05-26-2006 | On March 29, 2006, SCE initiated a controlled shutdown of Unit 3 in order to perform an inspection for a problem identified on Unit 2 (see LER 3-2006-002). At approximately 1450 PDT on March 29, 2006, with Unit 3 in Mode 4, SCE identified boric acid crystals on the Mechanical Nozzle Seal Assembly (MNSA) installed on the Unit 3 pressurizer Resistance Temperature Detector ( RTD) mechanical nozzle. SCE inspected and confirmed RCS leakage past the MNSA seal and is reporting this occurrence in accordance with 10CFR50.73(a)(2)(i)(B) as a condition prohibited by Technical Specifications.
SCE concluded that the RCS leak was caused by (1) primary water stress corrosion cracking of the pressurizer nozzle and (2) incomplete compression of the MNSA grafoil seal when the MNSA was installed (March 1998).
SCE removed the leaking MNSA and repaired the nozzle with Inconel 690 material. In addition, the two remaining MNSAs at Unit 3 were removed and the nozzles replaced with Inconel 690 material.
There are no MNSAs currently in use at San Onofre Unit 2 or Unit 3.
The safety significance of this event is minimal. |
---|
LER-2006-003, Reactor Coolant System Pressure Boundary Leak Caused by Incomplete Compression of a Mechanical Nozzle Seal Assembly Grafoil Seal.Docket Number |
Event date: |
03-29-2006 |
---|
Report date: |
05-26-2006 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
---|
3622006003R00 - NRC Website |
|
Discovery Date: March 29, 2006 Reactor Vendor: Combustion Engineering Mode: Mode 4 — Hot Shutdown Power: 0 percent
Background
Primary water stress corrosion cracking (PWSCC) of Alloy 600 causes nozzles [NZL] installed in Reactor Coolant System (RCS) [AB] piping and the pressurizer [PZR] to develop cracks. At SONGS, in some cases, cracking also resulted in very minor RCS leakage (reported to the NRC in LERs 3-1986-003, 2-1992-004, 3-1995-001, 3-1996-004, 3-1997-001, and 2-1997-004).
Southern California Edison (SCE) used Mechanical Nozzle Seal Assemblies (MNSAs) to address PWSCC at six locations in Unit 2 and three locations in Unit 3. Some of these were installed as a preventive measure even though the nozzles had no indication of leakage.
MNSAs were designed to provide an external seal for instrument nozzles and to prevent a nozzle from ejecting in the event of nozzle failure. A MNSA compresses a grafoil seal against the exterior of the vessel parent material and is held in place by four or six bolts threaded into shallow holes drilled into the vessel parent material around the subject nozzle (see attached diagram of a MNSA).
This essentially moves the pressure boundary from the original nozzle weld to the grafoil seal.
As of March 2006, SCE had removed all Unit 2 MNSAs and replaced the nozzles with Inconel 690 MNSAs and replace the nozzles during the upcoming Unit 3 Cycle 14 refueling outage (4Q 2006).
In Modes 1, 2, 3, and 4, Technical Specification (TS) 3.4.13 prohibits any pressure boundary leakage from the Reactor Coolant System (RCS). If pressure boundary leakage exists, SCE is required to place the Unit in Mode 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The TS basis includes leakage past a MNSA as RCS pressure boundary leakage.
Description of Event:
On March 29, 2006, SCE initiated a controlled shutdown of Unit 3 (see LER 3-2006-002). At approximately 1450 PDT on March 29, 2006, with Unit 3 in Mode 4, as part of the normal visual inspection for RCS leakage inside containment, SCE identified boric acid crystals on the MNSA seal installed on the Unit 3 pressurizer Resistance Temperature Detector (RTD) mechanical nozzle (3TE-0101). (This MNSA had been installed in March 1998 as a preventive measure as the nozzle had no indication of leakage at that time). Subsequently SCE inspected and removed the MNSA and confirmed RCS leakage past the MNSA seal. SCE repaired the nozzle by replacing it with Inconel 690 material ("half nozzle" repair technique).
SCE found no evidence of boric acid when this MNSA was last inspected on May 5, 2005. Based on radionuclide analysis, SCE determined that the nozzle began leaking approximately one year ago, and concluded that the MNSA began leaking some time after May 5, 2005 (and during Cycle 13 operation). Consequently, SCE is reporting this occurrence in accordance with 10CFR50.73(a)(2)(i)(B) as a condition prohibited by Technical Specifications.
Cause of Event
The boric acid crystals on the exterior of the MNSA indicate that both the nozzle and the MNSA leaked.
SCE believes the pressurizer nozzle leak was caused by PWSCC. SCE performed eddy current examination of the pressurizer RTD nozzle and detected three axially oriented indications on the inside diameter approximately 13.5 inches inside the tube. The approximate length of the indications ranged from 0.25 to 0.50 inch. These results are indicative of PWSCC.
SCE concluded the MNSA seal leak was caused by incomplete compression of the grafoil seal when it was installed (March 1998). The incomplete compression was most likely due to the bolts not reaching a depth that would have compressed the seal to the designed values. This could have resulted from (1) the threaded holes not being machined deep enough, and/or (2) insufficient thread lubrication causing the bolts to indicate the required torque values prior to fully compressing the seal. SCE confirmed the MNSA was installed in accordance with the vendor's procedure; however, the procedure did not require verification of seal compression by direct measurement when this MNSA was installed.
In November 2000, SCE became aware that another nuclear plant experienced a MNSA that was installed in a "cocked" position. In response that event, the vendor improved their MNSA installation procedure to include a requirement to measure the gap between the lower flange and the vessel surface to verify seal compression (in addition to other procedure changes). SCE was aware of the procedure change and the new requirement to verify seal compression for MNSAs installed after the procedure revision date. SCE reviewed all SONGS MNSAs and concluded that only MNSA 3TE-0101 was vulnerable to cocking. In January 2001, SCE inspected 3TE-0101 and determined it was not cocked, but did not also verify MNSA seal compression. SCE now views this as a missed opportunity to correct this condition.
Corrective Actions
SCE performed the following corrective actions:
1. SCE removed the MNSA seal on the Unit 3 pressurizer RTD nozzle after performing inspections in an effort to determine the cause of the failed seal.
2. SCE examined the Unit 3 pressurizer RTD nozzle and repaired it with Inconel 690 material ("half nozzle" repair technique).
3. SCE removed the two remaining MNSA seals at SONGS Unit 3. Inspection of the seals indicated they had been installed with adequate compression of the grafoil seal. In addition, no indication of leakage was observed at the associated nozzles and eddy current examinations revealed no detectable indications of flaws. Nevertheless, SCE replaced the nozzles with Inconel 690 material ("half nozzle" repair technique).
Safety Significance
The safety significance of this event is minimal. MNSAs are designed and maintain the ability to prevent ejection of a nozzle even if a complete circumferential crack were to occur. They also are intended to provide a seal at the surface of the parent material to prevent leakage should a crack in the nozzle propagate throughwall. In this case, the MNSA remained capable of performing its safety function of preventing nozzle ejection even though it did not provide a leak tight seal. SCE's RCS visual inspection program also provided identification of this nozzle leak.
Finally, the consequences of a postulated nozzle ejection would be bounded by the existing small break Loss of Coolant Accident evaluation in Chapter 15 of the Updated Final Safety Analysis Report for San Onofre Units 2 and 3.
Additional Information
Previous occurrences: SCE has not previously reported a failure of a MNSA to prevent leakage. As discussed above, SCE previously reported instances of RCS pressure boundary leaks at SONGS due to PWSCC (LERs 3-1986-003, 2-1992-004, 3-1995-001, 3-1996-004, 3-1997-001, and 2-1997-004).
Side Pressurizer RTD Mechanical Nozzle Seal Assembly (for illustrative purposes only) � Pressurizer Vessel Lower Flange RTD Nozzle Compression Collar Seal Retainer 1.00 Max Bolt (13.00') Top Plate (Anti-Ejection Collar) Grafoil Seal
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|