operations

23

Corrective Action

Documents

21028, 2523154, 2523306, 2526449, 2494408

71111.12

Drawings

OFD-102A-3.3

Flow Diagram of Low Pressure Injection System (Core

Flood)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OSS-0254.00-00-

28

(MECH) Design Basis Spec for the Low Pressure Injection

and Core Flood System (LPI)

070

Miscellaneous

Oss-0254.00-00-

4001

(MECH) Design Basis Spec for Reactor Building

Containment Isolation

046

OM-251.0797.004

I/B - DMV - 1367 & DMV-1385 - 6-inch Seated Butterfly

Valve

D03

PT/1/A/0203/006 B

Low Pressure Injection Pump Test-Decay Heat

031

Procedures

PT/3/A/0151/058

Rev. 011-Penetration 59 Leak Rate Test

011

Work Orders

20678136, 20668054, 20448182, 20678136, 20675159,

20513458, 20568516, 20592909, 20663523, 1866458

Corrective Action

Documents

26323, 2526449

OFD-102A-2.1

Flow Diagram of Low Pressure Injection System Borated

Water Supply and LPI Pump Suction

Drawings

OFD-102A-2.2

Flow Diagram of Low Pressure Injection System LPI Pump

Discharge

Operator Logs for ONS Units 1, 2, and 3 on July 8, 2024

Risk assessments for the week of July 29, 2024, for ONS

Units 1, 2, and 3

Elevated Risk Activity Plan 2024 SSF Annual Outage

Risk assessments for the week of August 5, 2024, for ONS

Unit 2

Risk assessment for the week of August 19, 2024, for ONS

Unit 1

Risk assessment for the week of September 2, 2024, for

ONS Units 1, 2, and 3

Risk assessment for the week of September 9, 2024, for

ONS Unit 2

Risk assessments for the week of July 8th for ONS Units 1,

2, and 3

OSS-0254.00-00-

25

Design Basis Specifications for the Instrument Air System

71111.13

Miscellaneous

OSS-0254.00-00-

1053

Protected Service Water System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OSS-0254.00-00-

2005

(Elect) Keowee Emergency Power Design Basis Document

AD-EC-ALL-0240

Online Risk Management Process

AD-NF-ALL-0501

Electronic Risk Assessment Tool (ERAT)

AD-OP-ALL-0201

Protected Equipment

AD-OP-ALL-0210

Operational Risk Management

AD-WC-ALL-0200

Online Work Management

AD-WC-ALL-0410

Work Activity Integrated Risk Management

IP/2/A/0315/012

TXS RPS Power Range Calibration at Power

OP/0/A/1106/041

Turbine Building Ventilation

OP/0/A/1107/011 D

Removal and restoration of 100KV components

OP/0/A/1600/010

Operation of the SSF Diesel-Generator

101

OP/2/A/1102/004A

ICS Operation

017

Procedures

SD 3.2.16

Control of Passive Design Features

011

Work Orders

20557591, 20598649, 20295961, 20676362, 20685925

OSC-6928

Containment Isolation Single Failure Analysis

004

OSC-7592 02

BS-1&2 Stroke Time and Header Fill Time Calculation

OSC-8592

LPS-1054/1055/1061/1062 Capability Evaluation

OSC-8787

Containment Isolation System Notebook

OSC-9592

Gas-Water Waterhammer Loads in Building Spray Header

(PIP O-08-5705, PDO)

Calculations

OSC-9610

Evaluation of LPI, CF, RBS, & HPI Systems for Generic Letter 2008-01

2

Corrective Action

Documents

20135, 2521546, 1906532, 2521011, 2413191,

2450961, 2521743, 2522001, 2469194, 2521743,

2494408, 2355644, 2327394, 2327551, 2401085,

2514567, 2346040, 1785659, 2520135, 2525104, 2518879

O-1422-H-132

Instrument Details Reactor Building Auxiliary Coolers

LPSW Supply Control Valve 2LPSW-1054

OFD-103A-3.1

Flow Diagram of Reactor Building Spray System (BS)

Drawings

OFD-121D-2.1

Flow Diagram of Emergency Feedwater System

71111.15

Engineering

Changes

24596

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OSS-0254.00-00-

1000

(Mech) Design Basis Specification for the Emergency

Feedwater System

059

OSS-0254.00-00-

1034

(MECH) Design Basis Specification for the Reactor Bldg

Spray System

29

OSS-0254.00-00-

1039

(Mech) Design Basis Specification for the Low Pressure

Service Water System

064

Miscellaneous

OSS-0254.00-00-

4001

Design Basis Document for Reactor Building Containment

Isolation

046

AD-EG-ALL-1612

Environmental Qualification (EQ) Program

009

AD-OP-All-0105

Operability Determinations

AD-PI-ALL-0100

Corrective Action Program

IP/0/A/3012/002

Disconnect and Reconnect of Air Operated Valves

036

IP/0/A/3012/007A

Diagnostic Testing of Air Operated Valves Using

Teledyne/Quiklook System

005

MP/0/A/1100.026

Heat Exchanger - Motor Driven Emergency Feedwater

Pump Cooler Maintenance

009

MP/0/A/1200/032

Valves - Butterfly - Disassembly and Reassembly

039

MP/0/A/1200/032

Valves - Butterfly - Disassembly and Reassembly

040

OP/3/A/1104/005

Reactor Building Spray System

044

PT/2/A/0151/063

Penetration 63 Leak Rate Test

008

PT/3/A/0150/024

Reactor Building Spray System Leakage

015

PT/3/A/0152/002

Building Spray System Valve Stroke Test

034

Procedures

PT/3/A/0203/012

HPI/LPI/RBS Piping Ventilation

018

Work Orders

271110, 20271109, 20271533, 20580165, 20258991,

258852, 20214911, 20521928, 20266999, 20661273,

20583830, 20420226, 20271533

OSC-2754

RCS Wide Range Pressure Instrument loop current

leakage calc

OSC-2820

Emergency Procedure Setpoints

043

OSC-4542

RBS System GL 89-10 Applicability

008

OSC-6210

Rosemount Transmitters QLE

OSC-7480

LPI/HPI Hydraulic Analysis (EOP Bases)

71111.18

Calculations

OSC-8125

Diverse HPI/LPI actuation system loop uncertainty and

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

setpoint determination

OSC-8829

Digital RPS/ES Wide range RCS pressure instrument loop

uncertainty

Corrective Action

Documents

2520680, 2524513, 2512808, 2517564, 2491967

OEE-259-03

E/D - Reactor Bldg Spray System - RB Spray Pump A

Outlet VLV 2BS-1

013

OEE-259-04

E/D - Reactor Bldg Spray System - RB Spray Pump B

Outlet VLV 2BS-2

2

Drawings

OFD-100A-3.1

Flow Diagram of Reactor Coolant System

Engineering

Changes

408734, 414836, 424546

NEI 99-01

Development of Emergency Action Levels for Non-Passive

Reactors

OSS-0254.00-00-

1000

(MECH) Design Basis Specification for the Emergency

Feedwater System

OSS-0254.00-00-

28

(MECH) Design Basis Spec for the Low Pressure Injection

and Core Flood System (LPI)

070

OSS-0254.00-00-

1034

(MECH) Design Basis Specification for the Reactor Bldg

Spray System

29

Miscellaneous

OSS-0254.00-00-

4001

(MECH) Design Basis Spec for Reactor Building

Containment Isolation

046

AD-EG-All-1132

Preparation and Control of Engineering Changes

AD-OP-ALL-0110

General Equipment Operating Standards

006

EP/2/A/1800/001

0M

Unit 2 EOP Enclosures 5.1-5.10

004

EP/2/A/1800/001

0Q

Unit 2 EOP Enclosures 5.41-5.47

010

IP/0/A/0075/008

Rosemount Pressure Transmitter Assembly, Initial

Calibration, And Mounting Instructions

PT/2/A/0150/067

2LP-40 & 2LP-41 Leak Test

010

Procedures

PT/2/A/0600/013

Motor Driven Emergency Feedwater Pump Test

077

Work Orders

20173121, 20518868

71111.24

Calculations

ONTC-1-124A-

U1 and 2 LPSW pump test acceptance criteria

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0001-001

ONTC-1-124A-

0005-001

U1 and 2 LPSW Minimum flow line requirements

ONTC-1-124A-

0006-001

U1 and 2 LPSW pump discharge check valve leakage

OSC-11214

SSF Licensing Summary Documents

005

OSC-5093

SSF Electrical Distribution System Voltage Adequacy and

Fault Study

OSC-8721

Functionality Evaluation of the Areva Vacuum Can Sipping

System for Oconee

Corrective Action

Documents

2518355, 2518557, 1937198, 2049786, 2186961,

2490672, 2523872, 2524055, 2524972

Drawings

OFD-133A-2.5

Flow Diagram of Condenser Circulating Water System SSF

Aux Service

OM-351.0164.001

SSF Diesel Generator Instructions & Parts Manual

054

OSS-0254.00-00-

1005

(MECH) Design Basis Specification for the Standby

Shutdown Facility Auxiliary Service Water System

046

OSS-0254.00-00-

1008

(MECH) Design Basis Specification for the Standby

Shutdown Facility Diesel Support System

053

OSS-0254.00-00-

1043

(Mech) Design Basis Spec for the Keowee Turbine Guide

Bearing Oil (GBO) System

014

OSS-0254.00-00-

1043

(Mech) Design Basis Spec for the Keowee Turbine Guide

Bearing Oil (GBO) System

014

OSS-0254.00-00-

2014

(ELECT) Design Basis Document for the 4160/600/120V

SSF Essential AC Power System

019

Miscellaneous

OSS-0347.00-00-

0001

Safe Shutdown Diesel Electric Generating Unit

005

IP/0/A/2005/004

NEI, PP-EP SVS Static Voltage Regulator Exciter System

018

IP/0/A/4980/051C

ABB/ITE Type 51 Relay Test

045

IP/1/A/0315/014 A

TXS RPS Interposing Relay Test and Control Rod Drive

Breaker Trip Timing Test

018

IP/2/A/4980/050A

Brown Boveri Gr-5 Ground Shield Relay Test

011

MP/0/A/1600/004

Strainer - Zurn - SSF Service Water Maintenance

010

Procedures

MP/0/A/1800/003

Flange - to - Flange Connections

055

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

MP/0/A/5050/032

Diesels - SSF - 12 and 16 Cylinder - Preventive

Maintenance - 2, 4, and 6 Year

047

OP/0/A/1106/019

Keowee Hydro At Oconee

114

OP/0/A/1600/009

SSF Auxiliary Service Water System

039

OP/0/A/1600/010

Operation of the SSF Diesel-Generator

101

OP/0/A/2000/014

KHU-2 Generator

PT/0/A/0400/004

SSF Diesel Engine Service Water Pump Test

041

PT/0/A/0400/005

SSF Auxiliary Service Water Pump Test

070

PT/0/A/0750/023

Fuel Assembly Inspection by In-Mast Sipping

009

PT/0/A/0750/025

Fuel Assembly Inspection by Canned Sipping

001

PT/1/A/0251/001

LPSW Pump Test

114

PT/1/A/0600/012

Turbine Driven Emergency Feedwater Pump Test

108

PT/2/A/0202/011

High Pressure Injection Pump Test

PT/2/A/2200/003

KHU-2 Semi-Annual Surveillance

Work Orders

258991, 20250551, 20579847, 20580352, 20546018,

20573540, 20575868, 20648454, 20583389, 148508701,

20657258, 20685602, 20590405, 20634905

AD-EP-ALL-0104

ERO Common Guidelines and Forms

AD-EP-ALL-0107

Emergency Operations Facility (EOF) Services

AD-EP-ALL-0109

Offsite Protective Action Recommendations

AD-EP-ALL-0111

Control Room Activation of the ERO

AD-EP-ALL-0112

Onsite Protective Measures

AD-EP-ALL-0203

Field Monitoring During Declared Emergency

AD-EP-ALL-0301

Activation of the Emergency Response Organization

Notification System (ERONS)

AD-EP-ALL-0404

Administration of the Emergency Response Data System

(ERDS)

AD-EP-ALL-0406

Duke Emergency Management Network (DEMNET)

AD-EP-ALL-0407

Emergency Operations Facility Surveillance

AD-EP-ALL-0407

Emergency Operations Facility Surveillance

AD-EP-ALL-0500

Emergency Response Training

AD-EP-ALL-0500

Emergency Response Training

71114.01

Procedures

AD-EP-ALL-0501

Emergency Preparedness Staff Training and Job

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Familiarization

AD-EP-ALL-0902

Offsite Interface

AD-PI-ALL-0100

Corrective Action Program

CSD-EP-ONS-

0101-01

EAL Technical Basis Document

CSD-EP-ONS-

0101-02

ONS EAL Wallchart

AD-EP-ALL-0101

Emergency Classification

EP-ALL-EPLAN

Duke Energy Common Emergency Plan

EP-ONS-EPLAN-

ANNEX

Duke Energy Oconee Emergency Plan Annex

HP/0/B/1009/001

Emergency Equipment Inventory And Instrument Check

CSD-EP-ONS-

0101-01

EAL Technical Basis Document

71114.04

Procedures

CSD-EP-ONS-

0101-02

EAL Wall Chart

71114.06

Miscellaneous

Simulator Exam Guide 2404 (ASE3)

71114.08

Procedures

AD-EP-ALL-0801

Design and Development of Drills and Exercises

MSPI Margin and Derivation reports for Emergency AC

Power for October, November and December 2023 for

Units 1, 2 and 3

MSPI Margin and Derivation reports for Residual Heat

Removal for Quarter 3 2023 for Unit 1

MSPI Margin and Derivation reports for Residual Heat

Removal for Quarter 1 2024 for Unit 2

MSPI Margin and Derivation reports for Residual Heat

Removal for Quarter 2 2024 for Unit 3

Duke Energy Oconee Nuclear Station Units 1, 2, and 3

Mitigating Systems Performance Index (MSPI) Basis

Document

Miscellaneous

CP/0/A/2005/022

Determination of Reported Tech Spec Dose Equivalent

Iodine-131

71151

Procedures

AD-EP-ALL-0305

Fleet Emergency Preparedness (EP) Alert and Notification

System (ANS) Siren Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

21025, 2372374, 2505803, 2508058, 2495187, 2495288

OFD-102A-1.1

Flow Diagram of Low Pressure Injection System (Borated

Water Supply & LPI Pump Suction)

Drawings

OFD-102A-2.1

Flow Diagram of Low Pressure Injection System (Borated

Water Supply & LPI Pump Suction)

Crosby Information Notice 2024-01, May 6, 2024

Duke Metallurgy Report #6429, March 6, 2024

Miscellaneous

OSS-0254.00-00-

28

(Mech) Design Basis Spec for the Low Pressure Injection

and Core Flood System (LPI)

AD-LS-ALL-0018

Evaluating and Reporting Defects and Noncompliance in

Accordance with 10 CFR 21

Procedures

AD-PI-ALL-0106

Cause Investigation Checklists

71152A

Work Orders

20448182, 20668054, 20634548

Corrective Action

Documents

21856

71153

Procedures

OP/3/A/1102/010

Controlling Procedure For Unit Shutdown

257