Title | Acceptance Criterion for UHS Temperature Did Not Consider Instrument Uncertainty |
Description | The team identified a Green non-cited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to include an appropriate acceptance criterion for ultimate heat sink (UHS) temperature in surveillance procedures. Specifically, the acceptance criterion did not account for instrument uncertainty. The licensee entered the issue into their corrective action program as condition report 810638. As an immediate corrective action, the licensee established an action tracking item for control room operators to declare UHS inoperable if indicated temperature exceeded 90 degrees Fahrenheit. In addition, the licensee performed a historic review and did not find an example where the technical specifications (TS) temperature limit of 95 degrees Fahrenheit was exceeded. The team determined the failure to include appropriate acceptance criterion for UHS temperature in surveillance procedures was a performance deficiency. The performance deficiency was determined to be more than minor because it was associated with the Mitigating Systems cornerstone attribute of Equipment Performance and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of the UHS system to respond to initiating events to prevent undesirable consequences. Specifically, the failure to account for UHS temperature instrument uncertainty was significant enough to require revision of the associated surveillance procedures to ensure the validity of heat exchanger performance calculations and compliance with TS limits. The team determined the finding was of very low safety significance (Green) because it was not a design deficiency resulting in the loss of functionality or operability. The team did not identify a cross-cutting aspect associated with this finding because it is not indicative of present licensee performance. |
Site: | Farley ![]() |
---|---|
Report | IR 05000348/2014007 Section 1R21 |
Date counted | Jun 30, 2014 (2014Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.21 |
Inspectors (proximate) | D Mas E Stamm G Macdonald M Yeminy N Feliz Adorno R Nease S Kobylarz T Lighty |
Violation of: | 10 CFR 50 Appendix B Criterion V Technical Specification Technical Specification - Procedures |
INPO aspect | |
' | |
Finding - Farley - IR 05000348/2014007 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Farley) @ 2014Q2