MONTHYEAR0CAN109902, Monthly Operating Repts for Sept 1999 for Arkansas Nuclear One,Units 1 & 2.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Arkansas Nuclear One,Units 1 & 2.With 0CAN099907, Monthly Operating Repts for Aug 1999 for Ano,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Ano,Units 1 & 2. with 0CAN089904, Monthly Operating Repts for July 1999 for Ano,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ano,Units 1 & 2. with 0CAN079903, Monthly Operating Repts for June 1999 for Ano,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ano,Units 1 & 2. with ML20196A0191999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Arkansas Nuclear One,Units 1 & 2.With 0CAN059903, Monthly Operating Repts for Apr 1999 for Ano,Units 1 & 2. with1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ano,Units 1 & 2. with ML20205R6351999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ano,Units 1 & 2. with 0CAN039904, Monthly Operating Repts for Feb 1999 for Ano,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ano,Units 1 & 2. with ML20199F0351998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ano,Units 1 & 2 ML20198D2441998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ano,Units 1 & 2. with 0CAN119808, Monthly Operating Repts for Oct 1998 for Ano,Units 1 & 2. with1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Ano,Units 1 & 2. with 0CAN109806, Monthly Operating Repts for Sept 1998 for ANO Units 1 & 2. with1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for ANO Units 1 & 2. with 0CAN099803, Monthly Operating Repts for Aug 1998 for ANO Units 1 & 2. with1998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for ANO Units 1 & 2. with 0CAN089804, Monthly Operating Repts for July 1998 for Ano,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ano,Units 1 & 2 ML20236R0531998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ano,Units 1 & 2 ML20236R0781998-05-31031 May 1998 Correction to Monthly Operating Rept for May 1998 for ANO, Unit 2 0CAN069802, Monthly Operating Repts for May 1998 for ANO Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for ANO Units 1 & 2 0CAN059805, Monthly Operating Repts for Apr 1998 for Ano,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Ano,Units 1 & 2 0CAN049802, Monthly Operating Repts for Mar 1998 for Arkansas Nuclear One,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Arkansas Nuclear One,Units 1 & 2 ML20217B1131998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 0CAN029805, Monthly Operating Repts for Jan 1998 for Ano,Units 1 & 21998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Ano,Units 1 & 2 ML20217B1181998-01-31031 January 1998 Revised Monthly Operating Rept for Jan 1998 for Ano,Unit 1 0CAN019804, Monthly Operating Repts for Dec 1997 for ANO Units 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for ANO Units 1 & 2 ML20197J0851997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for ANO Units 1 & 2 ML20199D3841997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Arkansas Nuclear One,Units 1 & 2 0CAN109703, Monthly Operating Repts for Sept 1997 for Arkansas Nuclear One,Units 1 & 21997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Arkansas Nuclear One,Units 1 & 2 0CAN099702, Monthly Operating Repts for Aug 1997 for Arkansas Nuclear One Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Arkansas Nuclear One Units 1 & 2 0CAN089704, Monthly Operating Repts for Jul 1997 for Arkansas Nuclear One1997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Arkansas Nuclear One 0CAN079706, Monthly Operating Repts for June 1997 for Arkansas Nuclear One,Units 1 & 21997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Arkansas Nuclear One,Units 1 & 2 0CAN069703, Monthly Operating Repts for May 1997 for Arkansas Nuclear One (Ano),Units 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Arkansas Nuclear One (Ano),Units 1 & 2 0CAN059705, Monthly Operating Repts for Apr 1997 for Arkansas Nuclear One Units 1 & 21997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Arkansas Nuclear One Units 1 & 2 0CAN049705, Monthly Operating Repts for Mar 1997 for Arkansas Nuclear One,Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Arkansas Nuclear One,Units 1 & 2 2CAN039703, Monthly Operating Rept for Feb 1997 for Arkansas Nuclear One,Unit 21997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Arkansas Nuclear One,Unit 2 1CAN039706, Monthly Operating Rept for Feb 1997 for Arkansas Nuclear One,Unit 11997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Arkansas Nuclear One,Unit 1 1CAN029703, Monthly Operating Rept for Jan 1997 for Arkansas Nuclear One,Unit 11997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Arkansas Nuclear One,Unit 1 2CAN029708, Monthly Operating Rept for Jan 1997 for Arkansas Nuclear One,Unit 21997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Arkansas Nuclear One,Unit 2 1CAN019702, Monthly Operating Rept for Dec 1996 for Arkansas Nuclear One Unit 11996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Arkansas Nuclear One Unit 1 2CAN019703, Monthly Operating Rept for Dec 1996 for Arkansas Nuclear One Unit 21996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Arkansas Nuclear One Unit 2 1CAN129603, Monthly Operating Rept for Nov 1996 for Arkansas Nuclear One-Unit 11996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Arkansas Nuclear One-Unit 1 2CAN129608, Monthly Operating Rept for Nov 1996 for Arkansas Nuclear One-Unit 21996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Arkansas Nuclear One-Unit 2 1CAN119602, Monthly Operating Rept for Oct 1996 for Arkansas Nuclear One,Unit 11996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Arkansas Nuclear One,Unit 1 2CAN119605, Monthly Operating Rept for Oct 1996 for Arkansas Nuclear One,Unit 21996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Arkansas Nuclear One,Unit 2 1CAN109607, Monthly Operating Rept for Sept 1996 for Arkansas Nuclear One Unit 11996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Arkansas Nuclear One Unit 1 2CAN109604, Monthly Operating Rept for Sept 1996 for Arkansas Nuclear One-Unit 21996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Arkansas Nuclear One-Unit 2 1CAN099602, Monthly Operating Rept for Aug 1996 for Arkansas Nuclear One Unit 11996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Arkansas Nuclear One Unit 1 2CAN099606, Monthly Operating Rept for Aug 1996 for Arkansas Nuclear One,Unit 21996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Arkansas Nuclear One,Unit 2 2CAN089607, Monthly Operating Rept for July 1996 for ANO-21996-07-31031 July 1996 Monthly Operating Rept for July 1996 for ANO-2 1CAN089603, Monthly Operating Rept for July 1996 for ANO-11996-07-31031 July 1996 Monthly Operating Rept for July 1996 for ANO-1 ML20116J6421996-07-31031 July 1996 Monthly Operating Repts for Jul 1996 for Jm Farley Nuclear Plant Units 1 & 2 2CAN079605, Monthly Operating Rept for June 1996 for ANO-unit 2.W/1996-06-30030 June 1996 Monthly Operating Rept for June 1996 for ANO-unit 2.W/ 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L8931999-10-31031 October 1999 Rev 1 to BAW-10235, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs ML20212L1141999-10-0101 October 1999 Safety Evaluation Granting Request for Exemption from Technical Requirements of 10CFR50,App R,Section III.G.2.c 0CAN109902, Monthly Operating Repts for Sept 1999 for Arkansas Nuclear One,Units 1 & 2.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Arkansas Nuclear One,Units 1 & 2.With ML20216J6271999-09-27027 September 1999 Rev 0 to CALC-98-R-1020-04, ANO-1 Cycle 16 Colr ML20212F5261999-09-22022 September 1999 SER Approving Request Reliefs 1-98-001 & 1-98-200,parts 1,2 & 3 for Second 10-year ISI Interval at Arkansas Nuclear One, Unit 1 0CAN099907, Monthly Operating Repts for Aug 1999 for Ano,Units 1 & 2. with1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Ano,Units 1 & 2. with ML20211F4281999-08-25025 August 1999 Safety Evaluation Concluding That Licensee Provided Acceptable Alternative to Requirements of ASME Code Section XI & That Authorization of Proposed Alternative Would Provide Acceptable Level of Quality & Safety 0CAN089904, Monthly Operating Repts for July 1999 for Ano,Units 1 & 2. with1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ano,Units 1 & 2. with ML20210K8831999-07-29029 July 1999 Non-proprietary Addendum B to BAW-2346P,Rev 0 Re ANO-1 Specific MSLB Leak Rates 0CAN079903, Monthly Operating Repts for June 1999 for Ano,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ano,Units 1 & 2. with ML20207E7231999-06-0202 June 1999 Safety Evaluation Authorizing Proposed Alternative Exam Methods Proposed in Alternative Exam 99-0-002 to Perform General Visual Exam of Accessible Areas & Detailed Visual Exam of Areas Determined to Be Suspect ML20196A0191999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Arkansas Nuclear One,Units 1 & 2.With ML20196A6251999-05-31031 May 1999 Non-proprietary Rev 0 to TR BAW-10235, Mgt Program for Volumetric Outer Diameter Intergranular Attack in Tubesheets of Once-Through Sgs ML20195D1991999-05-28028 May 1999 Probabilistic Operational Assessment of ANO-2 SG Tubing for Cycle 14 ML20206M7711999-05-11011 May 1999 SER Accepting Relief Request from ASME Code Section XI Requirements for Plant,Units 1 & 2 0CAN059903, Monthly Operating Repts for Apr 1999 for Ano,Units 1 & 2. with1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ano,Units 1 & 2. with ML20206F0691999-04-29029 April 1999 Safety Evaluation Accepting Licensee Re ISI Plan for Third 10-year Interval & Associated Requests for Alternatives for Plant,Unit 1 ML20205M6941999-04-12012 April 1999 Safety Evaluation Granting Relief for Second 10-yr Inservice Inspection Interval for Plant,Unit 1 ML20205D6061999-03-31031 March 1999 Safety Evaluation Supporting Licensee Proposed Approach Acceptable to Perform Future Structural Integrity & Operability Assessments of Carbon Steel ML20205R6351999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ano,Units 1 & 2. with ML20205D4711999-03-26026 March 1999 SER Accepting Util Proposed Alternative to Employ Alternative Welding Matls of Code Cases 2142-1 & 2143-1 for Reactor Coolant System to Facilitate Replacement of Steam Generators at Arkansas Nuclear One,Unit 2 ML20204B1861999-03-15015 March 1999 Safety Evaluation Authorizing Licensee Request for Alternative to Augmented Exam of Certain Reactor Vessel Shell Welds,Per Provisions of 10CFR50.55a(g)(6)(ii)(A)(5) 0CAN039904, Monthly Operating Repts for Feb 1999 for Ano,Units 1 & 2. with1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ano,Units 1 & 2. with ML20212G6381999-02-25025 February 1999 Ano,Unit 2 10CFR50.59 Rept for 980411-990225 ML20203E4891999-02-11011 February 1999 Rev 1 to 97-R-2018-03, ANO-2,COLR for Cycle 14 ML20199F0351998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ano,Units 1 & 2 ML20198M7841998-12-29029 December 1998 SER Accepting Util Proposal to Use ASME Code Case N-578 as Alternative to ASME Code Section Xi,Table IWX-2500 for Arkansas Nuclear One,Unit 2 0CAN129805, LER 98-S02-00:on 981124,security Officer Found Not to Have Had Control of Weapon for Period of Approx 3 Minutes Due to Inadequate self-checking to Ensure That Weapon Remained Secure.All Security Officers Briefed.With1998-12-11011 December 1998 LER 98-S02-00:on 981124,security Officer Found Not to Have Had Control of Weapon for Period of Approx 3 Minutes Due to Inadequate self-checking to Ensure That Weapon Remained Secure.All Security Officers Briefed.With ML20196F4911998-12-0101 December 1998 SER Accepting Request for Relief ISI2-09 for Waterford Steam Electric Station,Unit 3 & Arkansas Nuclear One,Unit 2 ML20198D2441998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ano,Units 1 & 2. with ML20199F7401998-11-16016 November 1998 Rev 9 to ANO-1 Simulator Operability Test,Year 9 (First Cycle) ML20195B4801998-11-0707 November 1998 Rev 20 to ANO QA Manual Operations ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program 0CAN119808, Monthly Operating Repts for Oct 1998 for Ano,Units 1 & 2. with1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Ano,Units 1 & 2. with ML20197H0741998-10-29029 October 1998 Rev 1 to Third Interval ISI Program for ANO-1 ML20155C1351998-10-26026 October 1998 Rev B to Entergy QA Program Manual ML17335A7641998-10-22022 October 1998 LER 98-004-00:on 980923,inadvertent Actuation of Efs Occurred During Surveillance Testing.Caused by Personnel Error.Personnel Involved with Event Were Counseled & Procedure Changes Were Implemented.With 981022 Ltr ML20154J2471998-10-0909 October 1998 SER Accepting Inservice Testing Program,Third ten-year Interval for License DPR-51,Arkansas Nuclear One,Unit 1 0CAN109806, Monthly Operating Repts for Sept 1998 for ANO Units 1 & 2. with1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for ANO Units 1 & 2. with ML20154E2171998-09-28028 September 1998 Follow-up Part 21 Rept Re Defect with 1200AC & 1200BC Recorders Built Under Westronics 10CFR50 App B Program. Westronics Has Notified Bvps,Ano & RBS & Is Currently Making Arrangements to Implement Design Mods 0CAN099803, Monthly Operating Repts for Aug 1998 for ANO Units 1 & 2. with1998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for ANO Units 1 & 2. with ML20237B7671998-08-19019 August 1998 ANO REX-98 Exercise for 980819 ML18066A2771998-08-13013 August 1998 Part 21 Rept Re Deficiency in CE Current Screening Methodology for Determining Limiting Fuel Assembly for Detailed PWR thermal-hydraulic Sa.Evaluations Were Performed for Affected Plants to Determine Effect of Deficiency ML20236X2351998-08-0505 August 1998 Part 21 Rept Re Defect Associated W/Westronics 1200AC & 1200BC Recorders Built Under Westronics 10CFR50,App B Program.Beaver Valley,Arkansas Nuclear One & River Bend Station Notified.Design Mod Is Being Developed 0CAN089804, Monthly Operating Repts for July 1998 for Ano,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ano,Units 1 & 2 ML20196C7831998-07-30030 July 1998 Summary Rept of Results for ASME Class 1 & 2 Pressure Retaining Components & Support for ANO-1 ML20155H7161998-07-15015 July 1998 Rev 1 to 96-R-2030-02, Revised Reactor Vessel Fluence Determination ML20236R0531998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ano,Units 1 & 2 ML20249B7791998-06-22022 June 1998 Part 21 Rept Re Findings,Resolutions & Conclusions Re Failure of Safety Related Siemens 4KV,350 MVA,1200 a Circuit Breakers to Latch Closed ML20249B5091998-06-15015 June 1998 SG ISI Results for Fourteenth Refueling Outage 1999-09-30
[Table view] |
Text
.
M
- = Entergy operations,Inc.
1::252"Entergy 1448 SR 333 gg;;~
September 15,1999 OCAN099907 U. S. Nuclear Regulatory Commission Document Control Desk Mail Station GPI-17 Washington, DC 20555
Subject:
Arkansas Nuclear One -Units 1 and 2 Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Monthly Operating Report Gentlemen:
Arkansas Nuclear One (ANO), Units 1 and 2 Technical Specifications 6.12.2.3 and 6.9.1.6, respectively, require the submittal of a Monthly Operating Report. The purpose of this letter is to complete the reporting requirement for August 1999.
Very truly yours, di T y D. Vanderghft' Director, Nuclear Safety JDV/SLP Attachment
/l o c . .cm 9909210295 990831 PDR ADOCK 05000313 PDR R
U.S. NRC
. September 15,1999
.OCAN099907 Page 2 cc: Mr. Ellis W. Merschoff Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Arkansas Nuclear One P.O. Box 310 London, AR 72847 Mr. Nick Hilton NRR Project Manager Region IV/ANO-1 U. S. Nuclear Regulatory Commission NRR Mail Stop 04-D-03 One White Flint North 11555 Rockville Pike Rockville, MD 20852 Mr. Chris Nolan NRR Project Manager Region IV/ANO-2 U. S. Nuclear Regulatory Commission NRR Mail Stop 04-D-03 One White Flint North 11555 Rockville Pike Rockville, MD 20852
l i
. . 1 i
Arkansas Nuclear One Unit 1 Monthly Operating Report I l
l l
l l
I I
1 i
OPERATING DATA REPORT DOCKET NO: 50-313 UNIT: ANO Unit i DATE: Sept.15,1999 COMPLETED BY: Steven I . Coffman TELEPHONE: (501) 858-5560 OPERATING STATUS
- 1. Unit Name: Arkansas Nuclear One -Unit 1
- 2. Reporting Penod August 1-31
- 3. Licensed Thermal Power (MWt); 2,568
- 4. Nameplate Rating (Gross MWe): 903
- 5. Design Electrical Rating (Net MWe): 850
- 6. Maximum Dependable Capacity (Gross MWe): 883 *
- 7. Maximum Dependable Capacity (Net MWe): 836
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons
- 9. Power level To Which Restncted. If Any (Net MWe):
- 10. Reasons For Restrictions. If Any: J l
l MONTH YR-TO-DATE CUMULATIVE
- 11. Hours in Reporting Period 744.0 5,831.0 216,522.0
- 12. Number of Hours Reactor Was Critical 744.0 5,717.I 166,397.7
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 5,044.0
- 14. Hours Generator On-Line 744.0 5,711.5 163,896.4
- 15. Unit Reserve Shutdown Hours 0.0 0.0 817.5
- 16. Gross Thermal Energy Generated (MWH) 1,909,153 14,615,848 386,771,407
- 17. Gross Electrical Energy Generated (MWII) 653,416 5.069,490 130,289,589
- 18. Net Electrical Energy Generated (MWH) 625,634 , 4,861,948 124,113,336
- 19. Unit Service Factor 100.0 98.0 75.7
- 20. Unit AvailabilityFactor 100.0 98.0 76.I
- 21. Unit Capacity Factor (Using MDC Net) 100.6 99.7 68.6
- 22. Unit Capacity Factor (Using DER Net) 98.9 98.I 67.4
- 23. Unit Forced Outage Rate 0.0 2.0 9.0
- 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duratma of Each):
Refueling Outage IRI5 scheduled to commence Optember 10,1999 with an expected duration of 35 days
- 25. If Shut Down At End of Report Period. Estimated Date of Startup: _
- 26. Units in Test Status (Prior to Commercial Operation): Forecast Achieved INITIAL CRITICALITY 08/06n4 INITIAL ELECTRICITY 08/17/74 COMMERCIAL OPERATION 12/19n4
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-313 UNIT: ANO Unit 1 DATE: Sept.15,1999 COMPLETED BY: Steven L. Coffman TELEPHONE: (501) 858-5560 MONIW: August.1999 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 1= . 835 2: .
835 3......-- . . . .
837
- 4. .
838
- 5. 840 6 . . . . . . .
832 7 .. 838 8........................ 838 9 .. .. . .............
837 10......................... 836 I 1 . . . . . .. .. . .. . . . . .
835 12..................... 835 I 3 ... ..... 835 14 . ...... . 839 15 . . . . . . . 841 16 .. .... . . . . . . .
842 17..... 843 18 . . .... . 843 19...................... 844 20........................ 844 21............... 844
- 22. ...... 844 2 3 .. . . ....... 845
- 24. ........... . 847 25 ....... 847 26................. . 846 27................... 847 28 ... ... . .
845
, 29.................... 844 30 .. ...... . 845 31................ . . . . .
846 ,
AVGS: 841 INSTRUCTION On this format, list the average daily unit power level in MWe-Net for each day in reportmg month Complete to the nearest whole megawatt.
n e O
- 9 n T 9 m 0 N 1
9 o 1
C 6
5 OE I
t i , 5 TC )
U n 5 L 8 CN 1 3
1 1
n e
5 8- AE R 6
1 3- O tp v ER 4-0 N e e 0 1
5 A S t
S 5 V I U G E
TC R CE U Y ER B RT N DE RN s asls e (e OE EN OE i e NM ET O CV nt o Dc)a eaF c
r u
E i T A LH &R t
c uf JR S o
EM K PP EP r o rE I
e CI T ETM2 I S
U t
s noI niof(t n
a ONAOE e A I t s r
- at o S DUDCT C Garphep e e I t
i b r yt eSR i t
T ipr e b i
N h x or nv t e h x
E8 NK EfEE E S
N O
OD PO MC O
4 5 I
T C C
U D M E *X m E99 TD a R91 SQ .e mr n o _
YE i
R t, S u cet rS e c E s c clt u Wgu E #
e Si t sd l l eu e es nR Ou ETT : uuai r PA S NR de nnst d e DR NO AF N
E C
EO VP J EE hMMACIO t
aa e neh e - - - - - -
MI23459 uomt -
I R ST 3 NR WO N OPE F W -
D OOsR T R D DO n
o U
H 0GT 1NC i
t a
n 1II' A S
i 1 E s s
T I ETR ML m e
N H E U S )
i n
e s
n a e 8 l p c N x J O E n I S (t o&
e es i
A r tc g r E uT i ri n o
r R l f i
eo tsi n n r )n Fe c eaoEi a Rrt i l l N) t n n yT ar ep OS e egr rt eE sn I
R s el u mnoe i
t eitsi(
TU inpt elan r n mar ehre i
RAOI ui qaf sueu egpd pt UG EMReOA OO D -BABCDEFGH
- - - R 2
'1 f
X I
E I d A e D d u l
ed c e rh oc g e m FS : :
H No I FS
NRC MONTHLY OPERATING REPORT
. OPERATING
SUMMARY
August 1999 UNIT ONE The unit began the month operating at full power. At 2157 hours0.025 days <br />0.599 hours <br />0.00357 weeks <br />8.207385e-4 months <br /> on the sixth, power was reduced to ~85% to perform the monthly Turbine Governor Valve Testing. The unit returned to ,
full power at 0045 hours5.208333e-4 days <br />0.0125 hours <br />7.440476e-5 weeks <br />1.71225e-5 months <br /> the following day and operated the remainder of the month at full power.
Note: There were no challenges to the primary system code safeties nor automatic actuations of the electromatic relief valve during this reporting period.
I
i i
Arkansas Nuclear One Unit 2 Monthly Operating Report
)
t l
L
OPERATING DATA REPORT DOCKET NO: 50-368 UNIT: ANO Unit 2 DATE: Sept.15,1999 COMPLETED BY: Steven L. Coffman TELEPHONE: (501) 858-5560 OPERATING STATUS i
- 1. Unit Name: Arkansas Nuclear One - Unit 2
- 2. Reporting Period: August 1-31
- 3. Licensed ThermalPower(MWt): 2,815
- 4. Nameplate Rating (Gross MWe): 942.57
- 5. Design Electrical Rating (Net MWe): 912
- 6. Maximum Dependable Capacity (Gross MWe): 897
- 7. Maximum Dependable Capacity (Net MWe): 858
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report, Give Reasons ;
- 9. Power Level To Which Restricted. If Any (Net MWe):
- 10. Reasons For Restrictions. If Any- j MONTH YR-70-DATE CUMULATIVE
- 11. Hoursin Reporting Period 744.0 5.831.0 170,351.0
- 12. Number of Hours Reactor Was Critical 744.0 4,744.5 136,332.I
- 13. Reactor Reserve Shutdowa Hours 0.0 0.0 0.0
- 14. Hours Generator On-Line 744.0 4,688.4 134,026.5
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0 l
- 16. Gmss Thermal Energy Generated (MWH) 2,093,358 12,945,440 359,490,225 l
- 17. Gross Electrical Energy Generated (MWH) 684,842 4,238,454 118,494,787
- 18. Net Electrical Energy Generated (MWH) 653,762 4,045,976 112,824,844
- 19. Unit Service Factor 100.0 80.4 78.7
- 20. Unit Availability Factor 100.0 80.4 78.7 ,
- 21. Unit Capacity Factor (Using MDC Net) 102.4 80.9 77.2
- 22. Unit Capacity Factor (Using DER Net) %.4 76.I 72.6 l
- 23. Unit Forced Outage Rate OLO 0.0 8.8 I 24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):
Mid-Cycle Outane 2P99 Scheduled to begin 1155/M with an expected duration of 25 days.
I
- 25. If Shut Down At End of Report Period. Estimated Date of Startup.
- 26. Units in Test Status (Prior to Commercial Operation): Forecast Achieved INTTIAL CRITICALITY 12/05n8 INITIAL ELECTRICITY 12/26n8 COMMERCIAL OPERATION 03/26/80
i I
AVERAGE DAILY UNIT POWER LEVEL i
DOCKET NO: 50-368 UNIT. ANO Unit 2 DATE: Sept.15,1999 COMPLETED BY: Steven L. Coffman TELEPHONE: (501) 858-5560 MON 7H Au-t 19._92 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 1, . . . ... 876 2 .. = . . . . . . . . .
878 3...................
881 881 4 .. . . . . . . . . . . . ..
5; 879 879 6................
876 7 .... . . ..
g74 8= . . . . . . . . . . .
876 9........ . . .
875 10 . .. . . . . . . . . . . . . . .
875 11................... 873 12.. ... . . . . . .
872 13 . . . . ..
379 14 .. . . . . . . . .
881 15.....................
881 16 .. .. ..
879 17........................
- 18. 876 19 -
877 882 20 .. . . . . . ..
21... 879 4 22 .. .
883 23 ... . . . . .
882 24 . ....
881
- 25. .... . 882 26................. 882
- 27. . . .
880
- 28. .
879 2 9 ... ... . 880 30: ............. 880 31: 884 AVGS: 879 INSTRUCTION On this format, list the average daily unit power level in MWe-Net for each day in reporting month. Complete to the nearest whole megawatt.
n e O n T 9 E N o 0 f
2 9
9 C 6
5 OE I
t i
n 1
5
- TC )
U 5 L 8 CN 1 8 1 n 5 AE R 6
6 O tp e 1
v 4 3-N e e 0 1 ER 4 0
5 A S S 5 t
V I U G E
TC CE R ER U Y N B RT DE RN e e (e
- e. %. EN OE s etasH a f
1 M TO CV s a eaF r u
E i tc Dc)
TA E H &R e EN E K
I PP EP rufo JR IE S e
C T TM2 I I S
U t
snisf(
morL s e
ONAOE A I t t r S e
DUDCT C Gehpe
- a r p
o I
t i
b r yt oSR t i
b T ipr n i N h x rnv t e h x
E8 EfoEE E N3 OM 4 5 S P 3 N ME -
0 O -
1 I
C C
U M D E 'E .
E9 TD m se R99 SO YC . rc n e R1t S e e
rSec st i Es e cciut Wg E # l l Siadt sue On ETT aee
.mumi nR r PA S NR doea snste neh d e DR N E EO hMMACIO memt NO C VP t
AP J EE e M123459 R
ST I NR 3 WOP N OE F W DR T
O O *R D DO n
o U
H OGT i t
a S HINC A i n
T TT ET E s
s e
I N MU R E n _
H U S )
i n
a e
s n
e
'N l
p x J I
c -
O E s S ( t e&
A E
e es r
i tc g r o
R eT l f iri n r) l eo tsi n n r n Fe c eaoEi a Rrt i l l N) t n n Tar exp OS e es ,_rt c -(E R es:
mew *^-
I i^
T U pe en r
.- e A O : in ui ri em rh i
R a s qa e pd t U Hf sEMRAOA e
CO D e - - - - - - - -
RABCDEFGH 2
'1 E
X +
I E
I de A
D d u l
ed ce rh oc g e m FS ::
e FS E M 1
, e e NRC MONTHLY OPERATING REPORT OPERATING
SUMMARY
)
August 1999 UNIT TWO The unit began the month at full power. At 2117 hours0.0245 days <br />0.588 hours <br />0.0035 weeks <br />8.055185e-4 months <br /> on the twenty-first, power was reduced to
~95% power for quarterly Turbine Control Valve testing. The unit was returned to full power at 2356 hours0.0273 days <br />0.654 hours <br />0.0039 weeks <br />8.96458e-4 months <br /> that same day. The unit operated the remainder of the month at full power.
Note: There were no challenges to the primary system code safeties nor automatic actuations of the low temperature overpressure protection valves during this reporting period.