| | Reporting criterion |
---|
05000305/LER-2006-010 | | |
05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded |
05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | |
05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident |
05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | |
05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor |
05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | |
05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation |
05000289/LER-2006-001 | | |
05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | |
05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown |
05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown |
05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function |
05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition |
05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | |
05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | |
05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | |
05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | |
05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | |
05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000293/LER-2006-002 | | |
05000289/LER-2006-002 | | |
05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition |
05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | |
05000263/LER-2006-002 | | |
05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |