IR 05000269/1982005

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-269/82-05,50-270/82-05 & 50-287/82-05 on 820210-12.No Noncompliance Noted.Major Areas Inspected:Hpi Piping & Recovery of Insp Tool from Unit 2 Vessel
ML20042B439
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/25/1982
From: Blake J, Herdt A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20042B431 List:
References
50-269-82-05, 50-269-82-5, 50-270-82-05, 50-270-82-5, 50-2701-82-5, 50-287-82-05, 50-287-82-5, NUDOCS 8203250315
Download: ML20042B439 (4)


Text

. _ _ _ _ _ _ _ _.

__

__ _ _ - _

_

__ -

. _ _ _ _ _ - _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ - _

__

.

Mi[f7

/

UNITED STATES

,

NUCLEAR REGULATORY COMMISSION o

$

E REGION 11 e,

101 MARIETTA ST., N.W., SUITE 3100

%

ATLANTA, GEORGIA 30303 Report Nos. 50-269/82-05, 50-270/82-05 and 50-287/82-05 Licensee:

Duke Power Company 422 South Church Street Charlotte, NC 28242 Facility Name: Oconee Docket Nos. 50-269, 50-270 and 50-287 License Nos. DPR-38, DPR-47 and DPR-55 Inspection at Oconee site near Seneca, SC Inspector:

/

2 25 T2-

<

/

',

J. J. Blake ;

-

-

_

Date Signed

'

Approved by:

Mn mn ca

%7 f /V g A. R. HArdt,'SbEtion Chief

/Date gigned Engineering Inspection Branch Engineering and Technical Inspection Division SUMMARY Inspection on February 10-12, 1982 Areas Inspected This special, unannounced inspection involved 24 inspector-hours on site in the areas of Inspection of High Pressure Injection Piping (Units 1, 2 and 3), and j

Recovery of Inspection Tool from Unit 2 Vessel.

Results Of the two areas inspected, no violations or deviations were identified.

o

.

l

!

,

B203250315 820302 PDR ADOCK 05000269 G

PDR

.

-..

.

REPORT DETAILS 1.

Persons Contacted Licensee Employees

  • J. E. Smith, Station Manager
  • R. J. Brackett, Senior QA Engineer C. B. Cheezem, ISI Engineer J. M. Crowe, Senior QA Technical Suppcrt R. L. Gill, Licensing Engineer P. Earnhardt, Assistant Engineer, Mechanical Other licensee employees contacted included ISI technicians and engineering office personnel.

NRC Resident Inspector W. T. Orders, Senior Resident Inspector D. Myers, Resident Inspector

  • Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on February 12, 1982, with those persons indicated in paragraph 1 aoove.

The inspector informed the licensee that the following new items were identified for follow-up on future inspections.

a.

Inspector Follow-up Item (50-270/82-05-01) - Condition of Incore Instrument Tubes (see paragraph 5).

a.

Inspector Follow-up Item (50-270/82-05-02) - Cause of R.V. Inspection Tool Malfunction (see paragraph 5).

a.

Inspector Follow-up Item (50-270/82-05-03) - Volumetric Inspection of

,

l H.P. Injection Ldne Welds (see paragraph 6).

3.

Licensee Action on Previous Inspection Findings I

Not inspected.

4.

Unresolved Items Unresolved items were not identified during this inspection.

l I

.

.

5.

Reactor Vessel Inspection Tool Malfunction (Unit 2)

The Unit 2 Reactor Vessel was being ultrasonically inspected utilizing the-B&W ARIS II inspection system. At approximately 4:40 a.m. on February 7, 1982, the equipment was directed to re-inspect a weld in the lower vessel head. The vertical movement of the inspection tool was being controlled by the equipment computer which apparently malfunctioned in. a way that read erroneous position indicating data causing the boom to overshoot. The boom continued _to drive, after the lower.section of the boom was stopped by the incore instrument tubes, until the drive carriage had raised from the tracks approximately 413 feet. (The drive speed of the equipment was reported to be approximately 65 inches per minute at the time of impact and the weight of the equipment resting on the incore instrument tube was estimated to be approximately 5700 pounds.) After the drive carriage raised itself off the tracks, the boom toppled, coming to rest against the refueling bridge.

During February 8 and 9, 1982, the licensee'and B&W assessed the situation and prepared procedures and equipment for the instrument recovery operation.

On February 10, 1982, protective sleeves were placed over _ the incore in-strument -tubes adjacent to the boom resting site, and rigging required to manipulate the instrument during recovery was installed.

On February 11, 1982, the ARIS was carefully moved until the boom was vertical.

After visual inspection to ensure that there were no inter-ferences the equipment was raised vertically 'using the polar crane. The drive motor was then activated to move the drive carriage back down the boom to its proper location on the equipment rails.

As of the end of this NRC inspection, the licensee was waiting for the arrival of a computer specialist to inspect the ARIS computer and try to determine wL c caused the malfunction and to assess any other damage. This assessment wculd be made before the ARIS inspection tool was' removed from the vessel. After removal of the.ARIS from the vessel, the licensee plans

to do a complete visual inspection of the bottom of the reactor vessel.

_

There were no violations or deviations noted during the instrument recovery I

operation.

The inspector did inform the licensee that two new inspector (

followup items would be identified in this-report, they are as follows:

50-270/82-05-01, " Condition of Incore Instrumentation Tubes".

i 50-270/82-05-02, "Cause of R.V. Inspection Tool Malfunction".

l 6.

Inspection of High Pressure Injection Piping

.

c l

The inspector held discussions with the licensee's QA, Licensing Engi-

!

neering, and ISI personnel concerning the need for inspection of the Oconee High Pressure Injection Piping in light of the recently discovered pipe-crack problem at Crystal River Nuclear Plant.

i

!

-

-

-.

.

.

-. -

.

-

- -

-

-

.

.

.

,

The licensee's representatives stated that the welds in question had been visually and liquid penetrant inspected in Unit 2 during the current outage and that plans were being made to do radiographic inspection after the water level could be lowered enough to drain these lines. They also stated that there were no plans at this time to do any ultrasonic inspections.

During this inspection the Oconee Unit I was shut down because of a steam generator tube leak.

Unit 3 was also showing indications of primary to secondary leakage which might cause the Unit to be shut down. The licensee indicated that the high pressure lines on Unit 1 and Unit 3 would be in-spectable during a steam generator tube plugging outage and plans were being made to conduct those inspections.

The inspector visually inspected the high pressure infection piping inside the shield wall of Unit 2 and reviewed hanger and piping drawings for Units 1 and 2 to determine what similarities and differences there were between Oconee and Crystal River.

The inspector informed the licensee that an inspector followup item would be opened concerning the volumetric inspections of this high pressure piping.

The item is as follows:

50-270/82-05-03, " Volumetric Inspection of H.P. Injection Line Welds".

There were no violations or deviations noted during this phase of the inspection.