MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML23053A2112023-02-0707 February 2023 Owner'S Activity Report ML22216A0712022-06-29029 June 2022 Steam Generator Tube Inspection Report ML21216A2312021-07-15015 July 2021 Owner'S Activity Report ML21043A2502021-01-13013 January 2021 Owner'S Activity Report for Third Period of the Fourth Inspection Interval ML20252A2202020-09-0303 September 2020 Revised License Renewal Commitment Supplement Pressurizer Surge Line Welds Inspection Frequency ML20101H2942020-03-26026 March 2020 Summary of Facility Changes, Tests and Experiments ML20087G3072020-03-19019 March 2020 ASME Section XI Inservice Inspection Program Proposed Inservice Inspection Alternative N1-I5-NDE-003 ML20028D4922020-01-22022 January 2020 Inservice Testing Program Plan for Pumps, Valves, and Snubbers Fifth 10-Year Interval Update for Units 1 and 2; Request for Alternatives to Requirements of ASME OM Code ML19191A0092019-07-0202 July 2019 Owner'S Activity Report ML19179A0752019-06-24024 June 2019 Steam Generator Tube Inspection Report ML18361A6482018-12-20020 December 2018 ASME Section XI Inservice Inspection Program Relief Request N2-I4-LMT-003 - Fourth Interval Period 2 Limited Examinations ML18275A1052018-09-26026 September 2018 ASME Section XI Inservice Inspection Program Request for Proposed Alternative N1-I4-CS-002 Snubber Program Extension ML18255A0612018-09-0404 September 2018 Submittal of Steam Generator Tube Inspection Report ML18198A1152018-07-11011 July 2018 Owner'S Activity Report (Form OAR-1), for Refueling Outage N1R25 ML18033A3372018-01-0404 January 2018 Owner'S Activity Report Refueling Outage N2R25 - Second Period of the Fourth ISI Interval ML17160A2632017-06-0505 June 2017 ASME Section XI Inservice Inspection Program PRA Information to Support Proposed Inservice Inspection Alternatives N1-14-NDE-010 and N2-14-NDE-005 ML17121A0362017-04-24024 April 2017 ASME Section XI Inservice Inspection Program Relief Request N1-I4-LMT-002 - Fourth Interval Period 2 Limited Examinations ML16215A1922016-07-27027 July 2016 ASME Section XI Inservice Inspection Program - Proposed Inservice Inspection Alternative N1-14-NDE-008, Proposed Inservice Inspection Alternative N2-14-NDE-003 ML16202A0662016-07-12012 July 2016 Steam Generator Tube Inspection Report ML15091A6872015-06-25025 June 2015 Relief Request (RR) N2-I4-NDE-002, Inservice Inspection Program ML15069A2272015-03-0202 March 2015 ASME Section XI Inservice Inspection Program Proposed Inservice Inspection Alternative N2-I4-NDE-002 ML14115A0662014-04-21021 April 2014 ASME Section XI Inservice Inspection Program Relief Request N2-I4-LMT-002-Fourth Interval Period 1 Limited Examinations ML14035A0672014-01-14014 January 2014 Steam Generator Tube Inspection Report ML13204A1172013-07-17017 July 2013 ASME Inservice Testing Program for Pumps and Valves Request for Alternative to Requirements of ASME OM Code Request for Alternative G-1 ML13114A2532013-04-22022 April 2013 ASME Section XI Inservice Inspection Program Examination Results and Revised Request for Alternative to ASME Code Steam Generator Nozzle-to-Vessel Weld Examination Requirements, Alternative Request N2-I4-LMT-001-R1 ML13092A1322013-03-18018 March 2013 Summary of Facility Changes, Tests and Experiments ML11270A1222011-09-21021 September 2011 ASME Section Xl Inservice Inspection Program Relief Request N2-I3-PRT-002 - Limited Coverage Examinations Performed in the Third Ten-Year Inspection Interval ML1113805172011-05-17017 May 2011 ASME Section XI Inservice Inspection Program Request for Alternative ASME Code Pressurizer Nozzle-to-Vessel Weld Examination Requirements Relief Request N1-I4-NDE-003-R1 ML1026404402010-09-21021 September 2010 Steam Generator Tube Inspection Report ML1023600412010-08-19019 August 2010 Fourth Interval Inservice Testing Program Plan, Pump Relief Request P-6, Response to Request for Additional Information ML1020101112010-07-19019 July 2010 Submittal of Report on Second Refueling Outage of Third Period of Third Inspection Interval ML0913302362009-05-12012 May 2009 Response to NRC Comments on the Fourth Interval ISI Program ML0828801602008-10-0707 October 2008 Fourth Interval Inservice Inspection Plan and Associated Proposed Alternatives and Relief Requests ML0706601122007-03-0606 March 2007 Containment IWE Inservice Inspection Plan ML0701202682007-01-0909 January 2007 Revised ASME Section XI Inservice Inspection Program Relief Request Partial Examination of Reactor Pressure Vessel Head-to-Flange Welds-CMP-020 R1 ML0618704072006-07-0505 July 2006 Owner'S Activity Reports ML0505300492005-02-21021 February 2005 Annual Steam Generator Tube Inspection Report ML0424406182004-08-23023 August 2004 Virginia Electric and Power Company North Anna Power Station Unit 2 Owner'S Activity Reports ML0421101172004-07-28028 July 2004 Owners Activity Reports ML0409704242004-03-30030 March 2004 ASME Section XI Inservice Inspection Program Request to Use Code Case N-663 as Alternative ML0402906592004-01-22022 January 2004 Unit 1 ASME Section XI Inservice Inspection Program Relief Requests Partial Examination of Reactor Pressure Vessel Head-to-flange Welds ML0306903732003-02-26026 February 2003 Submittal of Annual Steam Generator Inservice Inspection Summary Report Performed During 2002 ML0221906272002-07-30030 July 2002 Virginia Electric and Power Co., (Dominion) North Anna Power Station Unit 2 Final Inservice Inspection Summary Report ML0207106972002-02-28028 February 2002 Annual Steam Generator Inservice Inspection Summary Report ML0201601652002-01-0404 January 2002 Inservice Inspection Report ASME Section XI, Subsection Iwl Concrete Inspections PLA-5343, Part 2 - Susquehanna Steam Electric Station Unit 2 Tenth Inspection Outage ISI Summary Report. Appendix D - ASME Repair and Replacements NIS-2 Forms2001-07-24024 July 2001 Part 2 - Susquehanna Steam Electric Station Unit 2 Tenth Inspection Outage ISI Summary Report. Appendix D - ASME Repair and Replacements NIS-2 Forms ML0036734581999-12-15015 December 1999 Inservice Inspection Summary Report for North Anna Power Station, Unit 2, 1999 Refueling Outage Owner'S Report of Inservice Inspections. 2024-02-01
[Table view] Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] |
Text
VIRGINIA ELECTRIC AND POWER COMPANY
.\ *_*.(* : .
RICHMOND, VIRGINIA 2~261 June 24, 2019 U.S. Nuclear Regulatory Commission Serial No.19-290 Attention: Document Control Desk NAPS/DPM RO Washington, D.C. 20555 Docket No. 50-339 License No. NPF-7 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION UNIT2 STEAM GENERATOR TUBE INSPECTION REPORT Pursuant to Technical Specification 5.6.7 for North Anna Power Station Unit 2, Dominion is required to submit a 180-day steam generator tube inspection report. The attachment to this letter provides the steam generator tube inspection report for the North Anna Unit 2 Spring 2019 outage.
Should you have any questions or require additional information, please contact Mr.
Daniel P. McGinnis at (540) 894-2487.
Very truly yours, N. Larry Lane Site Vice President Attachment Commitments made in this letter: None
cc: U.S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Avenue, NE Suite 1200 Atlanta, Georgia 30303-1257 Mr. G. E. Miller NRC Project Manager - North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 B-1A 11555 Rockville Pike Rockville, Maryland 20852-2738 Ms. K. R. Cotton NRC Project Manager U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Senior Resident Inspector North Anna Power Station 2
. \
ATTACHMENT .
NORTH ANNA UNIT 2 180-DAY NRC REPORT REGARDING STEAM GENERATOR TUBE INSPECTION PER TECHNICAL SPECIFICATION 5.6. 7 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
- l SPRING 2019- NORTH ANNA UNIT 2 STEAMJ3ENERATOR INSPECTIONS The following satisfies the North Anna Power Station Technical Specification (TS) reporting requirement section 5.6.7. During the North Anna Unit 2, spring 2019 refueling outage, steam generator (SG) inspections in accordance with TS 5.5.8.d were completed for all three steam generators ("A", "B" and "C").
The Unit 2 Steam Generators have accrued 22.1 Effective Full Power Years (EFPY) of operation as of the end of Cycle 26 (March, 2019).
Initial entry into Mode 4 occurred on April 7, 2019 (0135 Hrs); therefore, this report is required to be submitted by October 4, 2019.
Italicized wording represents TS verbiage. The required information is provided under each reporting requirement as follows:
A report shall be submitted within 180 days after the initial entry into Mode 4 following completion of an inspection performed in accordance
- with the Specification 5. 5. 8, "Steam Generator (SG) Program." The report shall include: **
- a. The scope of inspections performed on each SG The following primary side inspections were performed in each steam generator:
- Visual examination of both channel heads (as..:found / as-left) specifically including:
o all plugs o the divider plate weld region o the bottom of the bowl per NSAL-12-1 and NRC IN 2013-20 with the bowl dry
- 100% full-length inspection utilizing bobbin coil probes for all tubes except for Row 1 U-bends
- 100% Row 1 (98 tubes) U-bend region utilizing rotating coil probe
- 29% of h.ot leg top of tubesheet (+/-3") utilizing rotating coil probe with tube selection including 50% of the secondary side critical area in the sludge zone, 50%
of all tubes within five tubes of the bundle periphery, and other randomly sampled locations
- '17% of cold leg top of tubesheet' (+/-3") utilizing rotating coil probe with tube sample constituting 56% of all tubes within five tubes of the bundle periphery
- Special interest inspections of dents/dings with rotating coil probe (Sample: 100%
of dents/ding ~ 5 Volts) *
- Augmented sample inspections were perfc;>rmed in areas of special interest including hot leg expansion transitions, tube overexpansion locations. Results identified in Table 1 below.
' ,
- I Table 1 - Bobbin Probe Indication / Special Interest Exam Summary KEY: tubes / indications /
SG"A" SG "B" SG "C" indications tested with +Point TSP Wear 0/0/0 5/7/7 4/5/5 Dents ~5 Volts 2/2/2 ,,
2/2/2 1/ 1/ 1 Hot Leg MBH 14 / 14 / 14 18/19/19 11/11/11 Hot Leg OXP 353 / 451 / 36 323 / 445 / 20 503 / 790 / 23
'(.
Cold Leg OXP 149 / 170 / 4 ' 490 /657 / 8 605 / 1002 / 4 OVR 5/5/5 0/0/0 2/2/2 NTE 0/0/0 4/4/4 2/2/2 The following secondary side inspections were performed in each steam generator:
- Steam drum visual inspections to evaluate the cleanliness and structural condition of all accessible subcomponents including moisture separators, drain systems, and interior surfaces.
- Drop down examinations through the primary separators to assess the cleanliness and structural condition of the upper tube bundle and AVB supports.
- Visual inspections of J-nozzle to feedring internal interface for flow assisted corrosion in the carbon steel portions of the feed rings.
- Visual inspections of upper tube support plates via ]1h TSP handholes to assess structural condition and cleanliness, including that of TSP wedges and associated welds.
- Ultrasonic thickness measurement of selected feed ring locations.
The results of all secondary-side visual examinations performed were satisfactory.
- b. Degradation mechanisms found Tube Support Plate (TSP) wear was the only tube degradation mechanism reported during this inspection.
- c. Nondestructive examination techniques utilized for each degradation mechanism Table 2 identifies the examination technique used for the identified degradation mechanism.
Table 2 - Degradation Mechanisms and Inspection Techniques Degradation Classification Location Probe Type Mechanism Detection - Bobbin Existing Wear Tube Support Plate (TSP)
Sizing - +Point'
- d. Location, orientation (if linear), and measured sizes . (if available) of service induced indications As stated in the (b) response above, service induced indications were identified. Table 3 below provides the required information.
Table 3 - Tube Degradation Summary Max In-Situ Plugging SG Row Col Location ETSS Depth Testing Required?
(%TW) Required?
A No degradation detected during 2R26 03C -0.75 B 1 19 96910.1 12 No No to +0.18 03C-0.71 96910.1 8 No No to -0.17 05C -0.82 B 2 56 96910.1 9 No No to -0.32 05C-0.80 96910.1 8 No No to -0.27 05C-0.84 B 2 58 96910.1 6 No No to -0.41 05C-0.43 B 3 15 96910.1 12 No No to +0.33 05C-0.88 B 22 86 96910.1 8 No No to -0.44 C 2 13 02C -0.31 96910.1 8 No No C 2 93 03C +0.43 96910.1 5 No No
.. * ' .I 05C -0.60 96910.1 5 No No C 7 97 05C +0.34 96910.1 9 No No C 9 97 05C -0.61 96910.1 6 No No
- e. Number of tubes plugged during the inspection outage for each active degradation mechanism No tubes were plugged during this inspection.
- f. The number and percentage of tubes plugged to date, and the effective plugging percentage in each steam generator, Table 4 summarizes the current tube plugging status for North Anna Unit 2 steam generators.
Table 4 - Current Tube Plugging Status
... . ,.N.u.mb.er.of. :_: .
Steam-G~nerat6r
- * . Phigge.c;I T~be$ . .,._
_ P~r~ent P.iug.ged)'*:<
,. * . , : . :, ***.L ~-
A 1 0.03%
8 0 0.00%
C 7 0.19%
Total 8 0.07%
Since no sleeving has been performed in the North Anna Unit 2 SGs, the effective plugging percentage is the same as the actual plugging percentage.
- g. The results of condition monitoring, including the results of tube pulls and in-situ testing No tubes were pulled and no in-situ pressure tests were performed. The condition monitoring assessment concluded that the structural integrity, operational leakage, and accident-induced leakage performance criteria were not exceeded during the operating interval preceding 2R26.