08-22-2016 | An automatic turbine trip occurred resulting in an automatic Reactor Protective System ( RPS) actuation from mode 1 at 100% power due to loss of turbine load at 0841 Central Daylight Time on June 22, 2016. System actuation and responses were as designed. There were no Safety Systems inoperable that contributed to this event. The trip occurred during Post Modification Testing activities on the turbine Emergency Trip System ( ETS) pressure loop trip. Engineering failed to identify and disable the transmitter deviation based trip. The differences between the substituted input values selected for testing and the output of the signal selector block were sufficient to trigger the two transmitters-in-deviation trip for the ETS loop. |
---|
LER-2016-003, Unplanned Turbine Trip during DCS Modification due to Failure to Identify and Disable the Transmitter Deviation Based TripFort Calhoun Station |
Event date: |
06-22-2016 |
---|
Report date: |
08-22-2016 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(iv)(A), System Actuation |
---|
2852016003R00 - NRC Website |
|
|
---|
Category:Letter
MONTHYEARLIC-24-0012, Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information2024-10-0707 October 2024 Independent Spent Fuel Storage Installation - Response to Proposed Revision to Decommissioning Quality Assurance Plan (DQAP) - Request for Additional Information LIC-24-0011, Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-00952024-10-0202 October 2024 Independent Spent Fuel Storage Installation - Response to Application for License Amendment Request to Revise the License Termination Plan - Supplemental Information Needed, EPID L-2024-LLA-0095 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24255A0962024-09-12012 September 2024 License Amendment Request to Revise the License Termination Plan - Request Supplemental Information (License No. DPR-40, Docket No. 50-285) ML24243A1042024-09-12012 September 2024 Proposed Revision to the OPPD FCS DQAP - Request for Additional Information (License No. DPR-40, Docket Nos. 50-285, 72-054, and 71-0256) IR 05000285/20240022024-08-21021 August 2024 NRC Inspection Report 05000285/2024002 ML24235A0822024-08-10010 August 2024 Response to Fort Calhoun Station, Unit No. 1 - Phase 1 Final Status Survey Report to Support Approved License Termination Plan - Request for Additional Information - Request for Additional Information (EPID L-2024-DFR-0002) July 8, 2024 ML24180A2082024-07-0808 July 2024 Phase 1 Final Status Survey Reports Request for Additional Information Letter ML24183A3222024-07-0808 July 2024 Proposed Revision to the Omaha Public Power District Fort Calhoun Station Decommissioning Quality Assurance Plan - Acceptance Review LIC-24-0007, License Amendment Request (LAR) to Revise License Termination Plan (LTP)2024-06-18018 June 2024 License Amendment Request (LAR) to Revise License Termination Plan (LTP) IR 05000285/20240012024-06-0505 June 2024 NRC Inspection Report 05000285/2024001 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities LIC-24-0008, Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI2024-05-16016 May 2024 Proposed Revision to the Omaha Public Power District (OPPD) Fort Calhoun Station (FCS) Decommissioning Quality Assurance Plan (Dqap), Unit No. 1 and ISFSI LIC-24-0003, Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report2024-04-25025 April 2024 Independent Spent Fuel Storage Installation - Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-24-0006, (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan2024-04-17017 April 2024 (Fcs), Unit 1, Independent Spent Fuel Storage Installation, Phase 1 Final Status Survey Report to Support Approved License Termination Plan ML24079A1702024-03-10010 March 2024 ISFSI, Unit 1 - 10 CFR 50.59 Report, Quality Assurance (QA) Program Changes, Technical Specification Basis Changes, 10 CFR 71.106 Quality Assurance Program Approval, Aging Management Review, Commitment Revisions and Revision of Updated Safe LIC-24-0005, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2024-03-0101 March 2024 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-24-0002, Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report2024-02-27027 February 2024 Independent Spent Fuel Storage Installation - Submittal of Annual Radioactive Effluent Release Report ML24019A1672024-01-31031 January 2024 Issuance of Amendment to Renewed Facility License to Add License Condition to Include License Termination Plan Requirements IR 05000285/20230062023-12-21021 December 2023 NRC Inspection Report 05000285/2023006 LIC-23-0007, Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information2023-12-0606 December 2023 Response to Fort Calhoun, Unit 1 & Independent Spent Fuel Storage Installation Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Request for Additional Information IR 05000285/20230052023-11-0202 November 2023 NRC Inspection Room 05000285/2023005 ML23276A0042023-09-28028 September 2023 U.S. EPA Response Letter to NRC Letter on Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites MOU - Fort Calhoun Station, Unit 1 (License No. DPR-40, Docket No. 50-285) IR 05000285/20230042023-09-13013 September 2023 NRC Inspection Report 05000285/2023-004 LIC-23-0005, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 20232023-08-24024 August 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 ML23234A2392023-08-18018 August 2023 Letter to B Harisis Re Ft Calhoun Unit 1 LTP EA State of Nebraska Comment Request.Pdf ML23234A2412023-08-18018 August 2023 Email - Letter to M Porath Re Ft Calhoun Unit 1 LTP EA Section 7 Informal Consultation Request IR 05000285/20230032023-07-10010 July 2023 NRC Inspection Report 05000285/2023003 ML23082A2202023-06-26026 June 2023 Consultation on the Decommissioning of the Fort Calhoun Station Unit 1 Pressurized Water Reactor in Fort Calhoun, Nebraska IR 05000285/20230022023-06-0505 June 2023 NRC Inspection Report 05000285/2023002 ML23151A0032023-06-0505 June 2023 Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements 2nd Request for Additional Information (EPID L-2021-LIT-0000) June 2, 2023 LIC-23-0004, (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report2023-04-20020 April 2023 (FCS) Radiological Effluent Release Report and Radiological Environmental Operating Report LIC-23-0003, Annual Decommissioning Funding / Irradiated Fuel Management Status Report2023-03-15015 March 2023 Annual Decommissioning Funding / Irradiated Fuel Management Status Report LIC-23-0001, Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information2023-02-27027 February 2023 Response to Fort Calhoun Station, Unit No. 1 - Review of License Amendment Request to Add License Condition to Include License Termination Plan Requirements - Request for Additional Information ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000285/20230012023-02-24024 February 2023 NRC Inspection Report 05000285/2023001 LIC-23-0002, Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report2023-02-20020 February 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML23020A0462023-01-19019 January 2023 Threatened and Endangered Species List: Nebraska Ecological Services Field Office IR 05000285/20220062023-01-0505 January 2023 NRC Inspection Report 05000285/2022-006 ML22357A0662022-12-30030 December 2022 Technical RAI Submittal Letter on License Amendment Request for Approval of License Termination Plan IR 05000285/20220052022-10-26026 October 2022 NRC Inspection Report 05000285/2022-005 ML22276A1052022-09-30030 September 2022 Conclusion of Consultation Under Section 106 NHPA for Ft. Calhoun Station LTP ML22258A2732022-09-29029 September 2022 Letter to John Swigart, Shpo; Re., Conclusion of Consultation Under Section 106 Hnpa Fort Calhoun Station Unit 1 ML22265A0262022-09-26026 September 2022 U.S. Nuclear Regulatory Commission'S Analysis of Omaha Public Power District'S Decommissioning Status Report (License No. DPR-40, Docket No. 50-285) IR 05000285/20220042022-09-14014 September 2022 NRC Inspection Report 05000285/2022004 ML22138A1222022-08-0303 August 2022 Letter to Mr. John Shotton, Chairman, Otoe-Missouria Tribe of Indians, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1302022-08-0303 August 2022 Letter to Justin Wood, Principal Chief, Sac and Fox Nation, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22138A1242022-08-0303 August 2022 Letter to Mr. Reggie Wassana, Governor, Cheyenne and Arapaho Tribes, Oklahoma, Re., Ft Calhoun LTP Section 106 ML22101A1092022-08-0303 August 2022 Letter to Mr. Durell Cooper, Chairman, Apache Tribe of Oklahoma; Re., Ft Calhoun LTP Section 106 ML22138A1212022-08-0303 August 2022 Letter to Mr. Edgar Kent, Chairman, Iowa Tribe of Oklahoma, Re., Ft Calhoun LTP Section 106 2024-09-18
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000285/LER-2017-0012017-05-11011 May 2017 Unprotected Vital Area Barrier Due to Maintenance, LER 17-001-00 for Fort Calhoun Station, Unit 1, Regarding Unprotected Vital Area Barrier Due to Maintenance 05000285/LER-2016-0032016-08-22022 August 2016 Unplanned Turbine Trip during DCS Modification due to Failure to Identify and Disable the Transmitter Deviation Based Trip, LER 16-003-00 for Fort Calhoun, Unit 1, Regarding Unplanned Turbine Trip During DCS Modification Due to Failure to Identify and Disable the Transmitter Deviation Based Trip 05000285/LER-2016-0022016-07-0707 July 2016 Unanalyzed Condition Shutdown Heat Exchanger Isolations ti, LER 16-002-00 for Fort Calhoun, Unit 1, Regarding Unanalyzed Condition Shutdown Heat Exchanger Isolations 05000285/LER-2016-0012016-04-0808 April 2016 Technical Specification Violation due to Installation of an Unqualified Part in a Radiation Monitor, LER 16-001-00 for Fort Calhoun, Unit 1 Regarding Technical Specification Violation due to Installation of an Unqualified Part in a Radiation Monitor LIC-10-0054, Cancellation of Licensee Event Report 2009-003 for the Fort Calhoun Station2010-08-0404 August 2010 Cancellation of Licensee Event Report 2009-003 for the Fort Calhoun Station LIC-10-0052, Special Report on Inoperability of Main Steam Line Radiation Monitor RM-064 for Post Accident Monitoring2010-07-12012 July 2010 Special Report on Inoperability of Main Steam Line Radiation Monitor RM-064 for Post Accident Monitoring LIC-04-0105, LER 04-S01-00 for the Fort Calhoun Station Regarding Inadequate Security Compensatory Measures for a Security Zone2004-10-14014 October 2004 LER 04-S01-00 for the Fort Calhoun Station Regarding Inadequate Security Compensatory Measures for a Security Zone LIC-04-0002, LER 03-S02-00 for Fort Calhoun, Unit 1 Regarding Lack of Proper Compensation for a Security Zone2004-01-0808 January 2004 LER 03-S02-00 for Fort Calhoun, Unit 1 Regarding Lack of Proper Compensation for a Security Zone ML0330304982003-10-23023 October 2003 LER 03-S01-00 for Fort Calhoun Station Regarding Safeguard System Vulnerability Due to Inadequate Securing of a Security Door LIC-02-0115, LER 02-S01-00 for Fort Calhoun Unit 1 Regarding Possible Error in Classification of Safeguards Material on September 6, 20022002-10-0404 October 2002 LER 02-S01-00 for Fort Calhoun Unit 1 Regarding Possible Error in Classification of Safeguards Material on September 6, 2002 2017-05-11
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Fort Calhoun Station 05000-285
3. LER NUMBER
2016 - 00 003
BACKGROUND
Fort Calhoun Station (FCS) is a two-loop reactor coolant system (RCS) of Combustion Engineering design. Fort Calhoun Station replaced the original General Electric (GE) Mark I turbine control system with a Foxboro digital Turbine Control System (TCS) per engineering change (EC) 32387 in April 2011. The system was placed into service in December 2013. The turbine trip logic loops use 2 out of 3 (2003) trip logic. The trip logic reduces to 1 out of 2 (1002) logic when a loop transmitter fails or is bypassed. This creates a single point vulnerability (SPV) should a transmitter failure be undetected by the digital control system (DCS) while providing a false trip signal. This design was specifically included in the replacement of the TCS.
DESCRIPTION
A FCS trend of Rosemount transmitter failures recently caused engineering to reduce potential single point plant trip vulnerabilities by implementing a new modification for the TCS logic. The purpose of the modification was to eliminate the potential SPVs identified in multiple loops by changing the configuration of the signal selector block to provide 2 out of 2 (2oo2) trip logic when a transmitter is failed or bypassed and 2oo3 trip logic when all 3 inputs are available.
A work order (WO) implementing the EC was prepared and approved covering the configuration change and Post Modification Testing (PMT). The PMT was integrated into the work instructions, therefore no secondary PMT task was added to the electronic tracking, review and approval software. A Duty Manager Challenge, per WC-AA-2000 "Emergent Issue Response", was requested and performed by the Station Duty Manager for the activity. Engineering was performing a modification to the DCS to multiple turbine trip loops when the event occurred. Two loops involving lube oil pressure trip logic were successfully modified and tested under the WO just prior to the event.
An automatic turbine trip occurred resulting in an automatic Reactor Protective System (RPS) actuation due to loss of turbine load at 0841 Central Daylight Time (CDT) on June 22, 2016. The Headquarter Operations Officer (H00) was informed of the event per 10 CFR 50.72(b)(2)(iv)(B) (RPS Actuation) and 50.72(b)(3)(iv)(A) (Specified System Actuation (RPS)). This report is being submitted pursuant to 10 CFR 50.73(a)(2)(iv)(A), Specified System Actuation (RPS). The event was entered into the Corrective Action Program as CR 2016-05505. The trip occurred during Post Modification Testing activities on the turbine ETS pressure loop trip logic (third loop to be modified under the WO). There are two trip logic paths typically associated with the turbine trips: the first is the process level (e.g. low ETS pressure) with the second trip based on a deviation of 2 transmitters (2 in Deviation) from the median signal of the triplicated inputs processed by the signal selector block. Engineering failed to identify and disable the transmitter deviation based trip.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
I 05000-285 2016 - 003 Fort Calhoun Station - 00 The differences between the substituted input values selected for testing and the output of the signal selector block were sufficient to trigger the two transmitter deviation trip for the ETS loop.
CONCLUSIONS
Direct Cause(s):
1. Failure to identify the need to place block P3325_X2, Emergency Trip System Pressure 2-in- deviation input, in manual prior to PMT.
2. The values selected for the transmitter manual input during PMT placed the loop logic in a 2 in deviation condition which satisfied turbine trip logic through block P3325_X2.
The PMT for this modification was created by System Engineering following the completion of the Design Change Package (DCP). The DCP had installation instructions that identified placing the process trip block in manual but failed to recognize a second trip path existed. This information was not validated by the System Engineer while creating the work package and PMT.
Root Cause:
1. The Shift Management failed to set and to enforce standards related to the emergent work process.
The root cause was determined based on the organizational weakness that has been identified with the maintenance, implementation, and challenge of the emergent work process at FCS. It was identified that the overall standards associated with challenges to risk significant work within the station were below expectations.
Corrective Actions:
The basis for the corrective actions is to align the station on how to successfully implement the emergent work process at FCS. This includes the standards and expectations associated with the B-lists and risk determinations for items determined to be emergent. Direct and contributing causes were resolved through the use of setting expectations in the System Engineering department on technical products, station personnel training, and benchmarking fleet best practices.
FCS reviewed other work packages written or ghost written by System Engineering for same or similar errors, eliminated additional work on DCS components, and challenged the emergent work list to ensure bases and conditions were vetted with the correct amount of rigor to ensure similar events would not take place.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Fort Calhoun Station 05000-285
3. LER NUMBER
2016 - 00 003
SAFETY CONSEQUENCES
PMT on DCS caused a turbine trip protecting the main generator as designed. Plant safety systems shutdown the reactor plant and support systems operated as designed. The plant trip is considered uncomplicated.
SAFETY SYSTEM FUNCTIONAL FAILURE
This does not represent a safety system functional failure in accordance with NEI 99-02, revision 7.
PREVIOUS EVENTS
process to prevent the plant trip.
|
---|
|
|
| | Reporting criterion |
---|
05000285/LER-2016-001 | Technical Specification Violation due to Installation of an Unqualified Part in a Radiation Monitor LER 16-001-00 for Fort Calhoun, Unit 1 Regarding Technical Specification Violation due to Installation of an Unqualified Part in a Radiation Monitor | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2016-002 | Unanalyzed Condition Shutdown Heat Exchanger Isolations ti LER 16-002-00 for Fort Calhoun, Unit 1, Regarding Unanalyzed Condition Shutdown Heat Exchanger Isolations | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000285/LER-2016-003 | Unplanned Turbine Trip during DCS Modification due to Failure to Identify and Disable the Transmitter Deviation Based Trip LER 16-003-00 for Fort Calhoun, Unit 1, Regarding Unplanned Turbine Trip During DCS Modification Due to Failure to Identify and Disable the Transmitter Deviation Based Trip | 10 CFR 50.73(a)(2)(iv)(A), System Actuation |
|