12-14-2016 | Between October 15 and October 19, 2016, the Shearon Harris Nuclear Power Plant (SHNPP) reactor vessel closure head penetrations were being examined. SHNPP was shut down for a scheduled refueling outage ( RFO) for cycle 20 (RFO-20).
Nondestructive examinations identified four rejectable indications impacting four penetration nozzles. Indications associated with nozzles 30, 40, and 51 were indicative of primary water stress corrosion cracking (PWSCC), with the largest indication having an axial extent of 0.372 in. with a through-wall extent of 0.247 in. (39 percent). The fourth indication was identified on nozzle 23 by dye penetrant testing. This indication had a rounded profile indicative of a weld fabrication void, and was 0.307 in. on the major dimension.
The weld was fabricated during the previous outage, RFO-19. The void was originally identified during RFO-19 and was acceptable.
However, the void has since opened to unacceptable dimensions due to normal operating conditions.
A leak path assessment and a bare metal visual examination of the reactor vessel head top was completed, with no leakage identified.
The three PWSCC indications were repaired using the inside diameter temper bead weld method. The fabrication void was removed via localized grinding, with no additional welding necessary. All repairs were completed prior to exiting the refueling outage. |
---|
|
---|
Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20243012023-05-15015 May 2023 – Notification of Licensed Operator Initial Examination 05000400/2024301 IR 05000400/20230012023-05-10010 May 2023 – Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 2024-09-10
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out 05000400/LER-2022-006-02, Auxiliary Feedwater Pump Inoperability2023-07-11011 July 2023 Auxiliary Feedwater Pump Inoperability 05000400/LER-1922-006-01, Auxiliary Feedwater Pump Inoperability2023-03-10010 March 2023 Auxiliary Feedwater Pump Inoperability 05000400/LER-2022-007-01, Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus2023-01-26026 January 2023 Automatic Reactor Trip Due to Loss of Power from the a Auxiliary Bus 05000400/LER-2022-006, Auxiliary Feedwater Pump Inoperability2022-12-20020 December 2022 Auxiliary Feedwater Pump Inoperability 05000400/LER-2022-007, Automatic Reactor Trip Due to Loss of Power from the ‘A’ Auxiliary Bus2022-12-20020 December 2022 Automatic Reactor Trip Due to Loss of Power from the ‘A’ Auxiliary Bus 05000400/LER-2022-008, Automatic Actuation of Auxiliary Feedwater System2022-12-19019 December 2022 Automatic Actuation of Auxiliary Feedwater System 05000400/LER-2022-005-01, Manual Reactor Trip Due to B Condensate Pump Motor Failure2022-11-28028 November 2022 Manual Reactor Trip Due to B Condensate Pump Motor Failure 05000400/LER-2022-005, Manual Reactor Trip Due to B Condensate Pump Motor Failure2022-10-21021 October 2022 Manual Reactor Trip Due to B Condensate Pump Motor Failure 05000400/LER-2022-004, Both Trains of High Head Safety Injection Inoperable2022-06-30030 June 2022 Both Trains of High Head Safety Injection Inoperable 05000400/LER-2022-003, Manual Reactor Trip Due to Degrading Condenser Vacuum2022-06-28028 June 2022 Manual Reactor Trip Due to Degrading Condenser Vacuum 05000400/LER-2022-001, Essential Services Chilled Water Chiller Inoperable Due to Pre-Rotation Vane Actuator Control Arm Position2022-03-10010 March 2022 Essential Services Chilled Water Chiller Inoperable Due to Pre-Rotation Vane Actuator Control Arm Position 05000400/LER-2016-0072017-02-0909 February 2017 Containment Spray System Valve Actuation, LER 16-007-01 for Shearon Harris Unit 1, Regarding Containment Spray System Valve Actuation 05000400/LER-2016-0062016-12-14014 December 2016 Reactor Vessel Closure Head Penetration Nozzle Indications Attributed to Primary Water Stress Corrosion Cracking and a Weld Fabrication Void, LER 16-006-00 For Shearon Harris Nuclear Plant, Unit 1 Regarding Reactor Vessel Closure Head Penetration Nozzle Indications Attributed to Primary Water Stress Corrosion Cracking and a Weld Fabrication Void 05000400/LER-2016-0042016-12-0707 December 2016 Reactor Trip and Safety Injection During Turbine Control Testing at Low Power, LER 16-004-00 for Shearon Harris, Unit 1, Regarding Reactor Trip and Safety Injection During Turbine Control Testing at Low Power 05000400/LER-2016-0052016-12-0707 December 2016 Offsite Power Undervoltage Caused Actuation of Several Systems, LER 16-005-00 for Shearon Harris Nuclear Power Plant, Unit 1 Regarding Offsite Power Undervoltage Caused Actuation of Several Systems 05000400/LER-2016-0022016-09-19019 September 2016 'A' Essential Services Chilled Water Chiller Trip due to Oil Leak from Failed Tube Fitting, LER 16-002-00 for Shearon Harris, Unit 1, Regarding 'A' Essential Services Chilled Water Chiller Trip Due to Oil Leak from Failed Tube Fitting 05000400/LER-2016-0012016-09-0101 September 2016 Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions, LER 16-001-00 for Shearon Harris, Unit 1, Regarding Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions ML1015505742010-01-12012 January 2010 Event Notification for Harris on Offsite Notification Due to Discovery of Tritium in Water Leakage Onsite 2024-07-22
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Inf000llects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
2016 006 Shearon Harris Nuclear Power Plant — Unit 1 05000- 400 00 3. LER NUMBER 1. FACILITY NAME Note: Energy Industry Identification System (EllS) codes are identified in the text within brackets [ ].
A. Background
Event Date: October 15, 2016 through October 19, 2016 Mode: 6 Reactor Power: 0 percent In October 2016, Shearon Harris Nuclear Power Plant (SHN PP) was shut down for the scheduled refueling outage (RFO) for cycle 20 (RFO-20). During the outage, the inspection of the reactor vessel closure head (RVCH) [RPV] control rod drive mechanisms (CRDM) [DRIV] penetration nozzles [NZL] occurred. The RVCH was manufactured by Chicago Bridge and Iron, Serial Number T40.
No Structures, Systems or Components (SSCs) were inoperable at the start of this event that contributed to the event. No change in plant mode or in reactor power occurred as a result of this event.
This condition is reportable in accordance with 10 CFR 50.73(a)(2)(ii)(A), as an event or condition that resulted in the condition of the nuclear power plant, including its principal barriers, being degraded.
B. Event Description
Nondestructive examinations (NDE) identified four rejectable indications, each impacting a separate penetration nozzle.
Indications associated with nozzles 30, 40, and 51 were identified through ultrasonic (UT) examination and were attributed to primary water stress corrosion cracking (PWSCC). All three PWSCC indications exhibited an axial orientation and were located on the downhill side of the nozzle at the toe of the J-groove weld. The indications had an axial extent of 0.223 in., 0.372 in., and 0.223 in. for nozzles 30, 40, and 51, respectively. The through-wall extent was 0.049 in. (8 percent), 0.247 in. (39 percent), and 0.152 in. (24 percent) for nozzles 30, 40, and 51, respectively.
The fourth indication was identified on nozzle 23 by penetrant testing. This indication had a rounded profile indicative of a weld fabrication void, and was located in the mid-section of the weld bevel on the high hill side of the nozzle. The size of the indication was 0.307 in. on the major dimension. The weld was fabricated during the previous outage, RFO-19, where the void was originally identified and was found to be acceptable. However, the void has since opened to unacceptable dimensions due to normal operating conditions.
The 2004 Edition of the ASME Code Section XI Acceptance Criteria in Table IWB-3663-1 General Note (a) states, "Linear surface flaws of any size in the partial penetration nozzle to vessel (J-groove weld) are not acceptable." A rejectable flaw in a partial penetration nozzle weld in the RVCH does not meet the acceptance standards referenced per ASME Code Case N-729-1. ASME code also provides acceptance criteria for leaving acceptable rounded indications in place. Thus, all rejectable PWSCC and rounded weld fabrication voids required repair and were reportable as a degraded barrier.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Inf000llects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
2016 006 Shearon Harris Nuclear Power Plant — Unit 1 05000- 400 00 3. LER NUMBER 1. FACILITY NAME C. Causal Factors The cause of the indications in nozzles 30, 40 and 51 was attributed to PWSCC, which occurs under conditions of high tensile stresses (operating and/or residual), conducive environment (temperature and chemistry), and susceptible material. The CRDM nozzles in the HNP RVCH were originally constructed from Alloy 600 tubing and Alloy 82/182 weld metal. There is widespread industry operating experience that documents PWSCC of Alloy 600 dissimilar metal weld configurations.
Nozzle 23 was repaired during RFO-19 using the inside diameter temper bead (IDTB) weld method. In spite of the precautions in place to ensure first-time weld quality when executing weld repairs on Class 1 components, fabrication voids will occasionally occur. The pre-service examination of the repair identified a rounded indication of 0.135 in. on the major dimension, which is within the acceptance threshold of less than 0.1875 in. During RFO-20, the same indication was identified as having opened to 0.307 in. on the major dimension. This change is the result of normal operating conditions.
The fabrication void was removed, thus no further opening of the void is anticipated.
D. Corrective Actions
A leak path assessment and a bare metal visual examination of the reactor vessel head top was completed, with no leakage identified. The three PWSCC indications were repaired using the IDTB weld method. The fabrication void was removed via localized grinding, with no additional welding necessary. Penetrant testing was performed, revealing no further fabrication void in the repaired location. All RVCH CRDM nozzles were inspected, as required by ASME Code Case, due to previously identified PWSCC indications.
E. Safety Analysis
After PWSCC was identified in RFO-17, inspections of the RVCH were required every refueling outage in accordance with ASME Code Case N-729-1, as conditioned by 10 CFR 50.55a. These inspections include NDE for all RVCH penetrations to identify indications, and are supplemented by bare metal visual examinations of the RVCH. If rejectable indications are found, repairs are completed in accordance with both ASME Code and with relief requests submitted to the NRC on a case-by-case basis. This ensures indications are identified and repaired before any significant impact on the integrity of the weld occurs.
The bare metal visual examination and UT examination did not reveal any through-wall leakage. There was not a breach in the fission product barrier, and the structural integrity of the reactor vessel was not significantly compromised.
Therefore, there was no significant impact to the health and safety of the public.
F. Additional Information
PWSCC has previously been detected for welds associated with nozzles 5, 17, 38, 49, and 63 (RFO-17), 37 (RFO-18), and 14, 18, and 23 (RFO-19). LERs 2013-001-00, 2013-003-00, and 2015-003-00 all document previous experience with indications in the RVCH CRDM penetration nozzles.
|
---|
|
|
| | Reporting criterion |
---|
05000400/LER-2016-001 | Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions LER 16-001-00 for Shearon Harris, Unit 1, Regarding Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000400/LER-2016-002 | 'A' Essential Services Chilled Water Chiller Trip due to Oil Leak from Failed Tube Fitting LER 16-002-00 for Shearon Harris, Unit 1, Regarding 'A' Essential Services Chilled Water Chiller Trip Due to Oil Leak from Failed Tube Fitting | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000400/LER-2016-003 | Containment High-Range Radiation Monitors Declared Inoperable Due to Potential for Temperature Induced Current | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000400/LER-2016-004 | Reactor Trip and Safety Injection During Turbine Control Testing at Low Power LER 16-004-00 for Shearon Harris, Unit 1, Regarding Reactor Trip and Safety Injection During Turbine Control Testing at Low Power | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000400/LER-2016-005 | Offsite Power Undervoltage Caused Actuation of Several Systems LER 16-005-00 for Shearon Harris Nuclear Power Plant, Unit 1 Regarding Offsite Power Undervoltage Caused Actuation of Several Systems | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000400/LER-2016-006 | Reactor Vessel Closure Head Penetration Nozzle Indications Attributed to Primary Water Stress Corrosion Cracking and a Weld Fabrication Void LER 16-006-00 For Shearon Harris Nuclear Plant, Unit 1 Regarding Reactor Vessel Closure Head Penetration Nozzle Indications Attributed to Primary Water Stress Corrosion Cracking and a Weld Fabrication Void | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000400/LER-2016-007 | Containment Spray System Valve Actuation LER 16-007-01 for Shearon Harris Unit 1, Regarding Containment Spray System Valve Actuation | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
|