07-18-2006 | On April 19, 2006, while removing insulation from the surge line of the Unit 1 pressurizer, an insulation contractor discovered boric acid on the insulation. On April 25, 2006, the leakage was identified as originating from the number 52 pressurizer heater near the upper weld between the pressurizer heater sleeve and heater coupling. Technical Requirements Manual Limiting Condition for Operation (TI r.n) 3.4.f rnnriitinn A was entered for ^no Or more ASME components not in conformance due to pressure boundary leakage. The heater coupling and a portion of the sleeve was cut out of the system and the remaining portion of the heater sleeve was plugged and welded using an engineered ASME section III repair detail. On April 28, 2006, following the repair of the pressurizer, TLCO 3.4.f Condition A was exited.
Analysis of the boric acid found on the pressurizer and the pressurizer insulation determined a leak existed during the past operating cycle which is not in compliance with Technical Specification 3.4.13, "RCS Operational Leakage," that states there will be no pressure boundary leakage in Modes 1, 2, 3 and 4. This leak was identified through refueling outage inspection activities, not during plant operation.
The root cause of the observed boric acid leakage was intergranular stress corrosion cracking of the number 52 pressurizer heater sleeve through a locally sensitized section of the Type 316 stainless steel base material. The corrective action to prevent recurrence will be the implementation of long-term recommendations provided by the Exelon Generation Company, LLC, Asset Management Group to prevent future leakage, and implementation of actions required o comply with industry guidance to accept visual examinations for evidence of leakage.
There were no safety consequences impacting plant or public safety as a result of this event. This event is being reported pursuant to 10 CFR 50.73(a)(2)(i)(B) and 10 CFR 50.73(a)(2)(ii)(A). |
---|
LER-2006-001, Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater SleeveDocket Number |
Event date: |
04-25-2006 |
---|
Report date: |
07-18-2006 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded |
---|
Initial Reporting |
---|
4562006001R01 - NRC Website |
|
A. Plant Operating Conditions Before The Event:
Event Date: April 25, 2006 Event Time: 0030 Unit: 1 MODE: 6 Reactor Power: 0.0 percent Unit 1 Reactor Coolant System (RCS) [AB] Temperature: 92 degrees F, Pressure: N/A
B. Description of Event:
There were no additional structures, systems or components inoperable at the beginning of the event that contributed to the severity of the event.
On April 19, 2006, at 0300, while removing insulation from the surge line of the Unit 1 pressurizer, an insulation contractor discovered boric acid on the insulation.
On April 25, 2006, at 0030, following an extensive investigation, Exelon Generation Company, LLC (EGC) identified rouging on the insulation penetration for pressurizer [AB] heater number 52. Rouging is the development of surface deposits or staining, and is an indication of possible high temperature steam impingement on stainless steel. The leakage was identified as originating from the number 52 heater near the upper weld between the pressurizer heater sleeve and heater coupling. Technical Requirements Manual Limiting Condition for Operation (TLCO) 3.4.f Condition A was entered for one or more ASME components not in conformance due to pressure boundary leakage.
Analysis of the boric acid found on the pressurizer and the pressurizer insulation determined a leak existed during the past operating cycle which is not in compliance with Technical Specification (TS) 3.4.13, "RCS Operational Leakage," that states there will be no pressure boundary leakage in Modes 1, 2, 3 and 4. This leak was identified through refueling outage inspection activities, not during plant operation.
The heater coupling and a portion of the sleeve was cut out of the system and the remaining portion of the heater sleeve was plugged and welded using an engineered ASME Section III repair detail. A complete visual inspection of all 78 pressurizer heaters was performed to determine the initial extent of condition. Heater number 52 was identified as the only source of boric acid leakage from the pressurizer.
On April 28, 2006, at 0143, following the repair of the pressurizer, TLCO 3.4.f Condition A was exited.
. Cause of Event The coupling and portion of the heater sleeve removed were shipped to a testing facility to determine the cause of the observed leak.
The failure analysis of the removed heater sleeve identified a through-wall crack located in the heat affected zone of the heater sleeve near the upper coupling weld. The failure was caused by circumferentially oriented intergranular stress corrosion cracking (IGSCC). The crack propagated through the heater sleeve heat affected zone appearing to be heavily sensitized during fabrication welding. Typically, the material used for the sleeve, Type 316 stainless steel, is not susceptible to IGSCC in a pressurized water reactor (PWR) environment. However, sensitized 316 stainless steel can be susceptible to IGSCC in stagnant PWR environments containing oxygen. With the heater element inserted into the sleeve, a long, cylindrical, crevice, approximately 0.015" wide by 12" long, is created between the heater element and the sleeve.
Analysis of the boric acid found on the pressurizer and the pressurizer insulation determined a leak existed during the past operating cycle which is not in compliance with TS 3.4.13, "RCS Operational Leakage," that states there will be no pressure boundary leakage in Modes 1, 2, 3 and 4. This leak was identified through refueling outage inspection activities, not during plant operation.
The root cause of the observed boric acid leakage was IGSCC of the number 52 pressurizer heater sleeve though a locally sensitized section of the Type 316 stainless steel base material. The heater sleeve was sensitized through minor cold working of the inner diameter bore and by the heat generated by multiple weld passes on the coupling to heater sleeve weld.
D. Safety Consequences:
There were no safety consequences impacting plant or public safety as a result of this event.
All 78 PZR heater sleeves and couplings were visually inspected in the refueling outage. Heater 52 was confirmed to be the only leakage source. Based on the amount of boric acid present, the leak size was determined to be extremely small and the associated leak rate would be too small to be captured by normal surveillance methods. If leakage had increased, the normal charging system would be used to compensate for the leakage. The leak was identified through refueling outage inspection activities, not during plant operation. Had the pressure boundary leakage condition been identified in Modes 1, 2, 3 or 4, TS 3.4.13, "RCS Operational Leakage," would have required a Unit 1 shutdown to identify the leakage source and to perform the necessary repairs prior to resuming operation.
Operating experience for this design of stainless steel heater sleeve indicates that the heater at location 52 of Braidwood Unit 1 represents the only occurrence of IGSCC-induced circumferential cracking in the industry. With no other occurrences of leakage occurring in this large population of stainless steel heater sleeves, this data suggests an extremely low probability of occurrence of cracking in another heater sleeve.
A postulated severance or ejection of a heater sleeve due to circumferential cracking was evaluatAd. Ejection of A heater sleeve was found to be equivalent to a small break loss of coolant accident (SBLOCA). The consequences of such an event are bounded by the results of existing SBLOCA emergency core cooling system performance analysis.
Therefore, the impact on normal plant operation was insignificant.
This event did not result in a safety system functional failure.
E. Corrective Actions:
The corrective actions include:
- Cut out the failed heater sleeve portion, plug, and seal weld the sleeve to prevent further leakage. This action has been completed.
- Visually inspect all of the pressurizer heater sleeves for signs of boric acid leakage every refueling outage on Unit 1 and Unit 2, beginning with the next Unit 2 refueling outage, as the first inspection has already been completed on Unit 1. Inspections will be performed at every refueling outage, pending more definitive industry guidance. Inspections are to be bare metal inspections conducted by opening the convection shields or by removal of the mirror insulation.
The corrective action to prevent recurrence will be the implementation of long-term recommendations provided by the EGC Asset Management Group to prevent future leakage, and implementation of actions required to comply with industry guidance to accept visual examinations for evidence of leakage.
Previous Occurrences:
There have been no previous similar events at Braidwood Station.
Component Failure Data:
Manufacturer � Nomenclature � Model � Mfg. Part Number Westinghouse � Pressurizer � 1100J48 � N/A NRC FOR 66A (1-2001)
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|