05000305/LER-2006-002, Re Safety-Related Relay Racks with Improper Quality Classification of Foxboro Signal Conditioning Modules
| ML061780191 | |
| Person / Time | |
|---|---|
| Site: | Kewaunee (DPR-043) |
| Issue date: | 06/19/2006 |
| From: | Hartz L Dominion Energy Kewaunee |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 06-519 LER 06-002-00 | |
| Download: ML061780191 (6) | |
| Event date: | |
|---|---|
| Report date: | |
| Reporting criterion: | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(ix)(A) 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(viii)(B) |
| 3052006002R00 - NRC Website | |
text
4~Dominion Dominion Energy Kewaunee, Inc.
N490 Highway 42, Kewaunee, WI 54216-9511 JUN 19 2006 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 Serial No.06-519 KPS/LIC/RR: RO Docket No.
50-305 License No. DPR-43 DOMINION ENERGY KEWAUNEE, INC.
KEWAUNEE POWER STATION LICENSEE EVENT REPORT 2006-002-00
Dear Sirs:
Pursuant to 10 CFR 50.73, Dominion Energy Kewaunee, Inc., hereby submits the following Licensee Event Report applicable to Kewaunee Power Station.
Report No. 50-305/2006-002-00 This report has been reviewed by the Plant Operating Review Committee and will be forwarded to the Management Safety Review Committee for its review.
If you have any further questions, please contact Mr. Richard Repshas at (920) 388-8217.
Very truly yours, Leslie N. Hartz Site Vice President, Kewaunee Power Station Attachment Commitments made by this letter: NONE
ýJ:0ý
Serial No.06-519 Page 2 of 2 cc:
Regional Administrator, Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 Mr. D. H. Jaffe Project Manager U.S. Nuclear Regulatory Commission Mail Stop O-7-D-1 Washington, D. C. 20555 NRC Senior Resident Inspector Kewaunee Power Station
NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES 6-30-2007 (6-2004)
Estimated burden per response to comply with this mandatory collection request: 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br />.
Reported lessons learned are incorporated into the licensing process and ted back to industry.
LICENSEE EVENT REPORT (LER)
Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-(See reverse for required number of mail to Infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0066), Office of Management and Budget, Washington, DC 20503.
digits/characters for each block)
If a means used to Impose an Information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the Information collection.
FACILITY NAME (1)
DOCKET 1
of 4
Kewaunee Power Station000351 o
4 TITLE (4)
Safety-Related Relay Racks with Improper Quality Classification of Foxboro Signal Conditioning Modules EVENT DATE (5)
LER NUMBER (6)
REPORT DATE (7)
OTHER FACILITIES INVOLVED (8)
SEQUENTIAL IREV FACILITY NAME DOCKET NUMBER MO DAY YEAR YEAR NUMBER NO MO DAY YEAR 04 18 2006 2006
-- 002 --
00 06 19 2006 FACILITYNAME DOCKETNUMBER OPERATING N
THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR 0: (Check all that apply) (11)
MODE (9) 20.2201(b)
- 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(B) 50.73(a)(2)(ix)(A)
POWER 20.2201(d) 20.2203(a)(4) 50.73(a)(2)(iii) 50.73(a)(2)(x)
LEVEL (10) 100 20.2203(a)(1) 50.36(c)(1)(i)(A) 50.73(a)(2)(iv)(A) 73.71 (a)(4)
__ 20.2203(a)(2)(i) 50.36(c)(1)(ii)(A) 50.73(a)(2)(v)(A) 73.71(a)(5) 20.2203(a)(2)(ii) 50.36(c)(2) 50.73(a)(2)(v)(B)
OTHER 20.2203(a)(2)(iii) 50.46(a)(3)(ii)
X 50.73(a)(2)(v)(C)
Specify In Abstract below or in 20.2203(a)(2)(iv) 50.73(a)(2)(i)(A) 50.73(a)(2)(v)(D).
20.2203(a)(2)(v)
X 50.73(a)(2)(i)(B) 50.73(a)(2)(vii) 20.2203(a)(2)(vi) 50.73(a)(2)(i)(C) 50.73(a)(2)(viii)(A) 20.2203(a)(3)(i) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(B)
LICENSEE CONTACT FOR THIS LER (12)
NAME TELEPHONE NUMBER (Include Area Code)
Richard Renshas (920) 388-8217 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT 13)
MANU-REPORTABLE I
MANU-REPORTABLE
CAUSE
SYSTEM COMPONENT FACTURER TO EPIX
CAUSE
SYSTEM COMPONENT FACTURER TO EPIX SUPPLEMENTAL REPORT EXPECTED (14)
EXPECTED MONTH DAY YEAR SUBMISSION YES (If yes, complete EXPECTED SUBMISSION DATE).
X NO DATE (15)
I [ABSTRACT On April 18, 2006 at 1200 central standard time (CST), relay racks RR-1 19 and RR-120 were identified to contain Foxboro signal conditioning modules that did not have the required safety-related quality classification.
Equipment powered through these relay racks was declared inoperable. The signal conditioning modules require a classification of safety-related for electrical boundary and non safety-related for function. Four modules were identified that did not have a safety-related classification in RR-1 19 and two modules were identified that that did not have a safety-related classification in RR-1 20.
The following instrumentation and equipment were declared inoperable for relay racks RR-1 19 (Train A) and RR-1 20 (Train B): Reactor coolant system subcooling, reactor vessel level indication system, pressurizer safety valve outlet temperature, pressurizer power operated relief valve outlet temperature, and shield building ventilation damper control.
The station entered a 12-hour Technical Specification (TS) action statement for both trains of the shield building ventilation system being declared inoperable. This TS was exited at 1611 CST on April 18, 2006 with the return to service of RR-1 20. A seven day action statement for one train of the shield building ventilation system being inoperable was exited with RR-1 19 returned to service at 2128 CST on April 18, 2006.
This event was reported under 10 CFR 50.72(b)(3)(v)(C) for any event that could have prevented the fulfillment of the safety function of systems needed to control the release of radioactive material and is considered a safety system functional failure.U.S. NUCLEAR REGULATORY COMMISSION (1-2001)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
I SEQUENTIAL I REVISION Kewaunee Power Station 05000305 NUMBER NUMBER 2 of 4 2006 002 00 TEXT (If more space is required, use additional copies of NRC Form 366A) (17)
Event Description
On April 18, 2006 at 1200 central standard time (CST), relay [RLY] racks [RK] RR-1 19 and RR-120 were identified to contain Foxboro signal conditioning modules that did not have the required safety-related quality classification. Equipment powered through these relay racks was declared inoperable. The signal conditioning modules require a classification of safety-related for electrical boundary and non safety-related for function.
Four modules were identified that did not have a safety-related classification in RR-1 19 and two modules were identified that did not have a safety-related classification in RR-120.
The following instrumentation and equipment powered through relay racks RR-1 19 (Train A) and RR-120 (Train B) were declared inoperable: Reactor coolant system subcooling [TI], reactor vessel level [LI] indication system, pressurizer safety valve outlet temperature [TI], pressurizer power operated relief valve outlet temperature [TI], and shield building ventilation damper control [CDMP].
The station entered a 12-hour Technical Specification (TS) action statement for both trains of the shield building ventilation system being declared inoperable. This TS was exited at 1611 CST on April 18, 2006 with return to service of RR-120. A seven day action statement for one train of the shield building ventilation system being inoperable was exited with RR-1 19 returned to service at 2128 CST on April 18, 2006.
The relay racks were declared inoperable due to non safety-related fuses [FU] and cables [CBL] installed in six of the signal conditioning modules in these relay racks. The instruments associated with the six modules were not found in TS required instruments or alarms. The concern was that a downstream failure on the non safety-related modules could impact safety-related equipment since it did not have safety-related fault protection.
This event was reported under 10 CFR 50.72(b)(3)(v)(C) "Any event that at the time of discovery could have prevented the fulfillment of the safety function of systems that are needed to control the release of radioactive material." Event Notification 42509 was made on April 18, 2006 at 1922 CST.
An extent of condition was initiated to review all relay racks. Relay racks RR-101, RR-102, RR-103, RR-104, RR-105, RR-116, RR-117, RR-1 18, RR-1 19, and RR-120 were determined to have safety classification issues. Engineering evaluated if the equipment contained inside the relay racks was properly evaluated for the safety classification assignment. The purchase orders were reviewed for proper safety classification and the work history was reviewed for proper safety classification. All discrepancies were evaluated to determine the potential impact on safety related functions. Actions were taken as necessary to upgrade the applicable modules to the proper safety classification by either returning the module to the vendor for refurbishment and recertification or replacing the module. Further evaluation determined that none of the discrepancies impacted a safety-related function.
The Foxboro modules classified as non safety-related are maintained under the same vendor manuals, which use the same part numbers, as those classified as safety-related. All the parts purchased as spares are qualified as safety-related to avoid the possibility of putting non safety-related parts in safety-related applications. The power plug [CON] and cord set, chassis, fuse, and fuse holder are the same construction as all other Foxboro "H" line series of modules.U.S. NUCLEAR REGULATORY COMMISSION (1-2001)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3) tYEAR I
SEQUENTIAL I REVISION Kewaunee Power Station 05000305 NUMBER NUMBER 3 of 4
[ 2006 002 00 TEXT (If more space is required, use additional copies of NRC Form 366A) (17)
Event Analysis and Safety Significance:
This event is being reported in accordance with 10 CFR 50.73(a)(2)(i)(B) "Any operation or condition that was prohibited by the plant's Technical Specifications" and 10 CFR 50.73(a)(2)(v)(C) "Any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to control the release of radioactive material."
Equipment and instrumentation important to safety that could potentially be lost were both trains of the shield building ventilation damper controls and accident instrumentation. The scenario would be for an internal electrical short to occur in a non safety-related Foxboro module in each of relay racks RR-1 19 and RR-1 20 that could cause the entire loss of safety-related power to the relay racks.
Proper functioning of the shield building ventilation system is required to establish containment integrity. TS 3.6.a states: "Containment system integrity shall not be violated if there is fuel in the reactor which has been used for power operation, except whenever either of the following conditions remains satisfied: (1) The reactor is in the cold shutdown condition with the reactor vessel head installed, or (2) The reactor is in the refueling shutdown condition."
TS Table TS 3.5-6 contains the specifications for the instrumentation declared inoperable. TS 3.5.e states:
'The accident monitoring instrumentation in Table TS 3.5-6 shall be operable whenever the plant is above hot shutdown." The basis for this is to assure there is sufficient information available to aid the operator in identification of an accident and assessment of plant conditions during and following an accident. Although this event caused some of the TS Table TS 3.5-6 instrumentation to be inoperable, operation was within the allowance of the specifications.
This is considered a safety system functional failure since this condition could have prevented the fulfillment of the safety function of systems that are needed to control the release of radioactive material.
The safety significance associated with this event is minimal. The probabilistic risk model for Kewaunee analyzes for contributions to core damage and a large early release from containment. The shield building ventilation system is not a contributor to the core damage frequency or the large early release frequency, therefore the safety significance is minimal.
Cause
The initial results of the investigation determined that the causes of the relay rack equipment safety classification discrepancies are inaccurate asset database information and the installation of non safety-related modules in safety-related relay racks by the use of the asset database information in the development of maintenance work orders.U.S. NUCLEAR REGULATORY COMMISSION (1-2001)
LICENSEE EVENT REPORT (LER)
TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL REVISION Kewaunee Power Station 05000305 1
NUMBER NUMBER 4 of 4 2006 002 00 TEXT (If more space is required, use additional copies of NRC Form 366A) (17)
Corrective Actions
- 1. The non safety-related signal conditioning modules for RR-119 and RR-120 were immediately replaced or unplugged.
- 2. An extent of condition review was performed to determine the safety-related functions of instrumentation and components powered through the relay racks and correct any discrepancies found.
- 3. The necessary safety classification changes to the asset database were identified and are in the process of being changed.
Similar Events
None.