UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 March 21, 2014 Ms. C. Vice President Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312 SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT - NRC TEMPORARY INSTRUCTION 2515/186 INSPECTION REPORT - 05000348/2014405 AND 5000364/2014405

Dear Ms. Gayheart:

On March 6, the U.S. the Nuclear Regulatory Commission (NRC) completed an inspection at your Joseph M. Farley Plant using Temporary Instruction 2515/186, Inspection of Procedures and Processes for Responding to Potential Aircraft Threats. On March 6, the NRC inspector discussed the results of this inspection with you and other members of your staff. The inspector documented the results of this inspection in the enclosed inspection report.

The objective of this inspection was to assess the implementation procedures and processes of the Joseph M. Farley Plant that are required by Title 10 of the Code of Federal Regulations (CFR), Part 50.54(hh)(1), which provides the requirements for responding to a potential aircraft threat. The results from this inspection, along with the results from this inspection performed at other operating commercial nuclear plants in the United States, will be used to evaluate the U.S.

nuclear industrys readiness to safely respond to similar events. These results will also help the NRC to determine if additional regulatory actions are warranted.

No NRC-identified or self-revealing findings were identified during this inspection. However, the inspector documented one licensee-identified violation, which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement, U.S.

Enclosure transmitted herewith contains SUNSI. When separated from enclosure the transmittal document is decontrolled. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Joseph M. Farley Plant.

In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Security-Related Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1).

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

Sincerely,

/RA/

Eugene F. Guthrie, Chief Operations Branch 2 Division of Reactor Safety Docket No. 50-348, 50-364 License No. NPF-2 and NPF-8 Enclosure: Inspection Report 05000348/2014405 and 05000364/2014405, w/Attachment: Supplemental Information (Official Use Only)

cc: (See page 3) _ML14084A583__ ___ X SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRS RII:DRP RII:DRS RII;DRS SIGNATURE DRL2 FJE BBD GXG NAME DLANYI FEHRHARDT BDESAI EGUTHRIE DATE 3/18 /2014 3/18 /2014 3/18 /2014 3/ 21 /2014 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO C Gayheart 3 cc:

Lyle Brian Askren, Security (Site) Mgr.-

Nuclear Southern Nuclear Operating Company, Inc.

Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312 Stephen P. McGavin, Fleet Security Director Southern Nuclear Operating Co., Inc.

40 Inverness Center Parkway, Bin B042 Birmingham, AL 35242 David P. Burford, Fleet Cyber Security Manager Southern Nuclear Operating Co., Inc.

40 Inverness Center Parkway Bin B-042 Birmingham, AL 35242 Ms. Lisa B. Hogg Southern Nuclear Operating Co., Inc.

40 Inverness Center Parkway Birmingham, AL 35242 Letter to Cheryl from Eugene F. Guthrie dated March 21, 2014.

SUBJECT: JOSEPH M. FARLEY NUCLEAR PLANT - NRC TEMPORARY INSTRUCTION 2515/186 INSPECTION REPORT 05000348/2014405 AND 05000364/2014405 (Official Use Only)

Distribution:

RidsNrrPMJMFarley Resource C. Evans, RII EICS L. Douglas, RII EICS RIDSNRRDIRS PUBLIC S. Coker, NSIR/DSO/DDSO/ST T. Dimitriadis, RI R. Albert, NSIR B. Desai, RII B. Huffman, NSIR/DPR/DDIR/OB D. Funk, RIII J. Kozal, NSIR/DPR/DDIR/CB M. Haire, RIV E. Bowman, NRR/DPR/PGCB [Any required agreement state distribution]