07-19-2006 | On June 22, 2006, at 0620, with the plant at 100% power, it was discovered that there was no battery charger in service on one of the two Train B vital batteries in violation of Technical Specification 3.8.2.1, DC Sources. Further review determined that the battery charger had been disconnected from its associated battery bank since approximately 1858 hours0.0215 days <br />0.516 hours <br />0.00307 weeks <br />7.06969e-4 months <br /> on June 21 when alarms caused by the opening of the battery charger breaker were received in the Control Room.
While securing battery charger 1B after capacity testing, Maintenance electricians opened breaker DN4, which isolated both the battery charger and the portable battery charger from 125 VDC Bus 11B. The maintenance activity should not have repositioned breaker DN4. The opening of the breaker resulted in two Control Room alarms which operators believed to be expected alarms associated with the maintenance activity. The condition went unrecognized for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The cause of the event was personnel error by the electricians for opening the breaker when unsure of how to secure the charger and by the licensed Control Room Operator for incorrectly processing the alarms as expected. Additionally, subsequent Operations personnel failed to recoginize the meaning of the alarms or validate the status of the battery.
D |
---|
LER-2006-004, Technical Specification Violation Due to Inoperable Battery ChargerDocket Number |
Event date: |
06-22-2006 |
---|
Report date: |
07-19-2006 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
---|
4432006004R00 - NRC Website |
|
I. Description of Event
On June 22, 2006, at 0620, with the plant at 100% power, it was discovered that there was no battery charger [EJ, BYC] in service on one of the two Train B vital batteries [EJ, BTRY] in violation of Technical Specification 3.8.2.1, DC Sources. Further review determined that the battery charger had been disconnected from its associated battery bank since approximately 1858 hours0.0215 days <br />0.516 hours <br />0.00307 weeks <br />7.06969e-4 months <br /> on June 21 when alarms caused by the opening of the battery charger breaker [BKR] were received in the Control Room. While securing battery charger EDE- BC-1B [EJ, BYC] after capacity testing, Maintenance electricians opened breaker DN4, which isolated both the battery charger and the portable battery charger from 125 VDC Bus 11B [EJ, BU]. The maintenance activity should not have repositioned breaker DN4. The opening of the breaker resulted in two Control Room alarms which operators believed to be expected alarms associated with the maintenance activity. The condition went unrecognized for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The cause of the event was personnel error by the electricians for opening the breaker when unsure of how to secure the charger and by the licensed Control Room Operator for incorrectly processing the alarms as expected. Additionally, subsequent Operations personnel failed to recoginize the meaning of the alarms or validate the status of the battery.
The oncoming Control Room day shift questioned the alarms and discovered that 125 VDC bus 11B was supplied by its battery and that battery charger EDE-BC-1B was out of service. The battery charger was declared inoperable and TS 3.8.2.1 entered. At 0722 on June 22, 2006 station personnel closed the battery charger breaker to 125 VDC Bus 11B and exited TS 3.8.2.1.
II. Cause of Event
The cause for the event is personnel error by the electricians for opening battery charger output breaker DN4 when unsure of how to secure the charger. The maintenance procedure lacked detailed steps for "securing the battery charger." Although other electricians have successfully used the procedure in past maintenance activities, in this event the electricians were unsure of how to secure the battery charger. Upon recognition of the inadequate procedural guidance, the electricians did not seek clarification of the instruction, but developed a plan based on their understanding of the assignment and system line up to secure the battery charger. They did not stop and process a procedure change to incorporate the plan into the procedure.
A personnel error was also committed by Licensed Control Room Operators who assumed the alarms were associated with maintenance activities. The cause for this personnel error is that a licensed operator incorrectly processed the alarms as expected for the maintenance activity being performed. The licensed operator discussed the maintenance activity with the electrician, but resultant alarms and expected durations were not identified. Based on the communication with the electrician, the licensed operator processed the alarms as "expected," which resulted in Operations personnel failing to validate the reasons for the alarms. In addition, subsequent Operations personnel failed to recognize the meaning of the alarms or validate the actual status of the battery.
III. Analysis of Event
Each Train of the safety related portion of the DC power system consists of two 125-volt batteries, battery chargers and distribution panels. The loads supplied by the distribution panels include inverters for redundant vital instrument busses, distribution panels for power to Class lE loads, power for control and operation of Class lE systems for Engineered Safety Features, and power for selected non-Class lE loads. There are two Trains of DC power system at Seabrook Station. Each Train is equipped with a spare battery charger that can be connected to either battery on that Train.
The event consisted of not having a battery charger connected to one of the four vital batteries (EDE-B-1B) for a period of time longer than allowed by Technical Specification 3.8.2.1. While a battery charger was not connected, the associated battery provided power to the associated loads. Analysis determined that EDE-B- 1B would have been able to supply the 2-hour and 4-hour load profiles if a loss of offsite power or station blackout had occurred during the 12-hour period that the battery charger was disconnected.
This event is of regulatory significance because it met the reporting criterion of 10 CFR 50.73(a)(2)(i)(B) for a condition prohibited by the TS. The event was reported to the NRC on June 22, 2006 at 1428 (event # 42260) in accordance with Seabrook Station operating license condition 2.G for a violation of the Technical Specifications.
The event had no adverse impact on the plant or on the health and safety of the public or plant personnel. No plant transients, system actuations, or consequences resulted from the event. No other inoperable structures, systems, or components contributed to this event. The condition did not involve a safety system functional failure.
IV. Corrective Action The corrective actions to address this event include:
1. The individuals involved were coached and mentored on Station expectations.
2. An Operations Department Improvement Initiative was issued that focused on reinforcing management's expectations regarding the conduct of operations including control board monitoring, alarm response, configuration control and the return of equipment to service.
3. Management on shift obervations were conducted with each operating crew for a minimum of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to ensure consistent adherence to Station standards for the Conduct of Operations.
4. The Operations Department Manager will walk down this event in the field with Operations shift personnel, highlighting the actual vs. expected performance, what information and indications should have been used and what the expectations are for the Department.�
- 5. The Maintenance Department Manager will walk down this event in the field with Mechanical, Electrical and MC Maintenance personnel, highlighting the actual vs. expected performance, what information and indications should have been used and what the expectations are for the Department.
V. Similar Events A review of LERs for the previous two years did not identify any similar events.
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|