05000266/FIN-2013003-02
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Failure to Follow Operability Evaluation Process Following Water Leakage into the Control Room |
| Description | The inspectors identified a finding of very low safety significance and an associated non-cited violation of 10 CFR 50, Appendix B, Criterion V for the licensees failure to follow procedure EN-AA-203-1001, Operability Determinations/Functionality Assessments. Specifically, following water leakage into the control room, the licensees immediate operability determination failed to evaluate the effect the leakage had on the control room envelope operability. Additionally, the licensee did not address the functionality of the degraded flood barrier and its impact on operability. This issue was entered into the CAP as AR01877185. Corrective actions for this issue included performing a test of the control room envelope to demonstrate that appropriate positive pressure could be maintained with the known degraded barrier, and repair of the degraded flood barrier following performance of a functionality assessment. The inspectors determined the finding to be more than minor in accordance with IMC 0612, Appendix B, because it was associated with the Protection Against External Factors attribute of the Initiating Event Cornerstone, and adversely affected the Cornerstone objective of limiting the likelihood of events that upset plant stability and challenge critical safety functions during power operations. The inspectors determined the finding to be of very low safety significance in accordance with IMC 0609, Appendix A, Exhibit 1, because they answered No to the questions under Transient Initiators and External Event Initiators. The inspectors concluded that this finding has a cross-cutting aspect in the area of problem identification and resolution, corrective action program, because the licensee failed to thoroughly evaluate this problem such that the resolution addressed the cause and evaluated the condition for operability (P.1(c)). |
| Site: | Point Beach |
|---|---|
| Report | IR 05000266/2013003 Section 1R06 |
| Date counted | Jun 30, 2013 (2013Q2) |
| Type: | NCV: Green |
| cornerstone | Initiating Events |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.06 |
| Inspectors (proximate) | M Holmberg P Pelke S Burton J Laughlin D Betancourt K Barclay J Gilliam M Thorpe-Kavanaugh J Beavers E Sanchez V Myers J Steffes |
| Violation of: | 10 CFR 50 Appendix B Criterion V |
| CCA | P.2, Evaluation |
| INPO aspect | PI.2 |
| ' | |
Finding - Point Beach - IR 05000266/2013003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Point Beach) @ 2013Q2
Self-Identified List (Point Beach)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||