05000275/FIN-2018008-01
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Emergency Diesel Generator Mission Time for Operability Evaluations |
Description | The team identified an unresolved item (URI) related to diesel generator (DG) mission time for operability evaluations. On December 3, 2016, an operator discovered during rounds that the air inlet boot seal on DG 1-2 had degraded, and subsequently, an inspection of the other diesel generators (DGs) revealed that the DG 2-2 boot seal was also degraded. The licensee performed an operability evaluation and concluded that the DGs were operable based on a mission time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. The licensee then performed a past operability evaluation, concluding that the DGs had remained able to perform their safety function for this stated 24-hour mission time despite the deficiency; therefore no licensee event report was required by 10 CFR 50.73. The team requested information related to the basis of the 24-hour mission time. The licensee provided a non-controlled reference document, Engineered Safety Feature (ESF) Equipment Mission Time, to the licensees operability determination Procedure OM7.ID12. The document listed the mission time for the DGs as 7 days (24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />). The 6 and 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> values depend on the particular accident sequence and electrical power recovery time, and were from a letter sent to the NRC related to the licensees Individual Plant Examination of External Events (IPEEE), which is a plant-specific probabilistic risk assessment (PRA). The 7-day value is related to the required diesel fuel oil storage volume as discussed in Technical Specification Bases 3.8.3. The document also states that the licensee has no defined post-accident operation / mission times because such times are not mandated by regulation or recommended by NRC guidance. The team noted, however, that IPEEEs do not typically evaluate accidents past 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and furthermore, IMC 0326, Operability Determinations and Functionality, states that the use of PRA or probabilities of occurrence of accidents or external events is not consistent with the assumption that the event occurs, and is not acceptable for making operability decisions. Additionally, Procedure OM7.ID12 defines mission time as the duration of structure, system, or component (SSC) operation that is credited in the current licensing bases for the SSC to perform its specified safety function; however, as documented above by the licensee, there is no design or licensing basis mission time for the DGs. The licensees definition of mission time is essentially the same as described in IMC 0326. The inspectors performed a brief review of documents related to mission times. Technical Specification Limiting Condition for Operation 3.8.3, Diesel Fuel Oil, Lube Oil, Starting Air, and Turbocharger Air Assist, requires verification of diesel fuel oil level to satisfy a 7-day fuel oil storage requirement. Additionally, NUREG-1407 discusses an Electric Power Research Institute approach that defines and evaluates the capacity of those components required to bring the plant to a stable condition (either hot or cold shutdown), and maintain that condition for at least 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Also, the ESF equipment mission time document referenced several 30-day mission times for SSCs that would require emergency power from either offsite power, if available, or the DGs. The team also performed a search of previous NRC findings at the DCPP, Unit 1 and 2, and found one reference to a 7-day mission time for the DGs in NRC Pilot Engineering Inspection Report 2006005. The inspectors also reviewed NEI 97-04, Design Bases Program Guidelines, Revised Appendix B, Guidance and Examples for Identifying 10 CFR 50.2 Design Bases. The Appendix describes how the 10 CFR 50.2 design bases of a facility are a subset of the current licensing basis and are required pursuant to 10 CFR 50.34(a)(3)(ii) and (b) and 10 CFR 50.71(e), to be included in the updated Final Safety Analysis Report (FSAR). Title 10 CFR 50.2 design bases consist of design bases functions and design bases values. Design bases values are the values or ranges of values of controlling parameters established as reference bounds for design to meet design bases functional requirements. In other words, the 10 CFR 50.2 design bases include the bounding conditions under which SSCs must perform their design bases functions and may be derived from normal operation, or any accident or events for which SSCs are required to function. Because 10 CFR 50.71(e), IMC 0326, and Procedure OM7ID.12 indicated that DG mission time should be part of the design and licensing bases, and documented in the FSAR, but a DG mission time design and licensing basis does not appear to exist at DCPP, Units 1 and 2, the inspectors could not determine that an appropriate mission time was used for a past operability determination. Therefore, the team could not conclude that the licensee had not missed a 10 CFR 50.73 event report because of a potentially incorrect assumption about DG mission time. This is applicable to both units. Planned Closure Action(s): In order to resolve this issue, the NRC needs to determine whether or not the basis for the 24-hour DG mission time is appropriate by determining which standard or standards apply to mission time at DCPP, Units 1 and 2. Licensee Action(s): Because the licensees position is that the DG mission time is not a part of their current licensing or design basis, they maintain that the 24-hour mission time used in the past operability determination was adequate to provide reasonable assurance of operability and, therefore, no event report was required. However, prior to this inspection and because of other uncertainties in determining mission times, the licensee generated Notification 50832335 to reassess the mission times associated with the ESF equipment. The intent is to develop the bases for ESF equipment mission time in a controlled document. However, this effort is not yet complete and, as such, the mission time for the DGs has not been evaluated under this notification. Corrective Action Reference(s): Notifications 50832335, 50882125, 50882140, and 50882498. |
Site: | Diablo Canyon |
---|---|
Report | IR 05000275/2018008 Section 4OA2 |
Date counted | Jun 30, 2018 (2018Q2) |
Type: | URI: |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | E Ruesch J Braisted N Okonkwo J Reynoso G George |
INPO aspect | |
' | |
Finding - Diablo Canyon - IR 05000275/2018008 | |||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Diablo Canyon) @ 2018Q2
Self-Identified List (Diablo Canyon)
| |||||||||||||||||||||||||||||||||||||||||||||||