November 29, 2018
SUBJECT:
H. B. ROBINSON STEAM ELECTRIC PLANT - NRC MATERIAL CONTROL AND ACCOUNTING INSPECTION REPORT 05000261/2018412
Dear Mr. Remick:
On November 1, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a material control and accounting (MC&A) inspection at your H. B. Robinson Steam Electric Plant, Unit 2.
On November 19, 2018, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
However, the enclosed report contains Security-Related Information, and therefore will not be made publically available in accordance with 10 CFR 2.390(d)(1).
Sincerely,
/RA/
Randall A. Musser, Chief
Reactor Projects Branch 3
Division of Reactor Projects
Docket Nos. 50-261 License Nos. DPR-23
Enclosure:
cc: See Next page