Finding | |
---|---|
Title | Failure to Adequately Account for Raw Water Pump Discharge Check Valve Back Leakage |
Description | The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, which states, in part, that design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program. Specifically, prior to March 13, 2015, the licensee did not properly verify the adequacy of the raw water system flow rate to its safety related components through calculational methods or through a suitable testing program. The licensee failed to include the raw water pumps discharge check valves allowable back leakage acceptance criteria into the design calculation. In response to this issue, the licensee performed an operability determination and verified that with the current back leakage flow rates all downstream safety related loads would be properly cooled. This finding was entered into the licensees corrective action program as Condition Reports CR 2015-01801, and CR 2015-01835. The team determined that the failure to verify the adequacy of the raw water system design through calculational methods or through a suitable test program was a performance deficiency. This finding was more than minor because it was associated with the design control attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the reliability, availability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee failed to have adequate measures in place to ensure that a suitable test program verified design inputs which ensured the design attributes of the raw water system. In accordance with Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, dated June 19, 2012, Exhibit 2, Mitigating Systems Screening Questions, the issue screened as having very low safety significance (Green) because it was a design or qualification deficiency that did not represent a loss of operability or functionality; did not represent an actual loss of safety function of the system or train; did not result in the loss of one or more trains of non-technical specification equipment; and did not screen as potentially risk significant due to seismic, flooding, or severe weather. The team determined that this finding did not have a crosscutting aspect because the most significant contributor did not reflect current licensee performance, |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2015007 Section 1R21 |
Date counted | Mar 31, 2015 (2015Q1) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.21 |
Inspectors (proximate) | B Correll C Smith G Gardner J Bozga J Braisted J Dixon M Yeminy T Farnholtz |
Violation of: | 10 CFR 50 Appendix B Criterion III, Design Control |
INPO aspect | |
' | |